1975

1975 Malvern Road
Malvern East
Builder:First Construction
Project Manager:Skyward Management
Anticipated Completion Date:October 2021
Anticipated Settlement:November 2021

Project Update

July 2021

Dear Purchasers

We are pleased to provide the progress achieved on-site to date for 1975 Malvern East.

  •  External cladding: 90% completed
  • Stair installation completed
  • Internal plastering have commenced
  • Civil works for utilities to commence

We anticipate project completion to be achieved by October/November 2021. Settlement is anticipated to be around November or December 2021.

Please note as always timings are always anticipated and an exact settlement date will not be known until the Plan of Subdivision has been registered with the Titles Office and the Certificate of Occupancy achieved, and settlement is called. However, please rest assured that we are doing everything we can to deliver the project to you as soon as we can.

It is recommended to commence the finance process if you require one. Please do not underestimate the amount of time required to complete the finance process to ensure you are organized for a smooth and timely settlement.

We are pleased to attached photos taken from the site, showing the progress of the works to date.

We shall keep you updated on progress in the coming months and look forward to sharing regular updates on your future home at each milestone reached.

Skyward Management
Contact Charles Lou
Mobile 0431 786 862
Email cluo@skywardmanagement.com.au

+ View More

71 Station Street

71-73 Station Street
Fairfield
Builder:Halecorp
Project Manager:Codicote
Anticipated Completion Date:Q1 2022
Anticipated Settlement:Q1 2022

Project Update

June, 2021

The retaining wall part has been finished,  concreting part of the bottom car park basement has commenced and the civil will commence soon.

Construction continues to progress well.

At this stage we are advised the developers are targeting Q1 2022 for completion.

Updated photos attached.

Further updates to come in due course from the developer.

+ View More

835

835 High Street
Armadale
Builder:Flux
Project Manager:TBC
Anticipated Completion Date:Q2 2022
Anticipated Settlement:Q2 2022

Project Update

July, 2021

We are pleased to announce the structure of 835 High is complete!

Flux have been keeping busy, despite the several Covid disruptions we have all experienced.  We are currently tracking ahead of the contract construction program and look forward to the tower crane beginning its decent in the coming months. The crane is currently lifting the large doubled glazed, full height windows into place on levels 1 & 2. These feature large scale windows weigh in at 450kg and take 9 people to physically install!

Plastering is complete on Level 1 and pre-plaster works have commenced on Levels 2 and 3. Levels 4 and 5 are well underway with rough in (Electrical, Mechanical, Hydraulic etc.) and expect to be sheeted with plaster over the coming month. The views from level 1 upwards are exceptional and even better than we anticipated.

Looking two months ahead we can expect the project to be at “lock up stage” meaning all windows are in and the building is essentially sealed.  The joinery team from Trendgosa have begun fabricating joinery for level 1 and are looking to begin joinery install in the next fortnight.

Everything on site is going very well and we look forward to bringing you the next update in a couple of months where the building will begin to look like a high end, luxury apartment building.

We have had a very productive start to the project and are eager to maintain this efficiency moving into the second half of 2021.

Please see below images for more “insite”.

+ View More

Aintree Park

1432-1436 Malvern Rd
Glen Iris
Builder:Samssons Projects
Project Manager:N/A
Anticipated Completion Date:July 2021
Anticipated Settlement:August 2021

Project Update

July, 2021

Samssons Projects are happy to advise that the project at 1432-1436 Malvern Road Glen Iris is nearing completion
and settlement is anticipated for Mid August 2021.

A confirmed date will be provided once the titles are registered.

At this time we welcome you to book the following inspections

– Valuer Inspections from Monday 19th July
– Purchaser Inspections from Friday 30th July

All bookings must be requested and confirmed via email to the below contact person.

Contact for Inspection – Feras Saad-Eddin – feras@samssons.com.au

Please also copy in Marshall White Real Estate on the below email address
Larissa.Rael@marshallwhite.com.au

+ View More

Alma Village

244-246 Alma Road
Caulfield North
Builder:TBC
Project Manager:TBC
Anticipated Completion Date:Early 2023
Anticipated Settlement:Early 2023

Project Update

June, 2021

We are currently in the sales and marketing phase.

Whilst sales are occurring the development team is in discussions with builders and banks to bring Alma Village to life.

Construction updates will be provided quarterly.

Arcade

393 Burwood Road
Hawthorn
Builder:TBC
Project Manager:First Urban
Anticipated Completion Date:Late 2022
Anticipated Settlement:Late 2022

Project Update

June, 2021

We are currently in the sales and marketing phase.

Whilst sales are occurring the development team is in discussions with builders and banks to bring Arcade to life.

Construction updates will be provided quarterly.

+ View More

Ascot Place

9 Newsom Street
Ascot Vale
Builder:Creation Homes
Project Manager:TBC
Anticipated Completion Date:2023
Anticipated Settlement:2023

Project Update

June, 2021

We are currently in the sales and marketing phase.

Whilst sales are occurring the development team is in discussions with builders and banks to bring Ascot Place to life.

Construction updates will be provided quarterly.

+ View More

Balwyn Park

7 Cherry Road
Balwyn
Builder:Cobild
Project Manager:M2mg
Anticipated Completion Date:October 2021
Anticipated Settlement:October 2021

Project Update

June, 2021

We have outlined below the current status of the project at 7 Cherry Rd Balwyn.

We are installing joinery to the Ground Floor and are commencing tiling to the wet areas.
The plaster works have been completed on Ground and Level 1, and is approximately 75% complete
to Level 2.

The project is still on track for Mid October settlements. M2 will provide you with a firm date once we
are closer to the end of the project.

+ View More

Bloom

1240 Glen Huntly Road
Carnegie
Builder:Nantong Construction
Project Manager:Conrock
Anticipated Completion Date:TBA
Anticipated Settlement:TBA

Project Update

July, 2021

We are pleased to pass on an update for Bloom; 1240 Glen Huntly Road, Carnegie. We are advised that construction has continued over the past few months well and the builders advise that they are pushing and are hoping to be close to completion. That is what site is telling me. Minter Ellison will be managing Settlement and will be in touch with purchasers in due course. Further photos and any updates to be provided from the developer as they progress.

For those who require additional information, the builder (Sam) or Aaron is available on site to assist with most queries.

As previously advised we have ceased involvement with the Bloom development, with the exception of updates on our construction portal which we will continue to share with you here on the portal.

 

+ View More

Boston

16 Boston Road
Balwyn
Builder:S&K Group
Project Manager:M2 Management Group
Anticipated Completion Date:Q4 2022
Anticipated Settlement:Q4 2022

Project Update

June, 2021

We are proud to provide you with an update on your upcoming new residence.

Demolition has been completed and we have now appointed a builder.

On site works are scheduled to commence in July, which will be the foundation works.

Anticipated practical completion is quarter four of 2022.

+ View More

Botanica

488 Barkers Road
Hawthorn East
Builder:Austland Build
Project Manager:TBC
Anticipated Completion Date:Late 2022
Anticipated Settlement:Late 2022

Project Update

June, 2021

We are pleased to announce Botanica has sold out. Construction will start in August, pending to current tenant moving out and finalising construction documentations

The Developer has advised that a builder has been appointed, Austland Build, please see the link to check out their completed and in progress projects

www.austlandbuild.com.au

+ View More

Broadway

630 Glen Huntly Road
Caulfield South
Builder:Holm Park
Project Manager:INPG
Anticipated Completion Date:Late 2021
Anticipated Settlement:Late 2021

Project Update

June, 2021

Demolition has now commenced at Broadway.

Please continue to check on this page for further updates and photos

Carrington Hill

101 Carrington Road
Box Hill
Builder:D5
Project Manager:BHC Property
Anticipated Completion Date:Nov 2021
Anticipated Settlement:Dec 2021

Project Update

June, 2021

We are pleased to provide a construction update for the Carrington Project.

For Building C, we have external cladding and brickwork completed, electrical/ plumbing and Mechanical roughing completed. Garage doors have been installed. The timber floor is also completed.

Building B external cladding and windows are almost complete. Insulation and plastering works are almost completed. Waterproofing and Painting are in progress.

Building A has roof plumbing installed, insulation and plastering works have commenced, external cladding and windows are in progress.

We have appointed a settlement agency to assist with the settlement coordination for your upcoming valuations and inspections of your property. We anticipate construction completion in October / November 2021, and the settlements would take place around November / December 2021. These dates are expected to change due to the uncertainty of Covid-19 lockdown. However, please rest assured that we are doing everything we can deliver the project to you as fast as we can.

 

+ View More

Cascade

40 & 40a Whitehorse Road
Blackburn
Builder:Goldnest Construction
Project Manager:Skyward Management
Anticipated Completion Date:Late 2022
Anticipated Settlement:Late 2022

Project Update

June, 2021

We are pleased to advise you that the demolition works are progressing well and are due to complete soon.

We have secured Goldnest Construction as the project builder, they have completed several projects similar in size and are more than capable to deliver this project in a timely manner. We will be preparing the construction contract for signing and building permit in the coming weeks.

+ View More

Chapel Park

220 Chapel Road
Keysborough
Builder:TBC
Project Manager:TBC
Anticipated Completion Date:Early 2023
Anticipated Settlement:Early 2023

Project Update

July, 2021

The developer has advised they’re currently in the tendering stage for a builder. The closing date is the end of August.

Once a builder is appointed a further construction update will follow.

Chevron One

38 Stanhill Drive
Surfers Paradise
Builder:Hutchinson Builders
Project Manager:TBC
Anticipated Completion Date:June 2023
Anticipated Settlement:June 2023

Project Update

June, 2021

We are pleased to announce the following Chevron One Residences;

– underground cabling works are now complete

– the on-site display suite will soon be moved to a new location ready for excavation works to commence.

 

+ View More

Contour

250 Wattletree Road
Malvern
Builder:Ironside
Project Manager:First Urban
Anticipated Completion Date:July 2022
Anticipated Settlement:August 2022

Project Update

July, 2021

Dear Purchaser

The design team are pleased to announce that Ironside are the appointed builders of Contour. With Ironside having worked collaboratively before with Ascui & Co and Marshall White Projects, we expect a seamless transition from an August commencement to an anticipated July – August 2022 completion. More to follow soon

Further update and site pics to come in due course from the developers.

+ View More

Custom

20 Station Street
Highett
Builder:Balmain & Co
Project Manager:M2 Management Group
Anticipated Completion Date:August 2022
Anticipated Settlement:August 2022

Project Update

July, 2021

We are pleased to share that construction is progressing well on site with builder Balmain & Co completing the piling in the first week of July, finishing up ahead of schedule.

Capping beam works have commenced, along with the construction of the retaining walls along the South and Southeast perimeter of the site. The hoarding installation is due to begin in the coming weeks, along with the first shotcrete spray.

+ View More

Daracombe

369-371 Cotham Rd
Kew
Builder:Pulitano Commercial Construction
Project Manager:N/A
Anticipated Completion Date:March 2022
Anticipated Settlement:March 2022

Project Update

June, 2021

We are pleased to pass on that the builder has been appointed for Daracombe. Pulitano Commercial Construction will build your new homes.

The builders have advised that they have started pilling, the anticipated Project completion will be March 2022 at this stage.

Further news and construction updates to come from the developer in due course.

 

+ View More

East Village Prahran

283-289 High Street
Prahran
Builder:Method Constructions
Project Manager:Prince Corporation
Anticipated Completion Date:October 2021
Anticipated Settlement:October 2021

Project Update

June, 2021

Construction has had some delays in construction due to some suppliers and manufacturers that were affected by the pandemic.

At this stage completion is expected late October 2021.

The directors at Method Constructions are still confident that we will be able to make up some time, particularly by engaging mainly local manufacturers that are less reliant on shipping and border restrictions.

All basement retention works have been completed including piling and anchoring, the bulk excavation down to the bottom of the second basement has been completed and, the concrete has been poured for the lift core, and crane base.

Currently the civil and drainage works of the lower basement are being done, as seen in the attached photo.

 

+ View More

Gardenia Park

8 Genista Avenue
Boronia
Builder:Batbuild
Project Manager:Skyward Management
Anticipated Completion Date:July 2021
Anticipated Settlement:August 2021

Project Update

June, 2021

We are pleased to provide the progress achieved on-site to date for Gardenia Park.
– Concrete driveway and crossovers completed
– External landscape works is 80% completed
– Carpet and appliance installation is to commence soon
– Final fixings and touch ups for internals underway

We are due to organise council inspection for Statement of Compliance once the landscape works is close to completion.

After SoC has been received, we can then lodge for the Plan of Subdivision.
We anticipate settlement to take place sometime early Aug 2021.

Please note timings are always anticipated and an exact settlement date will not be known until the Plan of Subdivision has been registered with the Titles Office and the Certificate of Occupancy achieved.

Developer’s solicitors will provide 2 weeks’ notice in advance for the settlement date.

Skyward Management
Contact Charles Lou
Mobile 0431 786 862
Email cluo@skywardmanagement.com.au

+ View More

Glenarm Square

1 Glenarm Road
Glen Iris
Builder:Hamilton Marino
Project Manager:N/A
Anticipated Completion Date:May 2022
Anticipated Settlement:May 2022

Project Update

July, 2021

Builder Hamilton Marino continues to make good progress onsite with the ground floor slab to be complete at the end of this month. Following this milestone the building structure will be visible coming out of the ground in the coming months.

DealCorp are currently working through the final communal amenity details and furniture selection with the interior and architecture teams.

Sales continue to progress well with strong interest and enquiry levels despite the recent Melbourne lockdowns.

Construction completion remains on track for mid 2022.

We look forward to keeping you up to date as key construction milestones are met.

Should you have any queries in the interim, please contact our sales manager:

Brett Hallam
0418 318 283
bhallam@dealcorp.com.au

Please also inform our settlement administrator if any of yours or your solicitor’s contact details change:

Madeleine Williams
mwilliams@dealcorp.com.au

 

+ View More

Greenwell

597 Burke Road
Camberwell
Builder:Creation Homes
Project Manager:Pomeroy Pacific
Anticipated Completion Date:September 2021
Anticipated Settlement:September/October 2021

Project Update

July, 2021

We are pleased to pass on the following update from the developer below:

  • Commenced painting
  • Installed garage doors
  • Continued with tiling
  • Completed walkway planter boxes
  • Complete all underground stormwater
  • Commencing fit off next week

Further updates to come in due course.

 

+ View More

Hazel Hawthorn

368 Auburn Road
Hawthorn
Builder:Quadrant
Project Manager:TBA
Anticipated Completion Date:Mid 2022
Anticipated Settlement:Mid 2022

Project Update

June, 2021

We have the main water tapping happening on the 8th June.

Slab pour to the back half of the ground floor slab anticipated for 10th June.

Basement drainage should be completed by 13th June.

Remaining footings in basement to be dug and poured week commencing 14th June.

+ View More

Highmont

3 James Street
Bayswater
Builder:D5 Building Group
Project Manager:Skyward Management
Anticipated Completion Date:Mid 2022
Anticipated Settlement:Mid 2022

Project Update

June, 2021

The Developer has advised that a builder has been appointed,  D5 Building Group, please click link and check out their completed and in progress projects.

Demolition has now commenced. Further updates to be provided by the developer in due course.

 

Skyward Management
Contact Charles Lou
Mobile 0431 786 862
Email cluo@skywardmanagement.com.au

 

+ View More

Hotham & Carlisle

99 Hotham Street
Balaclava
Builder:Paragon Development Group
Project Manager:Paragon Development Group
Anticipated Completion Date:September 2021
Anticipated Settlement:September 2021

Project Update

June, 2021

Joinery & marble have been installed to the Northern facing units. All cladding and screens to the northern facing units are now complete. The Car stacker structure is also complete.

Framing in the existing building and around the car stacker is underway. Feature curved cladding to start in the coming weeks.

Progress is continuing at a promising rate on site at 99 Hotham Street. Completion remains on track for September 2021.

Further updates to come from the developer in due course.

+ View More

Hurstmon

3 Hurstmon Street
Malvern East
Builder:Kapitol Group
Project Manager:Codicote
Anticipated Completion Date:Late 2022
Anticipated Settlement:Late 2022

Project Update

June, 2021

Following a competitive construction tender, developer Landream in collaboration with project managers Codicote have today announced that high-end residential builders, Kapitol Group, have been awarded the $17 million plus construction contract to deliver Hurstmon, Malvern East. Construction due to commence in July.

“Landream always strives to engage local professionals where possible across our portfolio of projects and Hurstmon was no exception,” comments Mitchell Crawford, Senior Development Manager of Landream.

The project is set to generate work for over 450 local contractors during the construction program, along with a construction loan facility provided by Bank of Melbourne.

Kapitol Group is the builder behind Sarah Sands, a bespoke development comprising of 31 apartments on Sydney Road in Brunswick; the Church Missionary Society of Australia’s redevelopment at St Andrew’s Hall in Parkville; and also has construction underway for 20 premium apartments at Bedford Street in Collingwood.

Emphasis has been placed on the delivery and installation of the unique vertical rammed earth columns that line the front and west façade of the building.

“Rammed earth columns sit proudly on the façade of Hurstmon paying homage to the earthy tones of the site’s surrounds and defining each residence, allowing residents to have a clear sense of their home,” comments Tim Clarke, Director of Telha Clarke.

This enables the building to meld seamlessly into the local streetscape, which is filled with the abundant native greenery that Malvern East is known for.

“Traditionally only starring in luxury homes, museums, art galleries and wineries due to its bespoke nature; Hurstmon is one of the only residential developments in Victoria to feature this beautiful and sustainable natural building finish,” comments Mitchell.

In keeping with the theme of supporting local, the earth for the columns will be sourced and manufactured in the Victorian High Country through a family run business called Earth Structures, carefully selected by Landream due to their high level of expertise.

Earth Structures are responsible for many of the buildings in Victoria that feature rammed earth including the renowned Tarrawarra Museum of Art located at the Tarrawarra Estate winery in the Yarra Valley.

Hurstmon is scheduled for completion by end of 2022.

+ View More

Iramoo

7 Iramoo Street
Balwyn
Builder:Austland Build
Project Manager:TBC
Anticipated Completion Date:Mid 2022
Anticipated Settlement:Mid 2022

Project Update

June, 2021

Construction has now commenced at Iramoo.

The Developer has advised that a builder has been appointed, Austland Build, please see the link to check out their completed and in progress projects

www.austlandbuild.com.au

Luar

22-24 Pakington Street
St Kilda
Builder:Drakk Constructions
Project Manager:David Parsons
Anticipated Completion Date:October 2021
Anticipated Settlement:October 2021

Project Update

June, 2021

I am pleased to say we are still on track in accordance with the previous advice, i.e. there have been no delay events of any kind.

Completion of the building

• As the building reaches ‘Practical Completion’ (the stage when it can be occupied but for minor defects which can be rectified after occupancy) we will undertake defects inspections with purchasers so that they will have an opportunity to have any minor items rectified
• At around about the same time, the building surveyor (who issues building permits) will issue a Certificate of Occupancy
• Defects will then be rectified

Issue of titles

• In order to have the new titles issued, we need to obtain Statements of Compliance from service authorities such as electricity, water, drainage, sewer, NBN etc as well as council. This process obviously relies on timely responses from authorities which is outside of our control and can be variable
• This statement must be provided to the Titles office which will then issue titles.

As to timing, we are looking at:

• Practical Completion: late August, early September
• Defect rectification, final clean etc: by late September
• Compliance: Early September to early October
• Settlements: early to mid October.

+ View More

Luminess

27 Russell Street
Essendon
Builder:Drakk (Vic) Pty Ltd
Project Manager:J2
Anticipated Completion Date:October 2022
Anticipated Settlement:October 2022

Project Update

June, 2021

Please see below a summary of construction progress for May 2021;

  • Basement excavation is near completion with 3rd basement drop (Sth side) expected to be completed mid-end June.
  • Shotcrete walls have been detailed for basement 1 & 2
  • Steel bracing has been installed
  • Upper temporary props have been installed.

Should you have any further concerns, you can contact Lee, Development manager on lee@urbanpropertyfinance.com.au or call 0418 555 265

+ View More

Melfort

496 Glenferrie Road
Hawthorn
Builder:Pulitano Commercial Construction
Project Manager:HS Consortium
Anticipated Completion Date:December 2021
Anticipated Settlement:December 2021

Project Update

June, 2021

We are pleased to pass on the following update from the developer:

The roof will be installed the week commencing the 14th of June and progress continues well onsite.

Construction is on track for completion in December 2021.

Further update to come from the developer in due course.

+ View More

Myrtle

203 Canterbury Road
Blackburn
Builder:TBC
Project Manager:TBC
Anticipated Completion Date:TBC
Anticipated Settlement:TBC

Project Update

July, 2021

We are currently in the sales and marketing phase.

Whilst sales are occurring the development team is in discussions with builders and banks to bring Myrtle to life.

Construction updates will be provided quarterly.

Olea

50 Kambrook Road
Caulfield North
Builder:Balmain & Co
Project Manager:BNG Group
Anticipated Completion Date:Late 2021
Anticipated Settlement:Late 2021

Project Update

June, 2021

We are pleased to pass on the following update from the OLEA group:

The building structure has continues to progress well as concrete pours have advanced from the basement to level 3.
The installation of precast and the wall framing system on ground floor through to level 2 have commenced. Services installation in the basement has also begun and will continue into next month along with the structure as it progresses towards top-out
Please see latest photos attached.

In the interim, we invite you to communicate BNG group on 1300 853 761 and ask to speak to Dina or email: Oleasales@bng.group for additional information.

For your journey Tom Hawkins will be your settlement co-ordinator. You can contact Tom on 03 8582 8972 or email to tom@settlement-solutions.com.au

+ View More

Parq

134-138 McKinnon Road
McKinnon
Builder:Fynnan Construction
Project Manager:Oxford Developments
Anticipated Completion Date:Qtr 1 2022
Anticipated Settlement:Qtr 1 2022

Project Update

June 2021

Let me start by saying thank you for bearing with us through the unforeseen delays last year.

I can understand your frustration driving past the site as it looks like there has been no progress in recent months.

In actual fact we have been working flat out with our basement construction, the complexity of this basement construction has given the illusion we are building slower than the other apartment buildings in the area.

I am delighted to tell you, we are in the final stages of our basement and you will start seeing concrete and steel come out of the ground very shortly.

Please see the image of the basement below, hopefully it gives you some insight as to how intricate this stage of the construction has been.

+ View More

Profile

1443 Dandenong Rd
Malvern East
Builder:Goldfields
Project Manager:M2
Anticipated Completion Date:September 2021
Anticipated Settlement:September 2021

Project Update

June, 2021

We are pleased to pass on the following update from the builder:

  • Stone benchtops all floors, all wet area tiles completed
  • Painting L2&3 ceilings
  • Common area lining
  • Basement ductwork
  • Cover L2 blueboard
  • External Render in progress
  • Joinery all floors
  • Plumber fit-off GF
  • Lift core cladding in progress
The majority of works have been completed for the interior and we are now progressing with cladding for the external facade. We look to finalize the majority of external work by end of this month. Due to covid lockdown, we have faced some delays from authorities as they have transitioned to working from home- we will continue to monitor if this will have any effect on the completion program. We are committed to delivering an outstanding project and appreciate the support of all our purchasers.

We are advised that the developer is anticipating September 2021 Practical Completion.

UPS Settlement firm for settlement liaison.
Amanda
amanda@upssettlement.com.au
0413 115 380
+ View More

Rose & Bird

30 Rosamond Rd
Maribyrnong
Builder:Creation Homes
Project Manager:Metro Property Management
Anticipated Completion Date:October 2021
Anticipated Settlement:October 2021

Project Update

June, 2021

Construction continues on site, and the team at Metro Property Development expect homes to be completed September 2021.

We will introduce you to our settlements team over the coming months who will take you through the settlement process and provide you with all the necessary information required to take possession of your new home.

Please contact Settlement Solutions for any valuation and purchaser inspections –

Tania Torres | Senior Settlement Coordinator

Property Settlement Solutions

P: +61 3 8582 8973  m:0400 332 306

E: tania@settlement-solutions.com.au

W: www.settlement-solutions.com.au

+ View More

Soligo

487 Whitehorse Road
Balwyn
Builder:Princi Property
Project Manager:TBC
Anticipated Completion Date:TBC
Anticipated Settlement:TBC

Project Update

June, 2021

We are currently in the sales and marketing phase.

Whilst sales are occurring the development team is in discussions with builders and banks to bring Soligo to life.

Construction updates will be provided quarterly.

Builder
Princi Property
Enquires@Princi.Property

+ View More

Tailor

481-491 Victoria Street
West Melbourne
Builder:Manresa Constructions
Project Manager:TBA
Anticipated Completion Date:August 2021
Anticipated Settlement:August 2021

Project Update

June, 2021

We are on track to finish at Tailor Residences around early August with settlements expected to be late August, all going to plan. The recent lockdown caused some delays on site re covid restrictions but those restrictions were lifted Friday.

The scaffolding has been removed from the front of the building so the front facade can be seen from the street. Floorboards are down (with protective covering), the kitchens are in with the stone benchtops currently being installed.

+ View More

Ten to Twelve

10-12 Lindsay Street
Brighton
Builder:Cobild
Project Manager:Hub Property Group
Anticipated Completion Date:Early 2022
Anticipated Settlement:Early 2022

Project Update

June, 2021

Progress at Ten to Twelve is going exceptionally well!

Plumbing and electrical rough in works to the ground floor apartments are 80% complete and mechanical rough in works are schedulled in for this week.

Cobild have commenced hanging the fire rated plasterboard, dividing the apartments to the corridor and making the building take shape.

This week Cobild will rough in all apartment fronts and begin waterproofing balconies.

We are excited and look forward to bringing you more updates as the project progresses!

If you have any questions please don’t hesitate to get in touch with Daniel Sergious at daniel@hubpg.com.au.

+ View More

The Avenue

15 Landale Avenue
Croydon
Builder:First Construction
Project Manager:BHC Property
Anticipated Completion Date:Qtr 3 2022
Anticipated Settlement:Qtr 3 2022

Project Update

July, 2021

The following is the progress of the works to date:

–          Concrete slab is completed

–          Brickworks has been delivered on site. To commence after framing.

–          Structural steel framing is anticipated to be installed soon

–          Light gauge steel to come after

There has been a delay with the steel framing due to increased demand.

Construction completion is currently anticipated to be by Quarter 3 of 2022.

+ View More

Timeless

555 Burke Road
Camberwell
Builder:Balmain & Co
Project Manager:J2 Projects
Anticipated Completion Date:May 2022
Anticipated Settlement:May 2022

Project Update

June, 2021

The builder Balmain & Co. are happy to report the following has now been completed;

  • Bulk excavation complete
  • Crane has been constructed
  • About to pour the basement concrete slab

We will provide further updates and news to come in due course from the developer.

+ View More

Two Eighty Waverley

280 Waverley Road
Malvern East
Builder:TBC
Project Manager:Shustin
Anticipated Completion Date:Late 2022
Anticipated Settlement:Late 2022

Project Update

July, 2021

We are currently in the sales and marketing phase.

Whilst sales are occurring the development team is in discussions with builders and banks to bring Walmer to life.

Construction updates will be provided quarterly.

Verse

18 -28 Wilkinson Road
Sunshine
Builder:Rise Constructions
Project Manager:Paragon Development Group
Anticipated Completion Date:September 2021
Anticipated Settlement:September 2021

Project Update

July, 2021

The northern block of townhouses are all tiled and joinery installed. Final coats of painting will be applied over the next few weeks.

The southern block of townhouses are being tiled with the majority of all joinery installed.

The mid-block is have all their services roughed in. Internal staircases and plastering to start shortly.

Eastern block are having their services roughed in. Internal staircases and plastering to start shortly.

Settlement Liason

Butterfield conveyancing

Max  9899 8028

+ View More

Walmer

649 Victoria Street
Abbotsford
Builder:Hamilton Marino
Project Manager:TBC
Anticipated Completion Date:Qtr 4 2022
Anticipated Settlement:Qtr 4 2022

Project Update

June, 2021

We are pleased to announce that the next stage of construction has commenced at Walmer.

Having craned in the excavators, the site is being cleared for basement construction this week – a total project completion date forecast for late 2022.

We look forward to keeping you updated on key milestones and progress in the months to come and invite you to discover more about Melbourne’s most exciting riverside development.

Construction updates will be provided quarterly.

+ View More

Wattle on the Park

2 Wattle Grove
McKinnon
Builder:Fynnan Constructions
Project Manager:KBMV
Anticipated Completion Date:Late 2021
Anticipated Settlement:Late 2021

Project Update

July, 2021

As of 5th July progressing with the building works towards the targeted completion date. Structural Steel works and frame being erected with great skill by the carpenters, windows have been delivered onsite and installed as the frame progresses.

Units 1 &2 internal stairs have been installed allowing for quicker access for the trades. Brick work has commenced in earnest and will continue over the next few weeks. Overall we are expecting major push in the works as the plumbers and electricians will commence rough-in of the services and the electrical pre-wire.

 

 

 

+ View More

For further enquiry or any issues, please contact:

Address: 1111 High Street Armadale VIC 3143
Email : georgie.lupson@marshallwhite.com.au
Phone : 03 9832 1197

X

X

Register for instant email alerts when a property matches your criteria.