1975

1975 Malvern Road
Malvern East
Builder:TBA
Project Manager:BHC Group
Anticipated Completion Date:Mid 2020
Expected Settlement:Mid 2020

Project Update

May, 2019

We are currently in the sales and marketing phase.

Whilst sales are occurring the development team is in discussions with builders and banks to bring 1975 to life.

Construction updates will be provided quarterly.

+ View More

232 Wattletree

232 Wattletree Road
Malvern
Builder:Cobild
Project Manager:Neoscape
Anticipated Completion Date:September 2019
Expected Settlement:September 2019

Project Update

May, 2019

The Fortis team visited site this week and are happy to share with you some photos and an update.

Cobild are right on track having successfully completed the roof sheeting and are now installing windows to all floors.

Cladding installation has commenced to the top and ground floor and internal plastering will commence imminently.

We are very pleased to report that construction of 232 Wattletree is progressing well with building completion currently targeted for September. As settlement approaches, we will regularly contact you with timing updates.

Fortis Development Group provides monthly eDM’s. Please contact us if you have not received this. 232 Wattletree settlement team are happy to discuss any further queries in regard to funding or any other matters about your home at 232 Wattletree, please feel free to contact us at any time.

Regular videos and updates are also put on up the on Instagram story- follow @fortisdg and click on the “232 Wattletree” button www.instagram.com/fortisdg/.

For any queries relating to Settlement, please contact Pip Wright from the Fortis Settlement Team on mobile +61 416 998 511 or email 232wattletree@fortis.com.au

+ View More

525 High

525 High Street
Prahran
Builder:Arc 3
Project Manager:Goldfields Group
Anticipated Completion Date:April 2019
Expected Settlement:April 2019

Project Update

May, 2019

We are excited to announce that the Project is complete and Settlements are underway.

Please contact  Erin Moore from Goldfields with any Settlement enquiries:  erin@goldfieldsgroup.com.au P) 0401581933

 

 

 

818 Caulfield Residences

818 Glenhuntly Road
Caulfield South
Builder:Cobild
Project Manager:TBA
Anticipated Completion Date:Early 2020
Expected Settlement:Early 2020

Project Update

April, 2019

We have pleasure in confirming that works onsite at 818 Caulfield Residences are progressing well.

Cobild have now organised for the underground power installation and piling will commence after Easter.

Completion of 818 Caulfield Residences remains on track for an anticipated settlement of approximately July 2020.

We will continue to provide you with updates of key milestones reached and firming up completion timelines, however please do not hesitate to contact Jenny Roche from Urban DC should you have any queries in the meantime jen@urbandc.com.au

 

+ View More

Aintree Park

1432-1436 Malvern Rd
Glen Iris
Builder:Samssons Projects
Project Manager:TBA
Anticipated Completion Date:Early 2020
Expected Settlement:Early 2020

Project Update

We are currently in the sales and marketing phase.

Whilst sales are occurring the development team is in discussions with builders and banks to bring Aintree Park to life.

Construction updates will be provided quarterly.

+ View More

Akora

5-7 Kooyong Road
Armadale
Builder:Ironside
Project Manager:Nash Management
Anticipated Completion Date:October 2019
Expected Settlement:Mid-Late 2019

Project Update

IRONSIDE have been making great progress on site. Based on this current timelines we are expect settlement to occur sometime in October 2019.

With this in mind we recommend purchasers who hare using finance to begin discussions with your banks as early as possible. We are finding banks have tightened up their lending criteria, lengthening the ordinary time for approving a loan.

Further and regular communication will come with regards to the process for settlement include expectations around the settlement process.

 

+ View More

Allegra

1538 – 1540 High Street
Glen Iris
Builder:TBA
Project Manager:Nash Project Management
Anticipated Completion Date:Mid 2020
Expected Settlement:Mid 2020

Project Update

We are currently in the sales and marketing phase.

Whilst sales are occurring the development team is in discussions with builders and banks to bring Allegra to life.

Construction updates will be provided quarterly.

Altus

260 -262 Burwood Hwy
Burwood
Builder:Iurada Construction
Project Manager:BHC Property
Anticipated Completion Date:Late 2019
Expected Settlement:Late 2019

Project Update

May, 2019

We are pleased to provide you with the progress achieved on site so far;

  • Level 3 slab has been poured.
  • Level 4 slab will be poured 29/04/2019
    Services: Sewer connected.

We are currently anticipating settlement time in November / December 2019.

We will keep you posted as we progress through the next phase.

 

 

+ View More

Anderson Park

585 Burke Road
Hawthorn East
Builder:TBA
Project Manager:Nash Project Management
Anticipated Completion Date:TBA
Expected Settlement:TBA

Project Update

April, 2019

The developer would like to advise that they are currently tendering for a builder, and would expect they will be able to make an announcement on the builder appointment during May 2019.

We will advise you all in due course.

Arcadian

511 Dandenong Road
Armadale
Builder:Charles Edgar
Project Manager:Samssons Projects
Anticipated Completion Date:Mid-late 2019
Expected Settlement:Mid-late 2019

Project Update

May, 2019

The developer has advised that it has been a busy and productive past few months on-site.

  • Gyprock has started on Ground and Level 1.
  • Plumbing in Carpark & Mechanical throughout.
  • Fire services throughout the building
  • Carpenter started throughout
  • Stripping formwork from the front end of the building
  • Expecting Lock up first week of June.

Completion is anticipated for Oct 2019. The developer doesn’t anticipate any delays from all sides of the project.

 

+ View More

Ashton Park

338 Burwood Hwy
Burwood
Builder:Iurada Construction
Project Manager:BHC Property
Anticipated Completion Date:June 2019
Expected Settlement:Mid 2019

Project Update

We are pleased to update you on the construction status for 338-340 Burwood Highway, Burwood.

Building B – Anticipated settlement early June.
Building A – Anticipated settlement mid of June

Building B – Kitchen Joinery are in, stairs are in expect for ground floor.

Building A – West area titles are in, currently doing plastering and painting works, stairs are in expect for ground floor.

We have engaged settlement solution as our settlement agent. Should you have any question, regarding settlement matter, please do not hesitate to contact with the below details:
Contact: Monique / Ph: 03 8582 8972 / Email: monique@settlement-solutions.com.au

+ View More

Ballantyne

1693 – 1697 Malvern Road
Glen Iris
Builder:Citi-Con
Project Manager:Charter Keck Cramer
Anticipated Completion Date:Early 2019
Expected Settlement:Early 2019

Project Update

May, 2019

The Certificate of Occupancy has now been achieved for lots 2 to 11.

The Plan of Subdivision has also now been lodged at the Land Titles Office for registration.

Once the Plan of Subdivision has been registered, settlement will be triggered. Letters will then be sent to your legal representative, requiring you to settle your apartment within the allocated timeframe.

We will continue to keep you updated as soon as any new information comes to light.

In the meantime, please do not hesitate to contact Monique Maclean from Property Settlement Solutions on 03 8582 8972 or email monique@settlement-solutions.com.au.

+ View More

Balmoral

1571 Malvern Road
Glen Iris
Builder:Cobild
Project Manager:Neoscape
Anticipated Completion Date:September 2019
Expected Settlement:Mid-late 2019

Project Update

May, 2019

The Fortis team visited site this week and are happy to share with you some photos and an update.

Cobild are right on track having successfully completed the roof sheeting and the external cladding to the top floor. Windows are currently being installed to the Ground Floor and Level 3, while the brickwork installation to the lower levels has just commenced.

We are very pleased to report that construction of Balmoral is progressing well with building completion currently targeted for September.

As settlement approaches, we will regularly contact you with timing updates.

For any queries relating to Settlement please contact Pip Wright from the Fortis Development Team.
M  +61 417 998 511   •  E balmoral@fortis.com.au   •  W  www.fortis.com.au

+ View More

Beckworth

184-186 Tooronga Road
Glen Iris
Builder:Harris HMC
Project Manager:TBA
Anticipated Completion Date:Mid 2020
Expected Settlement:Mid 2020

Project Update

April, 2019

Award Winning Builder, Harris HMC has now been appointed to commence construction on these beautiful residences.

Formed in 1984, Harris HMC is a family owned and operated Melbourne based Construction Group. Since their inception, Harris HMC has successfully completed a broad range of projects with an annual turnover in excess of $220million. They have established several rigorous internal standard operating procedures which contribute towards their ability to deliver exceptional projects with methodical planning, on-time and on-budget delivery, and a collaborative approach with their clients.

Construction commencing soon. We will update you further in due course.

 

+ View More

Bespoke

1394 Malvern Road
Glen Iris
Builder:Drive Construction
Project Manager:
Anticipated Completion Date:Early- Mid 2020
Expected Settlement:Early - Mid 2020

Project Update

Excitedly, we are pleased to announce that Manresa (www.manresa.com.au) has been appointed under letter of intent to build your new apartment at 1394 Malvern Road, Glen Iris.

The developer is now working with Manresa on pre-commencement items and anticipate that construction will commence by July.

Construction is forecast to take 14 months so at this stage we are aiming for a mid-2020 completion.

We look forward to updating you with further details in due course.

+ View More

Bloom

1240 Glen Huntly Road
Carnegie
Builder:Nantong Construction
Project Manager:Sam Segman
Anticipated Completion Date:Q3 2019
Expected Settlement:Mid-late 2019

Project Update

May, 2019

Bloom Glenhuntly is pleased to report that construction on site continues to progress well with the above ground structure now taking form.

Two basements and ground floor are now complete and the team is working on finishing the 1st Floor Slab in May 2019.

Plumbing, Electrical, Fire & Mechanical Services have started their works on basements and it is all progressing well.

At this stage, Bloom’s completion date is currently anticipated for the end of the year 2019 with further timings to come as we near Project completion.

Planned Milestone Dates on Project:

  • Level 1 Structure- Expected Completion – May 19.
  • Level 2 Structure- Expected Completion – June 19.
  • Level 3 Structure- Expected Completion- July 19.
  • Level 4 Structure- Expected Completion – Aug 19.
  • Level 5 Structure- Expected Completion – Sep 19.
  • Internal finishes are expected to start in June 19 and finish by Dec 19.

All enquiries from purchasers should be directed to: Cathleen at Nantong Construction P) 9827 2211 or E) cathleenntconstruction@hotmail.com or Jason Gujx E) Jjason.gujx@zoina.cn

+ View More

Botanical

16 Spring Road
Malvern
Builder:Hamilton Marino
Project Manager:Land Real
Anticipated Completion Date:Early-Mid 2020
Expected Settlement:Mid 2020

Project Update

May, 2019

The developer advises the following update:

  • Bulk excavation works were progressed in April reaching basement level 2.
  • Works completed to date are progressing in accordance with the construction timetable.

 Construction updates will be provided quarterly.

 

+ View More

Central Park

2A Nyora Street
Malvern East
Builder:TBA
Project Manager:TBA
Anticipated Completion Date:Q4 2020
Expected Settlement:Q4 2020

Project Update

May, 2019

We are currently in the sales and marketing phase.

 Whilst sales are occurring the development team is in discussions with builders and banks to bring Central Park to life.

 Construction updates will be provided quarterly.

+ View More

East End

20 Canterbury Road
Blackburn South
Builder:Carelli Construction
Project Manager:JPS Projects
Anticipated Completion Date:Mid- late 2019
Expected Settlement:Mid- late 2019

Project Update

The delivery of the East End Apartments is now well into the construction phase. Carelli Construction completed the basement works by the end of last year as planned. They are now focused on the construction of the basement lift shaft and the large ground level concrete slab. Once the ground level concrete slab is complete the next major mile stone will be to complete the above ground concrete and steel super structure.

The super structural is scheduled for completion just after Easter.
There still isn’t much to see yet because most of the work is underground, although below are a few pictures of the ground slab formwork and steel reinforcement. Looking forward as construction works continues, we will begin sending more pictures and news of the projects progress in our quarterly updates.

Anticipated date of Completion at this stage is on track for October 2019

+ View More

East Grove

2a Kenilworth Grove
Glen Iris
Builder:Cobild
Project Manager:Neoscape
Anticipated Completion Date:Early 2020
Expected Settlement:Early 2020

Project Update

May, 2019

We are pleased to provide the update from the Developer Fortis Construction Group within East Grove.

Cobild successfully completed the pilin and capping beam and shotcrete down into the Basement. You may have noticed a lot of action on site as we are now in the final stage of Bulk Excavation. Detailed excavation will commence towards the end of May at which point Cobild will be ready to

We will continue to update you each month, as well as provide you with important information regarding settlement arrangements as the building approaches completion. If you do not receive these please let us know.

 

+ View More

Eastbridge

833 High Street
Kew East
Builder:D5 Building Group
Project Manager:BHC Property
Anticipated Completion Date:Mid- late 2020
Expected Settlement:Mid-late 2020

Project Update

The appointed builder D5 Building Group has completed some sewer works at the rear of the property in preparation for the construction of the new townhouses.

Hoarding fence and temporary power to site is currently underway. There are a few authority and council approvals that are still pending approval before the builder can commence construction of the basement.

Majority of the purchaser changes are finally confirmed and already documented in the working drawings.

The project team is currently finalizing their building permit drawings and ensuring building codes compliances are met.

The developer is eager to get the construction underway as soon as possible.

Further updates to come in due course.

Practical completion is anticipated to be by third quarter of 2020.

+ View More

Emerald Grove

66 Stanley Rd
Keysborough
Builder:Fynnan Construction
Project Manager:N/A
Anticipated Completion Date:Late 2019
Expected Settlement:Late 2019

Project Update

Construction Commenced!

The developer is excited to announce that construction has started at Emerald Grove.
Civil work is ongoing underground and structural works will be starting soon.

Further updates to come in due course.

Form

21 Riversdale Road
Hawthorn
Builder:Cobild
Project Manager:Pax Project Management
Anticipated Completion Date:Mid- late 2019
Expected Settlement:Mid - late 2019

Project Update

2019 is off to a fantastic start on site at 21 Riversdale Road.
Our builders Cobild have officially topped out meaning key structural works are now complete.
A number of the external off-form concrete walls have been poured and are looking crisp. You will see this in the section above the carpark entry and also blade wall to the main entrance.

Furthermore, external glass doors to apartments have commenced installation as well as internal wall partition set outs are being placed and mechanical, electrical and hydraulic rough ins are well underway.
We have recently placed orders for our unique recycled timber from Just Eco and also the stunning stone from Signorino.
Our construction program is still tracking well with practical completion likely to be falling early October 2019.

+ View More

Hank

5-9 Hanke Road
Doncaster
Builder:Stemcom
Project Manager:Nash Management
Anticipated Completion Date:Early - Mid 2019
Expected Settlement:Early - Mid 2019

Project Update

May, 2019

Valuation Inspections have taken place, and completion is on track with Settlement anticipated for May/June 2019.

Please note that all information relating to completion and Settlement are with the Settlement coordinator, Amanda Wang from UPS Settlement.  Please contact Amanda on 0413 115 380 or via email: amanda@upssettlement.com.au

+ View More

Hello

82 Hawdon Street
Heidleberg
Builder:Valeo Construction
Project Manager:
Anticipated Completion Date:April 2019
Expected Settlement:April/May 2019

Project Update

It is our understanding that the developer, Ted Kirsch has been in touch with all purchasers individually to manage valuation and purchaser inspections.

Currently the developer is working on managing the defects with the builders while simultaneously waiting on the Land Titles office to issue titles. They are hoping that the Occupancy Certificate should issued by the end of the month allowing Settlement and key handover to be arranged.

Thanks for your patience and please email Ted Kirsh <retrohouse@bigpond.com> for any issues or contact Amy at Marshall White Projects on 9832 1278.

+ View More

Helm

300 Burwood Road
Hawthorn
Builder:Buildcept
Project Manager:TBA
Anticipated Completion Date:Early 2020
Expected Settlement:Early 2020

Project Update

Happy News!  We are very pleased to confirm that Buildcept have been formally engaged as the Builder for the HELM Apartments, and they have been on-site this week to finalise their Formal Planning in readiness for physical works to commence 9th January 2019.

Formal Planning has included designing and ordering of the tilt slabs, and final planning of the formal structure (e.g. Glass), so that everything will be in place for works to commence “full steam ahead” without delay.

Please do not hesitate to contact us with any questions you may have, and we wish you and yours a wonderful and safe Festive Season and New Year!

We look forward to providing you further HELM Construction updates in 2019.

Getting Ready for Settlement

If you are still investigating your finance options, we encourage you to contact Jarrod Hodges, Finance Manager at Hawthorn Finance, the multi-award winning lending and finance division of McLean Delmo Bentleys.

Jarrod will be able to assist you in every step of your finance application, doing the hard work for you to efficiently deliver tailored, cost-effective loan options to benefit you. Hawthorn Finance has strong networks and experience in dealing with over 30 different financiers, providing the purchasing power and Jarrod’s negotiating skills to enable you to obtain a better financial outcome than if you approached the banks of lending institutions directly.

Please contact Jarrod to discuss your financing options on jhodges@mcdb.com.au, or on his mobile, 0447 596 436.

+ View More

Highgreen

1457 High Street
Glen Iris
Builder:Ironside
Project Manager:VPP
Anticipated Completion Date:Mid 2020
Expected Settlement:Mid 2020

Project Update

The construction is tracking along very well, with bulk excavation for basement 1 fully completed and basement 2 80% completed, basement 1 shotcrete wall completed and basement 2 wall under construction.

For the coming month of April, the construction team anticipate to complete the following items

  • Complete detailing and shotcrete works to basement 2
  • Inground civil works
  • Dig and pour footing and slab of basement 2
  • Erect lift overrun walls

It’s anticipated completion will be in the 2nd quarter of 2020.

 

 

+ View More

Hotham

99 Hotham Street
Balaclava
Builder:Paragon Development Group
Project Manager:Paragon Development Group
Anticipated Completion Date:Mid 2020
Expected Settlement:Mid 2020

Project Update

May, 2019

We are pleased to announce that demolition has commenced. It should take approximately 3 weeks for demolition to complete.

Further updates to come in due course.

It is anticipated that project completion will be mid 2020.

 

Howard West

3-11 Howard Street
West Melbourne
Builder:Sinjen Pty Ltd
Project Manager:Pomeroy Pacific
Anticipated Completion Date:Early 2020
Expected Settlement:Early 2020

Project Update

March, 2019

Please refer below for the tenth update on the progress at Howard West, 3‐11 Howard St, West Melbourne.

  • During the first quarter of 2019, the heritage portions of the building to be retained have been fully braced and concrete structural slabs and columns have been completed for the car park basement, ground floor lobbies and tenancies, townhouse rumpus rooms and the townhouse first floor.
  • Associated service rough‐in works have also been completed at the same time
  • Key lead items have been procured for the fitout stages and most trade subcontracts have been let.

Schedule

There is no change to the schedule from the July 2018 update and completion is targeted for January 2020. As progress continues, we will keep you informed of any improvements to the schedule.

+ View More

Jackson Street

11 Jackson Street
St Kilda
Builder:Cobild
Project Manager:James Beresford
Anticipated Completion Date:Mid 2019
Expected Settlement:Q3 2019

Project Update

The Jackson Street team are pleased to provide the following update in relation to the construction progress:

We are currently mid-way through framing, wall services and glazing installation on all apartment floors. Planter boxes are also underway and we are aiming to have the building closed up in the next month allowing for the completion of internal fit out works.

Jackson Street construction is still aimed for completion in Quarter 2, 2019.

Jackson Street settlement is scheduled for Quarter 3, 2019.

 

+ View More

Lawson

39 Lawson Street
Hawthorn East
Builder:D5 Building Group
Project Manager:BHC Property
Anticipated Completion Date:Early - mid 2020
Expected Settlement:Early - mid 2020

Project Update

We are pleased to provide you with the progress achieved on site so far.

Wall has been finished 100%. In-ground plumbing and civil works have been completed. Excavating the footings and preparation for the concrete to be poured after Easter

We will keep you posted as we progress through the next phase.

bhcproperty.com/lawson-april-2019/

+ View More

Lothian Street

141 Arden Street
North Melbourne
Builder:Bear Projects
Project Manager:Exelon Projects
Anticipated Completion Date:August 2020 (Mid- late 2020)
Expected Settlement:(Mid- late 2020)

Project Update

April, 2019

The developer is pleased to provide the following update.

On 26th March 2019, Bear projects was formally appointed as the builder for Lothian Street. Kennedy Nolan Architects will continue to provide construction stage services.

Currently we anticipate that the project will be completed in August 2020, however this is an estimate only.

We will endeavour to provide quarterly project construction updates throughout this process.

+ View More

Luar

22-24 Pakington Street
St Kilda
Builder:Drakk Constructions
Project Manager:David Parsons
Anticipated Completion Date:Early - mid 2020
Expected Settlement:Early - mid 2020

Project Update

The developer is pleased to advise that they have engaged Drakk Constructions to build Luar apartments.

May 2nd, 2019: Demolition has commenced! See Picture attached.

Demolition is expected to be completed within 2 months and construction to be complete Q3 next year.

We will further update this page in due course. Thanks for your patience.

+ View More

Malvern Residences

1186-1188 Malvern Rd
Malvern
Builder:Cobild
Project Manager:TBA
Anticipated Completion Date:Late 2019
Expected Settlement:Early 2020

Project Update

The developer would like to provide the purchasers with the following update as @ 17th April 2019

Cobild Construction site progress is coming along . Please see updated photos.

Piling was completed last week and capping beams being laid this week with  bulk basement excavation commencing from next week .

Anticipated completion date May 2020.

Purchaser Change Requests

The developer have several purchasers that have requested changes during and subsequent to the sales campaign. These are currently being costed by  Cobild Construction.

These costings will then be distributed to the respective purchasers for their consideration. If required the purchaser, builder and FMD will meet to discuss these changes.

+ View More

McKinely Residences

171 Wattletree Road
Malvern
Builder:Ironside
Project Manager:Pomeroy Pacific
Anticipated Completion Date:Late 2019
Expected Settlement:Late 2019

Project Update

Construction for McKinley Residences is booming ahead. Ironside Construction has made significant process over the past few weeks and is confident that handover will be achieved by late 2019.

Recent site Works include:
• Ground floor and Level 1 fully formed up and concrete Slab 100% completed
• Construction of Level 2 walls and formwork has commenced
• Trade procurement is on schedule at approximately 60% complete

At this stage construction completion at McKinley Residences is anticipated to occur in Late 2019, with settlement to follow shortly thereafter.

If you have any queries in regards to settlement of your apartment, please do not hesitate to contact Bella Brown from Property Settlement Solutions on 03 8582 8979 or email bella@settlement-solutions.com.au

 

+ View More

Newman

2 Newman Ave
Carnegie
Builder:Steller
Project Manager:Steller
Anticipated Completion Date:End 2019
Expected Settlement:End 2019

Project Update

April, 2019

Construction continues to progress well and on schedule.

Completion is anticipated in the 2nd half of 2019. Please see updated photos.

Further construction updates will be provided quarterly.

Oakdon

1455 High Street
Glen Iris
Builder:Liberty Builders
Project Manager:Locandro Group
Anticipated Completion Date:May/ June 2019
Expected Settlement:Mid 2019

Project Update

May, 2019

We are pleased to advise that Oakdon Apartments is now ready for valuers to inspect your individual apartments.

Given the staging of construction we provide the following timeline as a guide to provide to your valuers.

Level 1 – Available for inspection from Wednesday 15th May 2019. (excluding 102)

Level 2 – Available for inspection from Friday 17th May 2019.

Level 3 – Available for inspection from Monday 20th May 2019. (excluding 304)

Level G, 102 & 304 – Available for inspection from Wednesday 22nd May 2019.

Please take this opportunity to speak with your broker/bank/financier and provide them with my details as listed below so that we can arrange an inspection for your valuation to be conducted;

Anna Duong 

anna@locandro.com.au 

03 9826 9908 

Once your valuer has contacted us directly we will meet them on site to assist and guide them through your property.

Thank you very much and we will provide further details shortly for the programming of Purchaser inspections which we anticipate to commence shortly after completion of the valuation inspections.

We thank you for your patience and are excited to show you your finished apartment shortly.

If you have any issues and would like to speak with the Project Manager directly, please contact Anna Duong or Dominic Locandro on 9826 9908

+ View More

Olea

50 Kambrook Road
Caulfield North
Builder:TBA
Project Manager:BNG Group
Anticipated Completion Date:Mid 2020
Expected Settlement:Mid 2020

Project Update

We are currently in the sales and marketing phase.

 Whilst sales are occurring the development team is in discussions with builders and banks to bring Olea to life.

 Construction updates will be provided quarterly.

+ View More

Parkfield

88 Dunblane Rd
Noble Park
Builder:Saw Constructions
Project Manager:BHC Property
Anticipated Completion Date:End 2019
Expected Settlement:Late 2019

Project Update

May, 2019

We are pleased to provide you with following update from the developer with the progress achieved on site so far.

TH 1-4 & 8-11: Roof frame has been completed. Ground floor brick has been completed and first-floor frame has been completed
TH 5-7: Ground floor framing
TH 12-18: Roof frame has been completed. Ground floor brick has been completed. First-floor frame has been completed
TH 19-30: Lock-up stage.

Drainage work and electricity mains have been completed at 100%.

Structural steel has been completed up to 95% and external windows doors have been completed up to 75%.

Currently anticipated settlement time will be October/November 2019.

We will keep you posted as we progress through the next phase.

 

+ View More

Pelham

54 Wattletree Road
Armadale
Builder:Figurehead
Project Manager:Pax
Anticipated Completion Date:Late August 2019
Expected Settlement:Mid-late 2019

Project Update

May, 2019

We are pleased to advise of the following update for Pelham;

The builders are progressing well onsite with the scaffold currently being removed and due for completion over the next few weeks, revealing the beautiful façade.

The joinery carcass installation is now complete, and the stone bench tops and splash backs are in the process of being installed. The timber flooring installation is well underway and the timber balcony soffits have now been completed.

The builders are also now progressing with the bathroom tiling and fixtures, and the painting throughout.

Completion of Pelham remains on track for late August, with settlements expected shortly thereafter in late August or early September. This is dependent on when the Occupancy Permit is granted and Titles are registered at the Land Titles Office.

We will continue to keep you up to date with progress over the forthcoming weeks.

 

Valuation Access

Access for valuation purposes is anticipated to be available in July. Please provide my contact details to your financier to make arrangements for access, if required, in due course:

Jenny Roche M: 0419 966 702

E: customercare@roulston.com.au

Purchaser Inspections

We anticipate inspections will commence in mid/late August. We will contact you again over the coming weeks to provide further details in relation to dates and times.

Please do not hesitate to contact the Settlement Team should you have any queries.

 

+ View More

Rostrevor Parade

97 Rostrevor Parade
Mont Albert North
Builder:TBA
Project Manager:TBA
Anticipated Completion Date:Mid 2020
Expected Settlement:Mid 2020

Project Update

We are currently in the sales and marketing phase.

 Whilst sales are occurring the development team is in discussions with builders and banks to bring Rostrevor Parade to life

 Construction updates will be provided quarterly.

+ View More

Royal Ascot

2 Mascoma Street
Ascot Vale
Builder:Marcus Group (A subsidiary of ABD Group)
Project Manager:Pomeroy Pacific
Anticipated Completion Date:Mid 2020
Expected Settlement:Mid 2020

Project Update

Works have started on site with the builder commencing site prep and the removal of contamination. The electrical substation works have been finally commissioned by Jemena. Over the coming weeks you will start to see the building activity ramp up as the builder fully mobilises to site.

McLaren Developments in conjunction with Pomeroy Pacific are committed to delivering Royal Ascot apartments for you and appreciate your continued patience as they push forward through the build.

Further updates will be provided in due course.

+ View More

St James

1A Yarra St
Hawthorn
Builder:Marcus Group
Project Manager:TBA
Anticipated Completion Date:Q3 2020
Expected Settlement:Q3 2020

Project Update

We are currently in the sales and marketing phase.

Whilst sales are occurring the development team is in discussions with builders and banks to bring St James Park to life.

Construction updates will be provided quarterly.

+ View More

The Anderson

791-795 Toorak Road
Hawthorn East
Builder:Cobild
Project Manager:Cobild
Anticipated Completion Date:June 2019
Expected Settlement:July 2019

Project Update

May, 2019

Exciting time is coming as the construction made good progress towards its completion and we are now in the last phase, if you have driven passed, you would have noticed big changes over the last a few months, as the team removed scaffolding, proceeded with the external finishes and completed all openings, the building is shaping up the Toorak/Tooronga junction with its well designed architectural form.

Our builder is on well on track of its schedule, the anticipated time for you to carry out any valuation and inspection is June/July.

UPS (Unique Property Settlements) has been appointed to work with you in relation to the settlement of your apartment purchase.

Their objective is to provide an efficient and seamless settlement of your apartment. They will work with you, and in conjunction with the developer and the builder, to coordinate valuers, solicitors and other service providers to ensure your property settles smoothly.

From this point onward, they will be communicating with you either by e-mail or telephone to update you as to construction progress, and to arrange valuation inspection, pre-settlement inspection and the other steps needed to facilitate your settlement. They will naturally be able to explain the details of the settlement process to you.

In the meantime, for any inquiry relating to settlement, please feel free to contact the Settlement Team as follows:

Amanda      amanda@upssettlement.com.au   +61 413 115 380

Felicia          felicia@upssettlement.com.au       +61 450 706 566

+ View More

The Davis

1A Davis Avenue
Camberwell
Builder:D5 Building Group
Project Manager:BHC Property
Anticipated Completion Date:Mid-late 2019
Expected Settlement:Mid-late 2019

Project Update

We are pleased to provide the progress achieved on site to date for The Davis:

External walls cladding and rendering 95% completed

– Internal walls plastering 100% completed

– Window glazing 90% completed

– Tiling to wet areas will commence this week

– Lifts installation to commence this week

Current construction progress is looking good, there is a chance that the builder may achieve practical completion in early June 2019.

If this is the case, this will bring settlement forward to take place in late June or Early July 2019.

We look forward to providing you further update in the coming months.

In preparation for the handover of your brand new townhouse at The Davis, we would love to take this opportunity to introduce you to the team at Settlement Solutions and provide you with some helpful tips to ensure that the settlement of your new townhouse is as smooth as possible.

Property Settlement Solutions has been appointed by the developer to manage the settlement and handover process of your new townhouse.

They will be your point of contact for matters leading up to the settlement of your townhouse. Settlement Solutions can provide access for bank valuers to conduct valuations and accompany you to your pre-settlement inspection. Furthermore, we are happy to assist you with any general enquiries in relation to handover and/or settlement.

Please do not hesitate to contact Monique from Property Settlement Solutions on 03 8582 8972 or email monique@settlement-solutions.com.au

 

+ View More

The Kent

382 Burwood Rd
Hawthorn
Builder:Cobild
Project Manager:HS Consortium
Anticipated Completion Date:Early 2020
Expected Settlement:Early 2020

Project Update

We are excited to let you know that the excavation of the two level basement carpark is now complete.

Some rock was found during the excavation which has delayed the construction program by approximately 2 weeks however the builder is confident this time can be made up during the balance of the construction period.

The pit for the crane has been established and the crane will be erected on site on in mid April.

Construction of the basement structure is due to be completed by the end of June 2019 and the top level (level 8) by end of October 2019.

The completion of The Kent (not settlement) is still anticipated for March/April 2020. This is subject to favourable conditions or unforeseen delays.

We will continue to keep you updated with construction progress.

If you have any queries in regards to settlement of your residence, please do not hesitate to contact Monique Maclean from Property Settlement Solutions on 03 8582 8972 or email monique@settlement-solutions.com.au.

+ View More

The Porter

1375 Burke Road
Kew East
Builder:KPA Property
Project Manager:Cold Fusion Capital
Anticipated Completion Date:May/ June 2019
Expected Settlement:June 2019

Project Update

Construction at The Porter is progressing.

  • Windows are 100% installed
  • Brick and metal cladding works have commenced, the substrates have been installed up to level 1
  • Internal plasterboard walls are complete up to level 1
  • Delivery of car stacker
  • Tiling installation has commenced
  • Joinery is currently being fabricated off-site

Next month may be stop and start with a number of public holidays on the horizon and poor weather forecasted; but we will endeavour to optimize the time we have, we expect the lift to be installed, external walls to be complete and commencement of internal fit-out.

We are pleased to inform you that  the anticipated completion of your apartment is now late-May 2019 with settlement to be in early June (subject to favourable conditions or unforeseen delays).

+ View More

The Regent

3 Whitehorse Road
Blackburn
Builder:Sycom Construction
Project Manager:Charter Keck Cramer
Anticipated Completion Date:Early- Mid 2020
Expected Settlement:Early - mid 2020

Project Update

May, 2019

The developer has provided us with the following update:

The site sewer infrastructure upgrade works are now on track to be completed by mid-May 2019 with the civil earthworks package (in ground services and roads) due to commence shortly after.

Under ideal weather conditions the civil construction period is estimated to take 6-8 weeks, commencing with site clearing and bulk earthworks followed by benching of the townhouses.

In addition, the retaining wall along the northern boundary will be constructed during phase by the civil contractor. Lot servicing infrastructure works to each stage will then begin.

We will continue to provide construction updates over the life of the project.

+ View More

The Rise

179 Blackburn Road
Doncaster East
Builder:Cobild
Project Manager:Nash Management
Anticipated Completion Date:April 2019
Expected Settlement:April 2019

Project Update

As you can appreciate there are number of critical documents that are required to be completed with relevant authorities in order to meet compliance so that The Rise can progress to settlement.

The developer is currently waiting the final authority’s to issue their final certificate, in order to be issued the Statement of Compliance from Council. Once the Statement of Compliance is issued, the developer can then lodge the Plan of Subdivision to the Land Titles Office for registration.

Once registration has occurred, then settlement can be triggered.

The developer and project team are doing everything within their capability to push these authorities through and to bring this project to completion as soon as practicable.

We respectfully request your patience and we will provide you with another update on settlement timing as soon we hear any further.
Window Furnishing

Lovelight have kindly extended their offer for orders where you will receive a 5% discount and ensure that your blinds are installed prior to settlement if you order and pay in full by 30th April 2019.

Please visit the dedicated The Rise website to complete your order online.

Please do not hesitate to contact Monique Maclean on 03 8582 8972 or email monique@settlement-solutions.com.au if you have any questions relating to this.

 

+ View More

The Royal

670-676 Glen Huntly Road
Caulfield South
Builder:Buildcept
Project Manager:TBA
Anticipated Completion Date:July 2019
Expected Settlement:July- Aug 2019

Project Update

May, 2019

The builders of The Royal have now topped out the structure. The focus now is on the fit out of the apartment floors.

  • Ground floor, wall framing, window framing, plumbing & electrical is well underway with plaster sheeting scheduled to start shortly.
  • The light weight structure to level 5 is near completion, with roofing deck scheduled for installation.

Build Cept are well on track to achieving practical completion by mid July 2019.

Approaching Settlement:

We are excited to formally introduce you to Cintcorp’s Settlement Team.

The Settlement Team are here to help prepare and guide you on your journey to settlement at The Royal, Caulfield.  The team will provide you with ongoing support, construction updates, coordinate and attend pre-settlement inspection appointments and coordinate and attend any bank valuation appointments required for finance approval.

Most importantly, the Settlement Team are your first point of contact for any questions or queries that you have moving forward. The team can be contacted by emailing settlements@cintcorp.com.au  or calling Amy on 0401 421 682

With construction progressing well, anticipated settlement is on-track to commence in July. Our team will continue to update you as we move closer to this date and construction milestones continue.

If you haven’t already, now is the time to notify your legal representatives and financiers of the upcoming settlement so that they can prepare all documentation and processes required for settlement to occur.

Our team are here to answer any questions that your legal or finance representatives have in the lead up to settlement.  Should they require any information, please pass our details onto them and we will work with them accordingly.

+ View More

Viola

390 Upper Heidelberg Road
Ivanhoe
Builder:JG King Projects
Project Manager:Nash Management
Anticipated Completion Date:Mid-late 2019
Expected Settlement:Mid-late 2019

Project Update

Over February/March, the final slabs were poured on the northern boundary lots. This required the installation of the last underground water tanks, which couldn’t be completed yet due to access requirements on the site.

In addition, these months saw the delivery of steel frames to all lots. Concurrently, timber frame delivery occurred during late March. This enabled construction of these frames to begin early April. It is anticipated that southern boundary lots will be completed in the next couple of weeks. With each email, you will notice the speed at which above ground construction takes place.

By the next update, you will see the finalisation of timber frame construction. This will make way for external lock up, when other internal work can progress.

 

+ View More

Walpole

40 Walpole Street
Kew
Builder:Cobild
Project Manager:Hub Property Group
Anticipated Completion Date:Early 2019
Expected Settlement:Early 2019

Project Update

We are pleased to advise that we are expecting to be in receipt of the Occupancy Permit within the next week or so and that settlement will occur in mid-March.

FINANCE REMINDER

If you require finance to settle your townhouse and you haven’t already, we highly recommend that you contact your preferred lender to begin the approval process.

We are able to facilitate valuation inspections from this time on. Please contact Sophie Hensman at sophie@hubpg.com.au or on 0409 384 382 if you would like to arrange a valuation inspection.

Please note that no settlement extensions will be granted. Penalty interest will apply immediately for any settlements overdue and the Vendor reserves all its rights under the Contract of Sale to issue Default Notices.

PURCHASER INSPECTIONS

At this stage we anticipate that we will be able to facilitate purchaser inspections towards the end of the first week of March.

Inspections will be 30 minutes long and will be conducted between the hours of 8:30am and 3pm, we will commence booking appointments once settlement has been called.

MOVE IN INFORMATION

For any information regarding the move in process, please refer to this document, or get in touch with Project Manager, Sophie Hensman on 0409 384 382 or sophie@hubpg.com.au

+ View More

Westend (Adderly, The Foundry, Spencer, Mailhouse)

185 Rosslyn Street
West Melbourne
Builder:Hacer
Project Manager:Urban
Anticipated Completion Date:Mid-late 2020
Expected Settlement:Mid-late 2020

Project Update

The developers advise that demolition is complete and are pleased to announce that Hacer has been confirmed as the builder for this Project.

Construction is starting to ramp up at West End with 4 bright red coloured cranes are currently being erected.

The developers have installed a camera on site which is taking photos every 15 minutes and another camera taking a photo of the entire site every day at 1pm. Please view this here for the most recent pics.

http://www.cloud9.camera/WestEndApt#

Further construction updates to follow in due course.

+ View More

Windsor Terrace

168 High Street
Prahran
Builder:Balmain Construction
Project Manager:Hub Property Group
Anticipated Completion Date:June 2019
Expected Settlement:June 2019

Project Update

Property Settlement Solutions has been appointed by Topgan to manage the settlement and handover process.

They are now your point of contact for matters leading up to settlement. We can provide access for bank valuers to conduct valuations and accompany you to your pre-settlement inspection. Furthermore, we are happy to assist you with any general enquiries in relation to handover and/or settlement.

For legal matters you must continue to liaise with your solicitor/conveyancer. Please ensure that they have a fully executed copy of your Contract of Sale.

At this stage construction completion of your apartment is anticipated to occur in the June 2019.

Please note that construction timelines are dependent on a number of variables such as weather and regulatory approvals, therefore these timings are indicative and may be subject to change.

We understand that the lead up to settlement for off the plan purchasers may be confusing. There are many different parties involved and it is not always clear whom you should contact.

Please understand that an exact settlement date cannot be provided until the Plan of Subdivision has been registered and the Certificate of Occupancy achieved.

We will ensure to keep you updated as construction progresses and we near settlement.

If you have any issues in regards to your purchase, please do not hesitate to contact Kim from Property Settlement Solutions on 03 8582 8979 or email kim@settlement-solutions.com.au with any questions that you may have

+ View More

For further enquiry or any issues, please contact:

Amy Bennison
Email : amy.bennison@marshallwhite.com.au
phone : 03 9832 1278

Please note our Concierge office hours are:

9.30 – 4.30pm on Tuesdays and Thursdays, and from
9.30 – 3pm on Fridays.

X

X

Register for instant email alerts when a property matches your criteria.