232 Wattletree

232 Wattletree Road
Malvern
Builder:Cobild
Project Manager:Neoscape
Anticipated Completion Date:Late 2019
Expected Settlement:Late 2019

Project Update

The developer informs us and is pleased to provide an update on the progress of your purchase within 232 Wattletree.

Cobild have kept the momentum through October and the basement structure is now complete. The attached photograph shows the groundfloor formwork and reinforcement almost complete and ready to pour concrete.

The developer will continue to advise on the status of construction as well as providing important information about settlement arrangements as the building approaches completion. Fortis Development Group provides monthly eDM’s. Please contact us if you have not received this.

Regular videos and updates are also put on up the on Instagram story- follow @fortisdg and click on the “232 Wattletree” button www.instagram.com/fortisdg/.

Sep 2019 is expected completion.

+ View More

308 Carlisle

308 Carlisle Street
Balaclava
Builder:VCON
Project Manager:Urban DC
Anticipated Completion Date:End Sep 2018
Expected Settlement:October 2018

Project Update

Works onsite are progressing well with valuation access now available and purchaser pre-settlement inspections likely to take place in the next 2 weeks.

Completion is currently anticipated for October depending on when Titles register and the Occupancy Permit is issued.

525 High

525 High Street
Prahran
Builder:Arc 3
Project Manager:Goldfields Group
Anticipated Completion Date:Early 2019
Expected Settlement:Early 2019

Project Update

Goldfields is pleased to report that construction onsite continues to track well.

Due some recent inclement weather – particularly high winds that have affected crane activities onsite, Arc 3 have encountered delays to construction progress at 525 High Street.

A revised program from Arc 3 is showing that construction will unfortunately no longer be completed by December 2018 as previously communicated. Whilst we still anticipate the building to be approximately 95% by the end of the year, the revised program is re-forecasting a new move-in date of mid-late February 2019.

+ View More

Akora

5-7 Kooyong Road
Armadale
Builder:Ironside
Project Manager:Nash Management
Anticipated Completion Date:Mid-Late 2019
Expected Settlement:Mid-Late 2019

Project Update

IRONSIDE have commenced procurement to ensure progress is maintained throughout the project and have started engaging trades.

The project team are currently reviewing purchaser changes with pricing to be finalised shortly. Over the coming weeks, pricing will be issued to purchasers for review. Once finalised you will be issued with a deed of variation to your contract of sale ratifying these changes. This must be returned before these works can begin. We appreciate your patience during this matter and look forward to your response.

September saw the commencement of basement retention works on site. Piling and capping beam have been completed and excavation works have commenced.

An important month with construction works ramping up. All piling works have been completed and excavation of the basement has commenced.

Project completion is anticipated for early Oct 2019 and  settlement late Oct 2019.

+ View More

Arcadian

511 Dandenong Road,
Armadale
Builder:Charles Edgar
Project Manager:Samssons Projects
Anticipated Completion Date:Mid-late 2019
Expected Settlement:Mid-late 2019

Project Update

The developer has advised us that it has been a very busy and productive past month on-site.
Most recently there have been 4 teams on site; one is doing the anchoring into the piles, one is doing the detailed pile excavation, and another doing the bulk excavation, the last team is preparing the walls to start spraying them with concrete, which should happen towards the end of this week or early next week.
The developer doesn’t anticipate any delays from all sides of the project.

+ View More

Ashton Park

338 Burwood Hwy
Burwood
Builder:Iurada Construction
Project Manager:BHC Property
Anticipated Completion Date:Mid 2019
Expected Settlement:Mid 2019

Project Update

We are pleased to advise that the development is tracking well for completion mid 2019. The developer advises that the following tasks have been completed in the current period;

Below ground works:

o Hydraulics & Civil works are complete

o Electrical works including NBN are complete and ready for connection

o Authority Connections works are currently in progress

Ground Floor:

o Ground Floor Concrete Slab preparations (Building B) are complete

o Ground Floor Concrete Slab preparations (Building A) is in progress

o Structural block walls (Building A&B) are both complete

o Formwork to Level 1 (Building B) also complete

Other:

o Steel framing (Building B) is in production

o Steel framing (Building A) Shop drawings in progress

For further information please visit http://www.bhcproperty.com/ashton-park-august-2018/

+ View More

Ballantyne

1693 – 1697 Malvern Road
Glen Iris
Builder:Citi-Con
Project Manager:Charter Keck Cramer
Anticipated Completion Date:Mid-late Oct 2018
Expected Settlement:Nov 2018

Project Update

We wish to advise and assure you that construction works are continuing to progress and the developer and builder are working towards the below anticipated completion timing.

With continual reviewing of the program and the onsite activity, the anticipated completion of your townhouse is now;

• Stage 1 (Lots 1 to 11) – Anticipated completion in late November, with settlement to follow shortly thereafter.
• Stage 2 (Lots 12 to 22) – Anticipated completion in early December, with settlement to follow shortly thereafter.

Please note that the above anticipated timing is subject to favourable conditions or unforeseen delays. Monique from Settlement Solutions will continue to provide you with regular construction updates leading up to settlement.

Financing Your Apartment

Due to the current lending changes within Australia, it is extremely important to do your due diligence with regards to financing your townhouse.

Please note: If you are settling with finance, your application should be well underway by now.

With continually changing market conditions, banks are tightening their lending criteria. Even if you have been pre-approved for a loan, you are encouraged to keep in touch with your bank or broker just to keep abreast of any lending changes that may have recently been implemented.

If you would like your bank or broker informed of valuation access, please advise of their contact details so that they may be included in the email distribution list for valuation access and availability.

We will be in touch again soon. In the meantime, please do not hesitate to contact Monique Maclean on 03 8582 8972 or email monique@settlement-solutions.com.au if you have any questions relating to this.

+ View More

Balmoral

1571 Malvern Road
Glen Iris
Builder:Cobild
Project Manager:Neoscape
Anticipated Completion Date:Mid-late 2019
Expected Settlement:Mid-late 2019

Project Update

We are pleased to provide you with an update on the progress of Balmoral.

Cobild kept their momentum through October and the basement structure is now complete. As you can see from the photo included, the ground floor formwork, reinforcement and post-tension cabling is almost complete and ready to pour concrete. We will continue to update you each month as well as provide you with important information regarding settlement as the building approaches completion.

At this stage Cobild is on schedule to complete construction in September 2019.

+ View More

Bloom

1240 Glen Huntly Road
Carnegie
Builder:Nantong Construction
Project Manager:Sam Segman
Anticipated Completion Date:Mid-late 2019
Expected Settlement:Mid-late 2019

Project Update

Bloom Glenhuntly continues to progress well.

Work is now taking place on the ground floor and at time of writing half of the ground floor is complete. Electrical, plumbing and fire subcontractors are on site now, doing rough in works. The concrete wall panel for basement has been installed.

The plan is for you to hear from the developer during the month of November with regards to any requests for variations to apartments. Thanks for your patience in this regard.

The project is expected to settle in Sep 2019.

Further construction update to be provided in December 2018.

+ View More

Centenary Apartments

817-819 Centre Road
Bentleigh East
Builder:Valeo Construction
Project Manager:Valeo Construction
Anticipated Completion Date:December 2018
Expected Settlement:Late 2018- Early 2019

Project Update

Valeo Construction is pleased to advise they have achieved their projected milestones and are tracking on Target for completion in December of this year.

Site progress Summary is as follows:

  • Services Trades (Fire, Electrical, Mechanical and Hydraulics) are 95% Completed Internally
  • Plasterer works are 100% Completed Internally
  • Finishes trades (Kitchens, Stone, Tiling, Painting and Services Fit out) are 90% Completed
  • Flooring has commenced and will be completed by the end November
  • Window Installation is 95% complete.
  • Atrium Steel has been installed and the Glass Roof has been installed
  • External Works (Cladding, Brickwork) is 90% complete
  • Balcony Balustrades have been installed
  • Landscaping works have commenced and aim to be completed mid-late November

As the construction of your apartment continues, we will endeavour to keep you updated with progress reports. If you have any queries or concerns, please do not hesitate to contact Valeo office on 03 9686 2588 or alternatively email info@valeoconstruction.com.au

+ View More

Charlemont Apartments

92 Hawthorn Road
Caulfield North
Builder:Shustin
Project Manager:Perkins Architects
Anticipated Completion Date:October2018
Expected Settlement:Mid-November 2018

Project Update

We wish to advise you of some exciting updates currently occurring at Charlemont.

The good news is that the Plan of Subdivision may be certified as early as next week and if this occurs the document will be lodged at the Land Titles Office (LTO) immediately and should be turned around within a 5 day period, as is their common practice.

Once the Plan of Subdivision is registered, settlement will be triggered. Letters will then be sent to your legal representative, requiring you to settle your apartment within the allocated timeframe. The developer will be accepting early settlements within the 14 or 21 day period.

Please note: If you are interested in settling immediately after the notice is received please ask your solicitor to notify the developers solicitor of this.

The building is looking fabulous and any noted defects have been closed out, ready for settlement.

Please contact the Settlement Company on 95306800 to arrange access to the apartments.

+ View More

East End

20 Canterbury Road
Blackburn South
Builder:Carelli Construction
Project Manager:JPS Projects
Anticipated Completion Date:Mid- late 2019
Expected Settlement:Mid- late 2019

Project Update

JPS and Bab Developments have now entered the construction phase in full swing with Carelli Construction. Site establishment and authority construction approval were completed during July and August and the Piling works commenced at the start of September. Carelli Construction are forecasting to complete the basement excavation and footings by the end of 2018.

Anticipated date of Completion at this stage is on track for October 2019

+ View More

Eastbridge

833 High Street
Kew East
Builder:TBA
Project Manager:TBA
Anticipated Completion Date:Mid 2020
Expected Settlement:Mid 2020

Project Update

The update for November is that there have been delays and that the developer is still in the process of negotiating with a few builders. They will now appoint a builder this month (November rather than previously outlined October).  Anticipated start date is now realistically early 2019.

Anticipated Date of Completion will be 2nd quarter of 2020.

+ View More

Form

21 Riversdale Road
Hawthorn
Builder:Cobild
Project Manager:Pax Project Management
Anticipated Completion Date:Mid- late 2019
Expected Settlement:Mid - late 2019

Project Update

The developer informs us they are into the second month of a 15 month build and things are tracking extremely well. The machines on site have been bulking out non stop and all concrete piles and capping beams have been constructed. The main foundations are in and things can only go up from here. It has been an ideal start to a great project and are sure things will continue to progress seamlessly.

The team from Cobild have been running a tight ship at 21 Riversdale Rd, with basement excavation close to complete. All concrete piles are in position and are held in place by the capping beam that makes for the footings to the ground floor slab. Anchors began to be installed last week and will be completed this week. Towards the end of the week the builders will begin to apply the shotcrete to the basement walls, creating a clean and crisp finish to the basement car park.
By the next update, the basement will be complete and the structure at Riversdale will have begun to come out of the ground, forming what’s to be one of Hawthorn’s iconic developments.
From the team at Moda, we are more than happy with the start we’ve had at Riversdale and are just as eager as purchasers to see the structure begin to take “FORM”

+ View More

Hank

5-9 Hanke Road
Doncaster
Builder:Stemcom
Project Manager:Nash Management
Anticipated Completion Date:Late 2018
Expected Settlement:Nov 2018

Project Update

The developer is pleased to advise that the Construction is continuing to progress well. The anticipated settlement date shall be around the end of November this year. The exact date is still to be confirmed.

For any enquiry about settlement please do not hesitate to contact Amanda Wang on 0413 115 380 or amanda@upssettlement.com.au

+ View More

Hello

82 Hawdon Street
Heidleberg
Builder:Valeo Construction
Project Manager:
Anticipated Completion Date:Late 2018
Expected Settlement:Late 2018

Project Update

The developer advises that due to builder construction issues, practical completion of the development is scheduled for 30th November 2018.

The major obstacles have been overcome, ie, connection of main power by Jemena which has held up the installation of the lift. With this now under way, it will mean that the rear of the building will be worked on as the temporary lift will be dismantled.

We have commenced the defects inspections and any rectifications required will be attended to prior to final inspections. The dates of these inspections will be advised in due course.

We therefore estimate that settlement will be the beginning of December.

+ View More

Helm

300 Burwood Road
Hawthorn
Builder:Buildcept
Project Manager:TBA
Anticipated Completion Date:Early 2020
Expected Settlement:Early 2020

Project Update

The developer is pleased to confirm that, after a lengthy tendering and vetting process in order to acquire a high-calibre, reliable Contractor, they have entered into a Letter of Intent Agreement to engage Buildcept as the Builder for the HELM Apartments.

Final Due Diligence on Buildcept’s Tender is being completed and we anticipate to have the formal Contract signed shortly

With the Soil Testing Phase now coming to an end, this is perfect timing for a seamless transition into the start of Building.  Original settlements were late 2019 and we now expect this to be within the 1st quarter of 2020, with the additional Christmas shutdown included.

+ View More

Howard West

3-11 Howard Street
West Melbourne
Builder:Sinjen Pty Ltd
Project Manager:Pomeroy Pacific
Anticipated Completion Date:Early 2020
Expected Settlement:Early 2020

Project Update

Façade retention works that were planned for October have been completed and the remainder of the demolition is now continuing. The lift core structure has been completed to height and a crane will be installed shortly. Excavation of the basement and services and ground slabs will take place once the demolition has been completed.

Note to Purchasers
We would ask that outstanding Deeds of Variation are returned by 15th November 2018, as finish trades are being finalised and approved by the end of November. Finish items with long lead times must be secured this year.

Schedule
There is no change to the schedule from the July 2018 update and completion is targeted for January 2020. As progress continues, we will keep you informed of any improvements to the schedule.

As progress continues, we will keep you informed of any improvements to the schedule.

+ View More

Jackson Street

11 Jackson Street
St Kilda
Builder:Cobild
Project Manager:TBA
Anticipated Completion Date:Mid 2019
Expected Settlement:Mid 2019

Project Update

The Jackson Street team are pleased to provide the following update in relation to the construction progress.

The basement structure has now been completed. Concrete panels have been installed on the basement slab and the suspended slab works are progressing well. The completion of the concrete structure is scheduled for the end of this year.

Jackson Street construction is still scheduled to be completed in Quarter 2, 2019.

We will provide further construction updates as the project progresses.

Vimeo Link available at: https://vimeo.com/291846751

+ View More

Luar

22-24 Pakington Street
St Kilda
Builder:TBA
Project Manager:TBA
Anticipated Completion Date:Late 2019
Expected Settlement:Late 2019

Project Update

The developer advises that demolition is about to commence.

Construction tenders are closed and the developer will shortly make an announcement regarding the builder.

At this stage looking at late 2019  for completion.

More information to come in coming weeks.

Malvern Residences

1186-1188 Malvern Rd
Malvern
Builder:Cobild
Project Manager:TBA
Anticipated Completion Date:Late 2019
Expected Settlement:Early 2020

Project Update

The developer is pleased to advise that Cobild have been appointed as the builder.

Cobild have commenced preliminary works including works with various external consultants be it the architects, engineers & authorities etc.

Demolition Works- The demolition contractor has been engaged for some time with works due to commence during November. The required protection works notices have been issued to the neighbours and the developer awaits a demolition permit.

An amended Planning Permit has been received. We anticipate purchaser change meetings to commence with the builder during the course of November

Further information will be provided in due course.

 

 

+ View More

McKinely Residences

171 Wattletree Road
Malvern
Builder:Ironside
Project Manager:Pomeroy Pacific
Anticipated Completion Date:Late 2019
Expected Settlement:Late 2019

Project Update

It is with great pleasure that we confirm that construction works have commenced for McKinely Residences. A piling rig has commenced in boring the concrete piers for the basement retention walls. Whilst other works have preceded this, the piling is a major item for the project. The builder Ironside Construction will now work continuously on site through to completion which is scheduled for the last quarter of 2019.

We and the developer understand that it has been a long wait for commencement. All our development, construction, funding and sales team have worked hard to make this happen. We appreciate the patience of our purchasers and look forward to delivering an outstanding development.

Basement excavation is currently progressing well. See photos attached.

+ View More

Nelson St

Eden Sq, Garden Sq, Yarra Sq, Yarra Townhouse; 42-58 Nelson Street
Ringwood
Builder:Hamilton Marino
Project Manager:Sunstone
Anticipated Completion Date:Early 2019
Expected Settlement:Early 2019

Project Update

Please find the latest update from the developer below:

As we are drawing near to the end of 2018, we would like to provide an update of our Nelson Street project. The construction is coming along well and has advanced into the finishes. Below are some details for your information –

What’s currently ongoing in the Apartment Buildings

* Roof waterproofing works are completed

* Joinery works are underway

* Lift Installation

* Storage cages installation

* Landscaping works started Townhouses

* Roof installation and services rough in are in progress for the Townhouses Settlement is anticipate in February 2019.

More updates will be provided after the New Year. Please note it’s important that you have made your arrangements with a finance group or bank ahead of this time to be ready for settlement.

+ View More

Oakdon

2a Scott Grove
Glen Iris
Builder:Liberty Builders
Project Manager:Locandro Group
Anticipated Completion Date:Mid 2019
Expected Settlement:Mid 2019

Project Update

The developer advises us that there are regular photography updates on instagram @tas_oakdon

A more formal update will be provided to purchasers towards the end of October. Thanks for your patience. If you have any issues and would like to speak with the Project Manager directly, please contact Anna Duong or Dominic Locandro on 9826 9908

+ View More

Olor

306-312 Swan Street
Richmond
Builder:Valeo Construction
Project Manager:Valeo Construction
Anticipated Completion Date:September 2018
Expected Settlement:October 2018

Project Update

We are informed that settlement for Olor is scheduled for the beginning of October 2018.

We are advised that Donald Rennie from Valeo Construction is managing settlement directly with you including keys, welcome packs etc.  Donald will be in touch with purchasers with further information with regards to this.

If you have any further queries please contact Donald on 03 9686 2588 or <Donald@valeoconstruction.com.au>

 

+ View More

Pelham

54 Wattletree Road
Armadale
Builder:Figurehead
Project Manager:Pax
Anticipated Completion Date:Mid-late 2019
Expected Settlement:Mid-late 2019

Project Update

Works onsite are progressing well, with Figurehead Construction having now completed the basement bored pile retention wall and the slab on the ground at basement level.  Installation of the precast concrete walls is underway on the lower levels and the first suspended concrete slab at the mid-level of the basement is complete.

The concrete slab at the Wattletree Road ground level is due to be completed at the end of this month and the concrete structure will continue to be erected over the next 4 months for completion by the end of 2018.

Construction of Pelham has commenced smoothly, and we expect this to continue through to completion. The target completion date remains on track for August 2019 with settlements shortly thereafter.

We will provide you with a further update in December.

+ View More

Royal Ascot

2 Mascoma Street
Ascot Vale
Builder:Marcus Group
Project Manager:Pomeroy Pacific
Anticipated Completion Date:Late 2019
Expected Settlement:Late 2019

Project Update

Early works have started on site already with the builder commencing site prep and the removal of contamination. The electrical substation works have been finally commissioned by Jemena. Over the coming weeks you will start to see the building activity ramp up as the builder fully mobilises to site.

McLaren Developments in conjunction with Pomeroy Pacific are committed to delivering Royal Ascot apartments for you and appreciate your continued patience as they push to resolve the issues.

Further updates will be provided in due course.

+ View More

Saint George

9-13 St Georges Avenue
Bentleigh East
Builder:Carelli Construction
Project Manager:
Anticipated Completion Date:Early 2019
Expected Settlement:Early 2019

Project Update

Construction at Saint George continues to progress well. Carelli Construction has now staged the Townhouses into front and rear groups – enabling greater efficiencies of trades on site.

At this stage completion is aiming for Q1 2019. All purchasers are able to email the dedicated project email addresses to receive further updates directly from Samuel Property: saintgeorge@samuel.com.au

+ View More

The Anderson

791-795 Toorak Road
Hawthorn East
Builder:Cobild
Project Manager:Cobild
Anticipated Completion Date:Mid-late 2019
Expected Settlement:Mid-late 2019

Project Update

The developer informs us that things are progressing well. The builder Cobild have completed the entire concrete structure, the stair core has been completed, services rough-in is ready to commence and scaffolding around the perimeter of the building has been completed. They are now ready to commence the external cladding.

Please see pictures included. At this stage anticipated completion is Q3 of 2019.

+ View More

The Courtyard

832 Doncaster Road
Builder:Maac Construction
Project Manager:
Anticipated Completion Date:Mid October 2018
Expected Settlement:End October 2018

Project Update

We confirm settlement of the Courtyard will not be taking place till early November 2018.

The developer is currently waiting on the bank to make the titles available so that they may lodge the Transfers.

Please get in touch with your solicitors as they will be receiving information direct from the vendors solicitor.

 

+ View More

The Davis

1A Davis Avenue
Camberwell
Builder:D5 Building Group
Project Manager:BHC Property
Anticipated Completion Date:Mid-late 2019
Expected Settlement:Mid-late 2019

Project Update

The developer advises that:

  • Ground floor slab is completed.
  • Wall framing to the ground floor is completed. First-floor framing underway
  • Structural steel has commenced.
  • Plaster/shaft liner has commenced.
  • Insulation installation to basement ceiling has commenced.
  • Civil drainage works have continued.
  • Hydraulic and electrical cast in/rough us underway.

Construction completion is still on track to be August 2019.

+ View More

The Kent

382 Burwood Rd
Hawthorn
Builder:Cobild
Project Manager:HS Consortium
Anticipated Completion Date:Early 2020
Expected Settlement:Early 2020

Project Update

The developer informs us that Cobild has commenced on site with the demolition of the existing building. (see pics)

At this stage completion is expected around March / April 2020.

We plan to provide regular further updates to purchasers over the coming months.

+ View More

The Porter

1375 Burke Road
Kew East
Builder:KPA Property
Project Manager:Cold Fusion Capital
Anticipated Completion Date:May 2019
Expected Settlement:May 2019

Project Update

The developer has advised that they have executed the construction contract with KPA Property and construction works have recommenced on-site.

The developers financiers have passed all the conditions precedent and we expect completion around May 2019.

We appreciate your patience through this time and we will be in touch with any further updates

+ View More

The Rise

37 Churchill Street
Blackburn East
Builder:Cobild
Project Manager:Nash Management
Anticipated Completion Date:December 2018
Expected Settlement:Mid Jan 2019

Project Update

We are advised by the developer that things are continuing to progress well. Completion is expected to be mid- December and settlement in mid- Jan.

Timeless

45 Orrong Road
Elsternwick
Builder:Cobild
Project Manager:Pax Project Management
Anticipated Completion Date:January 2019
Expected Settlement:February 2019

Project Update

The developer advises us that the scaffolding is down on the North side, unveiling what Cobild have been working on for the past 10 months.

Internal works have progressed well with all rough in and plaster works completed. Kitchens and joinery have been installed. Timber flooring will begin to be laid this week and carpets soon to follow. The apartments are looking fantastic which is a testament to the construction team and various consultants.

With only 7 weeks until Christmas, Cobild are working tirelessly to meet key deadlines. Construction is anticipated to be completed early in the new year and settlement most likely called in Febuary once titles are processed through the titles office.

We can’t wait for purchasers to call 45 Orrong Road home. We have a very exciting few weeks ahead, with stone bench tops and appliances arriving. What was just a concrete shell a few weeks back, is now fast becoming a luxury apartment.

We are extremely excited for the month ahead and encourage all purchasers to drive past the site and watch the building transform.

With settlement fast approaching, we have engaged the experts from “Settlement Solutions” to assist purchasers with the particulars surrounding the settlement process.We have used the SS team on previous projects and they are more than obliging to assist you with any query or request.

Settlement solutions will send out an introductory email shortly.

+ View More

Vanguard

781-807 Dandenong Road
Malvern East
Builder:ABD Group
Project Manager:Bensons Property Group
Anticipated Completion Date:November 2018
Expected Settlement:November 2018

Project Update

We are pleased to announce that your apartment at Vanguard will be ready to be inspected for bank finance valuation purposes from 10th October, 2018, if required.

If your bank requires a valuation inspection to be undertaken, please provide them with Carol Xu’s  contact details below in order for the bank’s valuer to contact the settlement team directly to arrange access to your apartment for valuation purposes:

Carol Xu
0438 871 773
CustomerRelations@bensons.com.au

If you have not already sent your broker or financier details to the settlement team, please do so at your earliest convenience.

As a result of the builder’s progress, settlement is now anticipated to occur in early November, 2018. The trigger for settlement will depend on when both the Occupancy Permit has been received and Titles have been registered at the Land Titles Office. Penalties will be charged for late settlement, so please ensure you are underway with your finance arrangements to avoid any unforeseen delays.

We will continue to keep you updated in the forthcoming weeks.

If you have any questions, please do not hesitate to contact the Customer Relations Team   CustomerRelations@bensonsproperty.com.au

+ View More

Viola

390 Upper Heidelberg Road
Ivanhoe
Builder:JG King Projects
Project Manager:Nash Management
Anticipated Completion Date:Mid-late 2019
Expected Settlement:Mid-late 2019

Project Update

August saw the completion of civil works on site. This critical component of the build now paves the way to begin construction on the retaining walls and slabs.

After considerable review, purchaser changes have also been finalised. Over the coming weeks, you will be issued with a deed of variation to your contract of sale ratifying these changes. This must be returned before these works can begin. We appreciate your patience during this matter and look forward to your response.

An important month of movement on site saw JG King complete the installation of services to all lots, including the electrical, gas, water, storm-water and communications infrastructure. While the photos only appear to show movement of soil above ground, it is below ground where considerable work has taken place. The white and orange pipes mark the location of each individual townhouse.

What You Can Expect Next
Over the next month you will see the site undergo rapid transformation as construction of retaining walls, underpinning of neighbouring properties and above ground work commence.

+ View More

Walpole

40 Walpole Street
Kew
Builder:Cobild
Project Manager:Hub Property Group
Anticipated Completion Date:Early 2019
Expected Settlement:Early 2019

Project Update

Construction continues to progress well with several key milestones having been achieved recently.

The builder, Cobild have made strong advancements onsite with the following being completed since we updated you last.

  • 100% Wall Framing Complete
  • 100% Windows Installed
  • 100% Services Rough In
  • External Classing Complete to Level 1 & 2
  • Level 2 Plasterboard Installed
  • Permanent Power Connected
  • Joinery placed into production

Construction completion continues to be on programme, with Settlement forecast to occur within the first quarter of 2019.

If you require finance to Settle your Townhouse and you haven’t already, we highly recommend that you contact your preferred lender to begin the approval process.
Please don’t hesitate to get in touch with Sophie Hensman on 0409 384 382 or sophie@hubpg.com for all enquires – she has replaced Alastair as Project Manager for Walpole.

We are excited to share that we have partnered with Lovelight to provide a window furnishings proposal designed especially for Walpole Street, Kew for your consideration. There are three options for you to choose from to best suit your townhouse – please click here to see the options.

If you are interested in taking up a package, we kindly request that you liaise directly with Ryan Lewis from Lovelight on ryan@lovelight.com.au or 1300 763 171. We also request that you please advise us of your intention and chosen design so we can coordinate the installation.

Packages are to be ordered by 30th November to ensure pre-settlement installation

For any questions please don’t hesitate to get in touch with Sophie Hensman on 0409 384 382 or sophie@hubpg.com for all enquires

+ View More

Westend (Adderly, The Foundry, Spencer, Mailhouse)

185 Rosslyn Street
West Melbourne
Builder:TBA
Project Manager:Urban DC
Anticipated Completion Date:Early 2020
Expected Settlement:Early 2020

Project Update

The developers advise that demolition is complete. Excavation and piling has officially commenced! It took longer than expected to obtain the building permit, however this has been achieved. Works are currently being undertaken by Nick and his team at LTE Excavations. It is a big job, spanning a block of nearly 1 hectare and comprising four separate apartment buildings and an on-site hotel, but everything is tracking well so far. With excavation now underway, all works are set to be completed in 2020, with Foundry and the Adina Hotel buildings to be completed first.

• Details of West End’s builder and terms have been agreed with West End’s Construction financier and once documentation has been finalised, an announcement will be made

+ View More

Windsor Terrace

168 High Street
Prahran
Builder:Balmain Construction
Project Manager:Hub Property Group
Anticipated Completion Date:Mid 2019
Expected Settlement:Mid 2019

Project Update

The developer has advised that in early August the level four concrete pour took place at Windsor Terrace. Since then the Alimak has been installed, site sheds have relocated from a leased premise onto the site, basement levels one and two are live with power whilst trades continue services install. Next week the level five concrete pour will take place with the ground floor walls to commence shortly after.

+ View More