308 Carlisle

308 Carlisle Street
Balaclava
Builder:VCON
Project Manager:Urban DC
Anticipated Completion Date:End Sep 2018
Expected Settlement:October 2018

Project Update

Works onsite are progressing well with valuation access now available and purchaser pre-settlement inspections likely to take place in the next 2 weeks. Settlement is currently anticipated for end September depending on when Titles register and the Occupancy Permit is issued.

525 High

525 High Street
Prahran
Builder:Arc 3
Project Manager:Goldfields Group
Anticipated Completion Date:Early 2019
Expected Settlement:Early 2019

Project Update

Goldfields is pleased to report that construction onsite continues to track well.

Due some recent inclement weather – particularly high winds that have affected crane activities onsite, Arc 3 have encountered delays to construction progress at 525 High Street. A revised program from Arc 3 is showing that construction will unfortunately no longer be completed by December 2018 as previously communicated. Whilst we still anticipate the building to be approximately 95% by the end of the year, the revised program is reforecasting a new move-in date of mid February 2019.

+ View More

Arcadian

511 Dandenong Road,
Armadale
Builder:Charles Edgar
Project Manager:Samssons Projects
Anticipated Completion Date:Mid-late 2019
Expected Settlement:Mid-late 2019

Project Update

The developer has advised us that it has been a very busy and productive past month on-site.
Most recently there have been 4 teams on site; one is doing the anchoring into the piles, one is doing the detailed pile excavation, and another doing the bulk excavation, the last team is preparing the walls to start spraying them with concrete, which should happen towards the end of this week or early next week.
The developer doesn’t anticipate any delays from all sides of the project.

+ View More

Balmoral

1571 Malvern Road
Glen Iris
Builder:Cobild
Project Manager:Neoscape
Anticipated Completion Date:Mid-late 2019
Expected Settlement:Mid-late 2019

Project Update

The developer has advised us that the capping beam is underway with bulk excavation scheduled to commence shortly thereafter. Construction is progressing well with the capping beam and ground anchors complete.
The first layer of shotcrete to the basement has also been completed, with the second layer underway this week.
Videos and photos posted to the Instagram page of Fortis www.instagram.com/fortisdg

+ View More

Bloom

1240 Glen Huntly Road
Carnegie
Builder:Nantong Construction
Project Manager:Sam Segman
Anticipated Completion Date:Mid-late 2019
Expected Settlement:Mid-late 2019

Project Update

Bloom Glenhuntly continues to progress well. The second pour of the slab on the ground level has been completed. Preparation for pour 3 slab on the ground has commenced. Prefabricated staircases have been installed in the stair shaft up to basement level 1. Suspended slab at the South East Corner has commenced.

Further updates and photographs to come in October.

+ View More

Centenary Apartments

817-819 Centre Road
Bentleigh East
Builder:Valeo Construction
Project Manager:Valeo Construction
Anticipated Completion Date:December 2019
Expected Settlement:Early 2020

Project Update

Valeo Construction is pleased to advise they have achieved their projected milestones and are tracking on Target for completion.

Site progress Summary is as follows:

  • Services Trades (Fire, Electrical, Mechanical and Hydraulics) completed 100% rough in works on Ground Floor, 90% Complete on Level 1 and 70% on Level 2.
  • We are pleased to announce that Valeo Construction have achieved their projected milestones and are tracking on Target for completion.

As the construction of your apartment continues, we will endeavour to keep you updated with progress reports. If you have any queries or concerns, please do not hesitate to contact Valeo office on 03 9686 2588 or alternatively email info@valeoconstruction.com.au.

+ View More

Charlemont Apartments

92 Hawthorn Road
Caulfield North
Builder:Shustin
Project Manager:Perkins Architects
Anticipated Completion Date:September 2018
Expected Settlement:October 2018

Project Update

We are pleased to advise you that your apartment will be ready for a pre-settlement inspection from Tuesday 11 September 2018.

Please contact the Settlement Company for Valuations on 95306800 to arrange access to the apartments.

Hello

82 Hawdon Street
Heidleberg
Builder:Valeo Construction
Project Manager:
Anticipated Completion Date:Late 2018
Expected Settlement:Late 2018

Project Update

The developer advises at this stage that they are looking at a completion date of the middle of October, once a certificate of Occupancy is obtained.

This would mean aiming for 1st week of November for Settlement.

We will advise further information in due course.

+ View More

McKinely Residences

171 Wattletree Road
Malvern
Builder:Ironside
Project Manager:Pomeroy Pacific
Anticipated Completion Date:Late 2019
Expected Settlement:Late 2019

Project Update

It is with great pleasure that we confirm that construction works have commenced for McKinley Residences. A piling rig has commenced in boring the concrete piers for the basement retention walls. Whilst other works have preceded this, the piling is a major item for the project. Our builder Ironside Construction will now work continuously on site through to completion which is scheduled for the last quarter of 2019.

We understand that it has been a long wait for commencement. All our development, construction, funding and sales team have worked hard to make this happen. We appreciate the patience of our purchasers and look forward to delivering an outstanding development.

We shall provide regular updates and photos as works progress.

+ View More

Nelson St

Eden Sq, Garden Sq, Yarra Sq, Yarra Townhouse; 42-58 Nelson Street
Ringwood
Builder:Hamilton Marino
Project Manager:Sunstone
Anticipated Completion Date:Early 2019
Expected Settlement:Early 2019

Project Update

The developer has advised that construction on Nelson Street has hit several milestones enabling the building completion to be early. Works have been carried out on site to date includes: – High Level Services – Windows & Balustrade Installed – Internal Partitions & Tiling – Carpentry & Joinery.

Settlement can now be anticipated in early February 2019

+ View More

Olor

306-312 Swan Street
Richmond
Builder:Valeo Construction
Project Manager:Valeo Construction
Anticipated Completion Date:September 2018
Expected Settlement:October 2018

Project Update

The developer advises that the Occupancy permit was achieved late last week and Plan of Subdivision has now been lodged with the Land Titles Office. Once the Plan has been registered by the Land Titles Office the titles will be released and enable the solicitor to call for settlements. The standard time frame for the Land Title Office to release the titles is 10 working days so we anticipate these to be released week commencing 24/09/2018.

That is putting settlement towards the end of Sep/ start of October. We will advise further info in due course.

+ View More

Pelham

54 Wattletree Road
Armadale
Builder:Figurehead
Project Manager:Pax
Anticipated Completion Date:Mid-late 2019
Expected Settlement:Mid-late 2019

Project Update

Works onsite are progressing well, with Figurehead Construction having now completed the basement bored pile retention wall and the slab on the ground at basement level.  Installation of the precast concrete walls is underway on the lower levels and the first suspended concrete slab at the mid-level of the basement is complete.

The concrete slab at the Wattletree Road ground level is due to be completed at the end of this month and the concrete structure will continue to be erected over the next 4 months for completion by the end of 2018.

Construction of Pelham has commenced smoothly, and we expect this to continue through to completion. The target completion date remains on track for August 2019 with settlements shortly thereafter.

We will provide you with a further update in December.

+ View More

Royal Ascot

2 Mascoma Street
Ascot Vale
Builder:Element 5
Project Manager:Pomeroy Pacific
Anticipated Completion Date:Mid-late 2019
Expected Settlement:Mid- late 2019

Project Update

Unfortunately, the developer has encountered significant setbacks to construction commencement due to a number of onerous, pre-commencement Authority requirements. . At this stage we are forecasting to commence construction in October 2018, however are still at the mercy of a number of statutory authorities.

McLaren Developments in conjunction with Pomeroy Pacific are committed to delivering Royal Ascot apartments for you and appreciate your continued patience as they push to resolve the issues. Further updates will be provided in due course.

+ View More

The Kent

382 Burwood Rd
Hawthorn
Builder:Cobild
Project Manager:HS Consortium
Anticipated Completion Date:Early 2020
Expected Settlement:Early 2020

Project Update

The developer has advised that the builder, Bayside Construct, unfortunately went into Administration about 2 months ago, however they have now secured a new builder and appointed Cobild Pty Ltd. www.cobild.com.au

Cobild will commence construction in September and at this stage anticipated date of completion is early 2020.

+ View More

Windsor Terrace

168 High Street
Prahran
Builder:Balmain Construction
Project Manager:Hub Property Group
Anticipated Completion Date:Mid 2019
Expected Settlement:Mid 2019

Project Update

The developer has advised that in early August the level four concrete pour took place at Windsor Terrace. Since then the Alimak has been installed, site sheds have relocated from a leased premise onto the site, basement levels one and two are live with power whilst trades continue services install. Next week the level five concrete pour will take place with the ground floor walls to commence shortly after.

+ View More

Address: 1111 High Street Armadale VIC 3143

Phone: +61 3 9832 1192
Email: zara.singh@marshallwhite.com.au