1975

1975 Malvern Road
Malvern East
Builder:First Construction
Project Manager:Skyward Management
Anticipated Completion Date:November 2021
Anticipated Settlement:November/December 2021

Project Update

October, 2021

We are pleased to advise the progress achieved on-site for 1975.

Construction is on track to be completed by the end of next week.

Council completed their inspection yesterday and now we are waiting for the Statement of Compliance to be issued.

Once this is issued, then we can lodge for the Titles, which can take up to 3 weeks.

Our solicitor will advise all purchasers’ solicitors once the Title has been lodged.

After new titles are received, 2 weeks notice in advance will be provided for settlement. Our solicitor will then advise the exact date for settlement. We anticipate this to be around late November to early December.

Please make sure your finance application is well underway by now.

The pre-settlement inspection is anticipated to take place in 2 weeks time. Our settlement agent will arrange a booking time.

Skyward Management
Contact Charles Lou
Mobile 0431 786 862
Email cluo@skywardmanagement.com.au

+ View More

835

835 High Street
Armadale
Builder:Flux
Project Manager:TBC
Anticipated Completion Date:Q2 2022
Anticipated Settlement:Q2 2022

Project Update

November, 2021

Despite the various roadblocks endured due to the restrictions in place over the past 4 months, we are pleased to announce construction progress is back to 100% and our builders are roaring back into it.

If you have had the opportunity to drive past site of late, you will have noticed the scaffold to the South has been dismantled and the beautiful façade has been unveiled. Carr have worked tirelessly with Flux ensuring every millimetre of the façade has been signed off before the scaffold came down.

What has been happening on site over the past few months?

  • The tower crane has been completely dismantled and transported off site
  • Scaffolding to the South and West facade has been dismantled
  • All glazing to residential apartments has been installed
  • Bathrooms to levels 1,2 & 3 have been tiled and ready for fit off
  • Levels 1,2 & 3 have all been sheeted with plaster and the ceiling sheets for level 4 were installed Oct 15th.
  • Kitchen joinery and stone to levels 1,2 & 3 has been installed
  • Kitchen appliances have been installed and commissioned to levels 1,2 & 3
  • Basecoat painting has commenced on Levels 1 & 2

Providing we don’t experience another industry shutdown or reduced capacity on site, Flux anticipates achieving PC (practical completion) in early to mid 2022.

We hope you and your families have been keeping well despite the crazy times we’ve all endured and look forward to sending the next update with apartments nearing completion.

Please see below images showing construction progress.

+ View More

88 Leveson

88 Leveson Street
North Melbourne
Builder:TBC
Project Manager:TBC
Anticipated Completion Date:Early 2023
Anticipated Settlement:Early 2023

Project Update

November, 2021

We are currently in the sales and marketing phase.

Whilst sales are occurring the development team is in discussions with builders and banks to bring 88 Leveson to life.

Construction updates will be provided quarterly.

Alma Village

244-246 Alma Road
Caulfield North
Builder:TBC
Project Manager:TBC
Anticipated Completion Date:Early 2023
Anticipated Settlement:Early 2023

Project Update

December, 2021

The end of restrictions could not have come soon enough for our industry, and we are thrilled to finally be able to commence our project delivery journey.

Despite many challenges posed by the pandemic, we have been working with our architects, engineers and other trusted project partners to finalise the plans and construction program.

Our aim is to commence demolition before the end of the year with construction to start early next year.

We will keep you posted regarding the progress on a regular basis and are excited to see this development take shape.

+ View More

Arcade

393 Burwood Road
Hawthorn
Builder:TBC
Project Manager:First Urban
Anticipated Completion Date:Late 2022
Anticipated Settlement:Late 2022

Project Update

November, 2021

We are currently in the sales and marketing phase.

Whilst sales are occurring the development team is in discussions with builders and banks to bring Arcade to life.

Construction updates will be provided quarterly.

Ascot Place

9 Newsom Street
Ascot Vale
Builder:Creation Homes
Project Manager:TBC
Anticipated Completion Date:2023
Anticipated Settlement:2023

Project Update

November, 2021

Civil works are progressing well at Ascot Place with lot benching now complete and below ground services installation nearing completion. Road pavement and kerb works will take place in later this year / early 2022.

Housing construction works are on track for commencement in December 2021 with the homes expected to be ready for settlement progressively from late 2022 to early 2023.

As you would appreciate, our construction program and expected settlement dates may be impacted by future work restrictions; however we will endeavour to keep you updated as construction progresses.

If you have any queries regarding the project, please continue to direct them to Larissa at Marshall White by email to larissa.rael@marshallwhite.com.au.

+ View More

Balwyn Park

7 Cherry Road
Balwyn
Builder:Cobild
Project Manager:M2 Management Group
Anticipated Completion Date:December 2021
Anticipated Settlement:December 2021

Project Update

December, 2021

Progress onsite has been at a furious pace now that we are able to get back to 100% capacity of workers onsite.

  • The external landscaping is being finalised, with major and minor planting complete with minor grasses still to be put in place and feature
  • Internal Joinery is all but complete and installed
  • Feature Lighting and finishes are being finalised
  • Feature entry Doors are installed.
  • Lobby Areas have been tiled with features inserts still to be completed.
  • First clean has occurred to ground and first floor apartments.

We are anticipating that the titles will be Received and Occupancy permit in the first week of December

Contact for settlement enquiries
Amanda Wang
UPS
email: amanda@upssettlement.com.au
Mobile: 0413 115 380
Tele: 9818 2488

+ View More

Bloom

1240 Glen Huntly Road
Carnegie
Builder:Nantong Construction
Project Manager:Conrock
Anticipated Completion Date:TBA
Anticipated Settlement:TBA

Project Update

December, 2021

We have been advised by the vendor that they are progressing with construction onsite and are projected to complete construction within the next three months (subject to lockdowns, restrictions etc).

The vendor has also advised that you can visit the physical site at 1240-1248 Glen Huntly Road, Carnegie and request a site walkaround with the site foreman.

Minter Ellison will be managing settlement and will in touch with purchasers in due course. Further photos and any updates to be provided from the developer as they progress.

As previously advised we have ceased involvement with the Bloom development, with the exception of updates on our construction portal which we will continue to share with you here.

+ View More

Boston

16 Boston Road
Balwyn
Builder:S&K Group
Project Manager:M2 Management Group
Anticipated Completion Date:Q4 2022
Anticipated Settlement:Q4 2022

Project Update

November, 2021

We are proud to provide you with an update on your upcoming new residence.

S&K have completed the Bulk Excavation of the basement, currently the Shotcrete Basement Walls are being sprayed and Basement Plumbing being installed.

The basement slab is intended to be poured in the coming weeks

Anticipated practical completion is quarter four of 2022.

+ View More

Botanica

488 Barkers Road
Hawthorn East
Builder:Austland Build
Project Manager:Austland Build
Anticipated Completion Date:Late 2022
Anticipated Settlement:Late 2022

Project Update

December, 2021

We are pleased to announce the below construction update;

• Existing house has been demolished.

• Building Permits – The final step is in the process, we will be getting the permit by the 1st week of December 2021 to allow the works to commence on site. Building permits contain detailed construction drawings and technical documents so the building works can be constructed in accordance with the building regulations and associated standards.

• Anticipated civil and site preparation works will start by 2nd-3rd week of December 2021.

We will keep you posted regarding the progress on a regular basis and are excited to see this development take shape.

+ View More

Broadway

630 Glen Huntly Road
Caulfield South
Builder:KSM Design and Construct
Project Manager:INPG
Anticipated Completion Date:December 2022
Anticipated Settlement:December 2022

Project Update

October, 2021

The builder has completed the rubbish clean up and top soil site scrape as per the attached photos along with the removal of the existing brick nib wall that was projecting across the boundary into the site.

By the end of the week, a new solid timber front hoarding will be installed together with secure temporary fencing to the rear along the laneway as well as the site survey to re-establish the correct title boundaries and provide setout marks to define the extent of the ground floor slab and structural walls.

We will continue to provide further updates in the coming weeks once firm dates have been agreed and confirmed between the design teams, the consultants, the builder and the developer.

+ View More

Candela

40 Upper Heidelberg Road
Ivanhoe
Builder:TBC
Project Manager:TBC
Anticipated Completion Date:Late 2023
Anticipated Settlement:Late 2023

Project Update

December, 2021

Early works have commenced at Candela with the appointment of a builder imminent.

Stay tuned for another update shortly.

Carrington Hill

101 Carrington Road
Box Hill
Builder:D5
Project Manager:BHC Property
Anticipated Completion Date:December 2021
Anticipated Settlement:December 2021

Project Update

December, 2021

As the restrictions for construction sites are recently lifted, we now have construction completed for Carrington Hill.

Also, we have booked in with the council for a final inspection this week.

A statement of compliance from the council will be issued within 2 weeks after council inspection. This is a critical milestone as it is required for the registration of the new 18 Land Titles.

The Land Titles registration process is subject to Land Title Office processing time and is usually 4 to 6 Weeks.

We are expecting the new Land Titles to be registered by December for purchasers’ settlement to occur.

Please do not hesitate to contact James on 0499 799 771 or email settlement@skywardmanagement.com.au if you have any questions.

+ View More

Cascade

40 & 40a Whitehorse Road
Blackburn
Builder:Goldnest Construction
Project Manager:Skyward Management
Anticipated Completion Date:Late 2022
Anticipated Settlement:Late 2022

Project Update

November, 2021

We are pleased to advise the progress achieved on-site to date for Cascade – Blackburn.

Construction work is on track:

• Site cut completed
• 3 Underground water tanks have been delivered on-site
• Drainage connections and footing reinforcement are underway

We are expecting upcoming concrete pour before Christmas break.

+ View More

Chevron One

38 Stanhill Drive
Surfers Paradise
Builder:Hutchinson Builders
Project Manager:TBC
Anticipated Completion Date:June 2023
Anticipated Settlement:June 2023

Project Update

November, 2021

We are pleased to announce the following works completed at Chevron One Residences;

works have commenced with the team from ICON now occupying the site

– the onsite display suite has been decommissioned ready for demolition to make way for excavation

– a new display suite space is currently being fit out at Bundall Corporate Centre, this will be ready in early November

 

+ View More

Contour

250 Wattletree Road
Malvern
Builder:Ironside
Project Manager:First Urban
Anticipated Completion Date:October/November 2022
Anticipated Settlement:October/November 2022

Project Update

December, 2021

The design team are pleased to announce that Ironside are the appointed builders of Contour.

So far onsite, the pouring of the basement wall is in the final stages. Soon after the pile of earth in the middle of the site will be removed and then the concrete slab at the bottom of the basement will be finished by Christmas.

Further updates and site pictures to come in due course from the developer.

+ View More

Custom

20 Station Street
Highett
Builder:Balmain & Co
Project Manager:M2 Management Group
Anticipated Completion Date:August 2022
Anticipated Settlement:August 2022

Project Update

November, 2021

We are pleased to share that construction is progressing well.

The building’s form continues to rise on site at Custom, Highett as our team progress-es through the structure stage. The level three concrete slab is now complete, along with formwork stripping from the basement up to level three. Services fit out and wall framing has also commenced in the basement and at ground level and will continue through levels one and two throughout November. Civil works within the boundary are currently underway at ground level and due to reach completion later in the month along with completion of the basement ramp.

Watch progress video – https://vimeo.com/644143155

+ View More

Daracombe

7 Daracombe Avenue
Kew
Builder:Pulitano Commercial Construction
Project Manager:N/A
Anticipated Completion Date:Late May 2022
Anticipated Settlement:Late May 2022

Project Update

October, 2021

We are pleased to pass on that the builder has been appointed for Daracombe. Pulitano Commercial Construction will build your new homes.

Unfortunately due to the industry shutdown and only 25% of workers being allowed on site, in accordance with the Government rules, we have experienced delays to the build. Our builder is currently working on providing a new program and completion dates. We will provide these new completion times within the coming weeks.

Further news and construction updates to come from the developer in due course.

 

+ View More

East Village Prahran

283-289 High Street
Prahran
Builder:Method Constructions
Project Manager:Prince Corporation
Anticipated Completion Date:Early 2022
Anticipated Settlement:Early 2022

Project Update

November, 2021

We write to update you on the current construction industry constraints and how this is affecting East Village Prahran.

The Covid work restrictions have significantly affected the construction industry, and like every other non-essential project in Melbourne, we have been impacted.

Progress slowed initially due to the Stage 4 Covid restrictions for building sites, limiting numbers to only 25% capacity of workers on site.

A further blow was yesterday’s announcement by the Victorian Government that construction will shut down in metropolitan Melbourne and other Local Government Areas currently in lockdown for two weeks from 11.59pm, Monday 20 September.

Prior to this announcement, the completion date was expected to be towards the end of November 2021, based on progress whilst working under Stage 4 restrictions.

We had a priority meeting with the Directors of Method Constructions last night, and I want to reassure you that they are working to minimize delays and are still committed to completing the project before the end of the year.

As the situation remains fluid it is very difficult to forecast a completion date with any certainty.  Occupancy Permit and Council Compliance Certification is achieved, a more realistic completion target would be by the end of January 2022.

We apologize for any inconvenience caused, and will pass on any further information as it comes to hand.

We will continue to keep you updated every 2-3 weeks on progress to provide you with enough time to be organised for settlement. We remain available to answer any specific questions you may have.

On a positive note we have received the Terrazzo Tiles from Italy, and the Natural Stone for the kitchens and bathrooms is expected to arrive at the Melbourne Docks this week.

Peter Mitrevski
Managing Director
peter.mitrevski@princecorp.com.au

+ View More

Gladstone Armadale

37 Gladstone Avenue
Armadale
Builder:Figurehead
Project Manager:KIN Property
Anticipated Completion Date:Late 2022
Anticipated Settlement:Late 2022

Project Update

November, 2021

Roulston would like to take this opportunity to formally introduce you to Jackie Zandveld from our Settlement Team who will be your main point of contact as we get closer to the point of project completion and settlement.

For buyers currently liaising with Marshall White regarding purchaser requests and alterations, please continue to deal with your agent directly whilst all final requests are captured over the coming weeks.

Jackie is thrilled to be communicating with you over your settlement journey at Gladstone. Jackie and her team will provide timely updates as the builder achieves construction milestones and keep you informed regarding timing for finance preparations and valuation access as we get closer to completion. We are looking forward to meeting you on site in due course to showcase your apartment at your pre-settlement inspection prior to handing over your keys and settlement pack once you have settled on your new home.

If you have passed by the site in recent weeks, you will have noticed a few important changes. Firstly, the demolition stage of the project is now underway and will continue from October into November. You will also notice a “Builder appointed’ sticker has been added to the property signage! We are pleased to announce that Figurehead has been appointed as the Builder of Gladstone Armadale. This appointment comes off the back of their successful delivery of Roulston’s two recent projects, Central Park and Pelham. Figurehead will formally commence on site later this year and early next year once final permits are in place.

Jackie will be in contact with you over the coming weeks to formally introduce herself, provide further detail on the process ahead and answer any questions you may have. Could we ask that you kindly reply to this email as soon as possible with your preferred contact number and email address for correspondence.
Jackie Zandveld
Settlement Coordinator
T: +61 438 812 800
E: customercare@roulston.com.au

 

+ View More

Glenarm Square

1 Glenarm Road
Glen Iris
Builder:Hamilton Marino
Project Manager:N/A
Anticipated Completion Date:June 2022
Anticipated Settlement:June 2022

Project Update

October, 2021

DealCorp would like to write with a brief update following the return of construction at Glenarm Square.

The industry was shutdown for the two weeks leading to October 5th and we would like to take this opportunity to assure you that builder, Hamilton Marino is revising the program in line with current restrictions and will do their best to make up for time lost and limited personnel onsite.

During early Spring and in recent days, Glenarm Square has achieved a number of significant milestones, including completion of the ground floor slab works, completion of the upper ground floor works, and the commencement of level 2 suspended slab. During the coming weeks, we anticipate the completion of the level 1 transfer slab, which will enable the design sequence to take place on the upper levels. Passing traffic will also notice the commencement of the façade scaffolding.

We are pleased to announce that the project is over 85% sold and we look forward to sharing more milestones as the project progresses.

If you have any queries, please reach out to our sales manager:

Brett Hallam
0418 318 283
bhallam@dealcorp.com.au

Please also inform our settlement administrator if any of yours or your solicitor’s contact details change:

Madeleine Williams
mwilliams@dealcorp.com.au

+ View More

Greenwell

597 Burke Road
Camberwell
Builder:Creation Homes
Project Manager:Pomeroy Pacific
Anticipated Completion Date:December 2021
Anticipated Settlement:December 2021

Project Update

December, 2021

Current works completed on site

• Commenced installing microwaves, ovens and cooktops
• Commenced timber flooring install
• Installed mirrors
• Continued with fit off

Unique Property Settlement (UPS) are pleased to advise that we have been appointed to work with you by the developer in relation to the Settlement services as construction works continue at 597 Burke Road, Camberwell.

Due to current government restriction and construction progress, settlement is expected to commence December 2021.

Our objective is to provide an efficient and seamless settlement of your townhouses. We will work alongside the developer, builder and yourself to coordinate valuers, solicitors and other service providers as a single point of contact that ensures your property settles smoothly.

From this point onwards, we will be communicating with you either by e-mails or phone calls to keep you updated with the construction progress, to arrange valuation inspection, pre-settlement inspection and so on. Meanwhile, we will also explain the detailed settlement process to you and provide advice regarding the current property market dynamics and financing strategies.

Could you please provide us your contact number via e-mail?

Customer Relations Team

You will receive a call from either Felicia or Amanda who will be your point of contact should you have any queries in relation to your townhouse in the lead up to settlement.

Name:
Felicia
Amanda

E-mail:
felicia@upssettlement.com.au
amanda@upssettlement.com.au

Mobile Number:
+61 450 706 566
+61 413 115 380

+ View More

Hazel Hawthorn

368 Auburn Road
Hawthorn
Builder:Quadrant
Project Manager:TBA
Anticipated Completion Date:Mid 2022
Anticipated Settlement:Mid 2022

Project Update

September, 2021

We are happy to report the following works are due to be completed by November pending any further restrictions

Roof Install

Widows install

Mechanical rough in works on ground floor commenced

+ View More

Highmont

3 James Street
Bayswater
Builder:D5 Building Group
Project Manager:Skyward Management
Anticipated Completion Date:November 2022
Anticipated Settlement:November 2022

Project Update

November, 2021

We are pleased to share the construction progress for Highmont project.

The following is the progress of the works to date:

• NBN pits and gas pipe installed
• Structure steel frame installed
• Shaft liner and walls completed
• Flooring and framing are in progress

Skyward Management
Contact Charles Lou
Mobile 0431 786 862
Email cluo@skywardmanagement.com.au

+ View More

Hotham & Carlisle

99 Hotham Street
Balaclava
Builder:Paragon Development Group
Project Manager:Paragon Development Group
Anticipated Completion Date:Late December 2021/March 2022
Anticipated Settlement:Late December 2021/March 2022

Project Update

November, 2021

We are pleased to advise our current anticipated settlement dates below:

Middle Block (Lots 5-14 & 20-29) – Late December 2021

Front Building (Lots 1-4) – March 2022

Rear Building (15-19) – March 2022

We will continue to send out regular updates to you all as works progress on site.

For all purchasers of townhouses in the Middle Block (Lots 5-14 & 20-29), can you please request your bank valuations to be completed prior to 30th November 2021.

Please have your banks/valuers contact Luke to arrange access. 0416 003 382

We will contact each individual purchasers when pre-settlement inspections are ready to be booked in.

We thank you for your patience and stay safe.

For all Settlement enquiries please contact

Butterfield Conveyancing
Attn: Max
General Contact Mobile: 0412 65 82 65
info@butterfieldconveyancing.com

Further updates to come from the developer in due course.

+ View More

Hurstmon

3 Hurstmon Street
Malvern East
Builder:Kapitol Group
Project Manager:Codicote
Anticipated Completion Date:Late 2022
Anticipated Settlement:Late 2022

Project Update

October, 2021

Construction recommences post lockdown with bulk excavation progressing.

Hurstmon is scheduled for completion by end of 2022.

Iramoo

7 Iramoo Street
Balwyn
Builder:Austland Build
Project Manager:TBC
Anticipated Completion Date:Mid 2022
Anticipated Settlement:Mid 2022

Project Update

December, 2021

Construction has now commenced at Iramoo.

1. Installation of Underground Piping and Drainage System – Work completed
2. Concrete Foundation – Rebar (reinforcement steel) work in progress. Pouring of concrete work in progress.
3. Preparation/Updating of Blueprints and Construction Plans – Ongoing process throughout the construction of project.

We will keep you posted regarding the progress on a regular basis and are excited to see this development take shape.

+ View More

Luar

22-24 Pakington Street
St Kilda
Builder:Drakk Constructions
Project Manager:David Parsons
Anticipated Completion Date:December 2021
Anticipated Settlement:December 2021

Project Update

December, 2021

Settlements are due to commence Early December

For all settlement valuation inspections please contact David Parsons 
M:  0407 983 241
P:  03 8676 9302
E:  
david@ppdm.com.au

+ View More

Luminess

27 Russell Street
Essendon
Builder:Drakk (Vic) Pty Ltd
Project Manager:J2 Projects
Anticipated Completion Date:Qrt 4 2022
Anticipated Settlement:Qtr 4 2022

Project Update

November, 2021

Construction is progressing well given the recent delays caused by the mandatory government shutdowns. We are pleased to report that the Ground floor slab is currently being poured onsite.

Luminess is looking at a Q4 2022 finish

Should you have any further queries please contact

Jenny Lu
J2 Projects
Assistant Project Manager
Jenny@j2projects.com.au
+61 402 508 091

+ View More

Melfort

496 Glenferrie Road
Hawthorn
Builder:Pulitano Commercial Construction
Project Manager:HS Consortium
Anticipated Completion Date:February 2022
Anticipated Settlement:March 2022

Project Update

November, 2021

With the impact of Covid 19 restrictions the builder expects to complete construction in mid February 2022 and we expect settlements to occur mid March 2022.

Further update to come from the developer in due course.

Myrtle

203 Canterbury Road
Blackburn
Builder:Fynnan Pty Ltd
Project Manager:TBC
Anticipated Completion Date:TBC
Anticipated Settlement:TBC

Project Update

September, 2021

We are pleased to announce that construction has now commenced on site.

Construction updates will be provided quarterly.

No.71

71-73 Station Street
Fairfield
Builder:Halecorp
Project Manager:Hub Property Group
Anticipated Completion Date:Q3 2022
Anticipated Settlement:Q3 2022

Project Update

October, 2021

We are pleased to report that despite government mandated restrictions the following works have now been completed on site

Basement

  • Services rough in is completed

GF

  • Metal wall frames and block party walls completed
  • Planter boxes constructed
  • Entry ramp is underway
  • Services rough in substantially completed

1st Floor

  • Metal wall frames and block party walls completed
  • Services rough in substantially completed

2nd Floor

  • Block party walls completed
  • Metal wall frames completed
  • Services rough in Substantially under way

3rd Floor

  • Set out underway for L3 Structure

Further updates to come in due course from the developer.

+ View More

Olea

50 Kambrook Road
Caulfield North
Builder:Balmain & Co
Project Manager:BNG Group
Anticipated Completion Date:February/March 2022
Anticipated Settlement:February/March 2022

Project Update

November, 2021

Unfortunately, despite the best efforts of the construction team, unavoidable issues related to COVID restrictions and sub-contractor resources on-site have and will affect the settlement timing for Olea Residences.

The builder currently expects that Valuation appointments and Pre-settlement inspections will be available in January/February 2022 with settlement expected to follow in February/March 2022. Please note; these dates are the current anticipated projections only.

We will continue to update this blog with any changes to settlement timing once available. Please feel free to contact Tom if you have any questions or concerns about your settlement or the above changes to settlement timing.

In the interim, we invite you to communicate BNG group on 1300 853 761 and ask to speak to Dina or email: Oleasales@bng.group for additional information.

For your journey Tom Hawkins will be your settlement co-ordinator. You can contact Tom on 03 8582 8972 or email to tom@settlement-solutions.com.au

+ View More

One Lakeview

1 Lakeview Avenue
Williamstown
Builder:Creation Homes
Project Manager:TBC
Anticipated Completion Date:Late 2022
Anticipated Settlement:Late 2022

Project Update

November, 2021

We are currently in the sales and marketing phase.

Whilst sales are occurring the development team is in discussions to bring One Lakeview to life.

Construction updates will be provided quarterly.

Parq

134-138 McKinnon Road
McKinnon
Builder:Fynnan Construction
Project Manager:Oxford Developments
Anticipated Completion Date:Qtr 1 2022
Anticipated Settlement:Qtr 1 2022

Project Update

November, 2021

We are delighted to inform you that we are now running this project at 100% capacity and have been doing so for the past 2 weeks.

We are in the process of finalizing our structure, and will begin shortly on our external cladding and glazing.

The team is pushing as hard as we can to ensure a Q1 2022 completion.

+ View More

Profile

1443 Dandenong Rd
Malvern East
Builder:Goldfields
Project Manager:M2
Anticipated Completion Date:December 2021
Anticipated Settlement:December 2021

Project Update

October, 2021

We are pleased to pass on the following update from the builder:

• Stone benchtops all floors, all wet area tiles completed
• Painting L2&3 ceilings
• Common area lining
• Basement ductwork
• Cover L2 blueboard
• External Render in progress
• Joinery all floors
• Plumber fit-off GF
• Lift core cladding in progress

The majority of works have been completed for the interior and we are now progressing with cladding for the external facade. We look to finalize the majority of external work by end of this month. Due to covid lockdown, we have faced some delays from authorities as they have transitioned to working from home- we will continue to monitor if this will have any effect on the completion program. We are committed to delivering an outstanding project and appreciate the support of all our purchasers.

We are advised that the developer is anticipating December 2021 Practical Completion.

UPS Settlement firm for settlement liaison.
Amanda
amanda@upssettlement.com.au
0413 115 380

+ View More

Rostrevor Parade

97 Rostrevor Parade
Mont Albert North
Builder:WestUrban Group
Project Manager:Hub Property Group
Anticipated Completion Date:Early 2023
Anticipated Settlement:Early 2023

Project Update

December, 2021

Demolition has finished on site , with the successful appointment of WestUrban Group. With early works to commence January 2022.

Construction updates will be provided quarterly.

Soligo

487 Whitehorse Road
Balwyn
Builder:Princi Projects
Project Manager:Princi Property
Anticipated Completion Date:December 2022
Anticipated Settlement:December 2022

Project Update

November, 2021

Construction has commenced on our Soligo project in Balwyn.

So far we have achieved;

• Perimeter retaining walls and new paling fences have now been completed.
• Site has now been stripped and benched along with the removal of the topsoil.
• Piling works have now been completed and the capping beam formed and sprayed.
• Bulk excavation will start next week (weather permitting) and the basement will soon start to take form.

You can also follow construction of Soligo on the Princi.Property Instagram account.

+ View More

Ten to Twelve

10-12 Lindsay Street
Brighton
Builder:Cobild
Project Manager:Hub Property Group
Anticipated Completion Date:Qtr 2 2022
Anticipated Settlement:Qtr 2 2022

Project Update

November, 2021

With construction restrictions lifted, progress at Ten to Twelve is going exceptionally well!

Please see below key milestones achieved this month.

• Internal personnel lifts ready to be installed
• Fireplaces installed across all levels
• Waterproofing to wet areas commenced on ground floor
• Bathtubs installed to ground floor and level one
• Basement smoke lobby doors installed
• Continuation of stone to facade of the building

We are excited and look forward to bringing you more updates as the project progresses!

If you have any questions please don’t hesitate to get in touch with Daniel Sergious at daniel@hubpg.com.au.

+ View More

The Avenue

15 Landale Avenue
Croydon
Builder:First Construction
Project Manager:BHC Property
Anticipated Completion Date:Qtr 3 2022
Anticipated Settlement:Qtr 3 2022

Project Update

December, 2021

The holiday season is just around the corner!

We are pleased to provide the progress achieved on-site to date for The Avenue, Croydon.

  • Light steel framing is underway with target completion before Christmas
  • Masonry works on the ground floor have commenced
  • Plumbing rough-in has commenced on the Ground floor

Construction completion is currently anticipated to be by Quarter 3 of 2022.

Please see photos taken from the site, as below:

+ View More

Timeless

555 Burke Road
Camberwell
Builder:Balmain & Co
Project Manager:J2 Projects
Anticipated Completion Date:Q2 2022
Anticipated Settlement:Q2 2022

Project Update

November, 2021

We are pleased to provide an update on the Timeless Apartments.

Progress on site is going well given the recent COVID shutdown.

Wall sheeting and window installation has commenced, and the basement is nearing completion.

Services have been roughed in and ceiling framing has commenced.

The prototype room is also coming together nicely.

The team is pushing hard for a Q2 2022 completion.

+ View More

Two Eighty Waverley

280 Waverley Road
Malvern East
Builder:TBC
Project Manager:Shustin
Anticipated Completion Date:Late 2022
Anticipated Settlement:Late 2022

Project Update

December, 2021

It is our pleasure to welcome you to our first newsletter. We hope you are well and enjoying post lockdown freedom. The end of restrictions could not have  come soon enough for our industry, and we are thrilled to finally be able to commence our project delivery journey.

Despite many challenges posed by the pandemic, we have been working with our architects, engineers and other trusted project partners to finalise the plans and construction program.

Our aim is to commence demolition this side of the year or early next year, subject to demolition permit being issued by the local council in timely manner.

We will keep you posted regarding the progress on a regular basis, but if you have any queries, please do not hesitate to contact us via email info@shustin.com. We are always happy to hear from you.

+ View More

Verse

18-28 Wilkinson Road
Sunshine
Builder:Rise Constructions
Project Manager:Paragon Development Group
Anticipated Completion Date:Early 2022
Anticipated Settlement:Mid December 2021 Commence through to Early 2022

Project Update

November, 2021

We are pleased to advise our revised anticipated settlement dates below:

Northern Block (Lots 1-9) – Mid December
Southern Block (Lots 20-30) – End of December
Middle Block (Lots 10-19) – Early 2022
East Block (Lots 31-37) – Early 2022

All subdivision items have been lodged to Council and are waiting on them to approve all items which can take some time.

Titles will be lodged next week. Land titles office can take up to 4 weeks to issue the new titles.

We will continue to send out regular updates to you all as works progress on site and will make contact with each individual purchasers when pre-settlement inspection are ready to be booked in.

We ask that all Northern & Southern Block purchasers complete valuations on their respective lots as soon as possible.

We thank you for your patience and stay safe.

PARAGON DEVELOPMENT GROUP

P: +61 3 8080 5888
E: settlements@paragondg.com.au
W: www.paragondg.com.au

+ View More

Walmer

649 Victoria Street
Abbotsford
Builder:Hamilton Marino
Project Manager:TBC
Anticipated Completion Date:Qtr 4 2022
Anticipated Settlement:Qtr 4 2022

Project Update

November, 2021

We saw many milestones on site accomplished with the erection of the tower crane completed, as well as the commencement of foundation piling.

Piling forms the very basis of construction and is the essential support needed for the structure. It is a technique that sets deep foundations for any form of construction work.

October: With construction back, it’s all hands on deck at Walmer. We saw the first slab of concrete for Basement 2 poured, and the removal of the remaining dirt well underway. Shotcrete of walls on the west elevation is complete with the north elevation to begin by the end of this week.

Move in date remains late 2022.

Construction updates will be provided quarterly.

+ View More

Wattle on the Park

2 Wattle Grove
McKinnon
Builder:Fynnan Constructions
Project Manager:KBMV
Anticipated Completion Date:March 2022
Anticipated Settlement:March 2022

Project Update

October, 2021

Another update as we slowly come out of another lockdown.

I hope everyone has been well and looking forward to easing of restrictions and Covid normal summer.

Fynnan builders have been back on site after the construction industry’s mandatory lockdown was lifted, and with the limit of 5 people on site have been trying to move the building towards the next objective. With strict Covid Safe rules in place, Fynnan have been progressing and managing the site in a responsible and safe manner ensuring that everyone on site is vaccinated and kept safe.

Since the last update, we can report that further exterior cladding has been installed as well as the roof being put on, making the building less prone to the external elements.

Internal rough-in of the electrical and plumbing have been completed as well as the installation of Skylights.

Mechanical services have been also installed in preparation for the plastering works (plaster sheets have been delivered to the site already).

Carpenters have been working tirelessly in preparation of the internal walls for the plaster to be installed.

We have applied to the Council for Town Planning Permit for Subdivision, which has been subsequently granted.

As we move closer to the holidays period  we hope to see further progress especially once the 5 person limit on building site is eased and we see more trades on site.

At this stage we are being advised by our builder that the completion date is  anticipated for March 2022 and they are aiming to meet that timeline subject to any further unforeseen restrictions.

Until our next update please keep safe and well.

From KBMV Developments Team

+ View More

For further enquiry or any issues, please contact:

Address: 1111 High Street Armadale VIC 3143
Email : georgie.lupson@marshallwhite.com.au
Phone : 03 9832 1197

X

X

Register for instant email alerts when a property matches your criteria.