1975

1975 Malvern Road
Malvern East
Builder:First Construction
Project Manager:Skyward Management
Anticipated Completion Date:October 2021
Anticipated Settlement:November/December 2021

Project Update

September, 2021

We are here to provide the progress achieved on-site to date for 1975 Malvern East. The following is the progress of the works to date:

  • Electrical- 90% completed
  • Joinery- 84% completed
  • Mechanical – 90% completed
  • Fixing – 89% completed
  • Appliances – 23% completed
  • Painting – 72% completed
  • Fixtures and fittings – 76% completed
  • Landscaping works – 70% completed

Due to the government’s new restrictions announced on Monday night, all construction sites will be shut down for 2 weeks. This will affect the completion date of your new homes.

This also delays the final council inspection before we can lodge for Titles to be registered. We are now expecting the settlement to be in late November or early December subject to the Titles being registered.

We anticipate bank valuations inspection to be conducted around late October.

Red Energy would have contacted you recently to organize the connection of electricity to your new homes. Please respond at your earliest if you have not done so already.

Red energy will need at least 20 days after your consent to connect the electricity.

We are pleased to share photos taken from the site, as below:

We shall keep you updated on progress in the coming weeks and look forward to sharing regular updates on your future home at each milestone reached.

Skyward Management
Contact Charles Lou
Mobile 0431 786 862
Email cluo@skywardmanagement.com.au

+ View More

71 Station Street

71-73 Station Street
Fairfield
Builder:Halecorp
Project Manager:Hub Property Group
Anticipated Completion Date:Q3 2022
Anticipated Settlement:Q3 2022

Project Update

September, 2021

The retaining wall part has been finished, concreting part of the bottom car park basement has commenced and the civil will commence soon.

Construction continues to progress well.

Q3 2022 estimated completion date.

Please do keep in mind that we are working through unprecedented times with covid and the most recent construction lockdown.

Further updates to come in due course from the developer.

Chloe Lewis | Project Manager
hubpropertygroup.com.au

+ View More

835

835 High Street
Armadale
Builder:Flux
Project Manager:TBC
Anticipated Completion Date:Q2 2022
Anticipated Settlement:Q2 2022

Project Update

July, 2021

We are pleased to announce the structure of 835 High is complete!

Flux have been keeping busy, despite the several Covid disruptions we have all experienced.  We are currently tracking ahead of the contract construction program and look forward to the tower crane beginning its decent in the coming months. The crane is currently lifting the large doubled glazed, full height windows into place on levels 1 & 2. These feature large scale windows weigh in at 450kg and take 9 people to physically install!

Plastering is complete on Level 1 and pre-plaster works have commenced on Levels 2 and 3. Levels 4 and 5 are well underway with rough in (Electrical, Mechanical, Hydraulic etc.) and expect to be sheeted with plaster over the coming month. The views from level 1 upwards are exceptional and even better than we anticipated.

Looking two months ahead we can expect the project to be at “lock up stage” meaning all windows are in and the building is essentially sealed.  The joinery team from Trendgosa have begun fabricating joinery for level 1 and are looking to begin joinery install in the next fortnight.

Everything on site is going very well and we look forward to bringing you the next update in a couple of months where the building will begin to look like a high end, luxury apartment building.

We have had a very productive start to the project and are eager to maintain this efficiency moving into the second half of 2021.

Please see below images for more “insite”.

+ View More

Aintree Park

1432-1436 Malvern Rd
Glen Iris
Builder:Samssons Projects
Project Manager:N/A
Anticipated Completion Date:September 2021
Anticipated Settlement:October 2021

Project Update

September, 2021

Samssons Projects would like to advise of the revised expected settlement date for the project at 1432-1436 Malvern
Road Glen Iris for October 2021.

Further confirmation will be provided 2 weeks prior to settlement.

We also now welcome all remaining Purchaser Inspections to be booked in via the below contact person.
Contact for Inspection – Feras Saad-Eddin – feras@samssons.com.au

Please also copy in Marshall White Real Estate on the below email address
Larissa.Rael@marshallwhite.com.au

Thank you and we look forward to showing you through your new apartment.

+ View More

Alma Village

244-246 Alma Road
Caulfield North
Builder:TBC
Project Manager:TBC
Anticipated Completion Date:Early 2023
Anticipated Settlement:Early 2023

Project Update

September, 2021

We are currently in the sales and marketing phase.

Whilst sales are occurring the development team is in discussions with builders and banks to bring Alma Village to life.

Construction updates will be provided quarterly.

+ View More

Arcade

393 Burwood Road
Hawthorn
Builder:TBC
Project Manager:First Urban
Anticipated Completion Date:Late 2022
Anticipated Settlement:Late 2022

Project Update

September, 2021

We are currently in the sales and marketing phase.

Whilst sales are occurring the development team is in discussions with builders and banks to bring Arcade to life.

Construction updates will be provided quarterly.

+ View More

Ascot Place

9 Newsom Street
Ascot Vale
Builder:Creation Homes
Project Manager:TBC
Anticipated Completion Date:2023
Anticipated Settlement:2023

Project Update

August, 2021

The team at Metro are excited to provide you with our first construction update for Ascot Place.

Whilst we all continue to live with a number of restrictions on our daily lives, construction sites have remained open and works commenced on site in July 21 as scheduled. Following a productive eight weeks, demolition is now complete and civil works are well underway.

At this stage our construction program has not been impacted by COVID restrictions and we remain on track to commence housing construction later this year; with the homes expected to be ready for settlement progressively from late 2022 to early 2023.

As you would appreciate, our construction program and expected settlement dates may be impacted by future work restrictions; however we will endeavour to keep you updated as construction progresses.

If you have any queries regarding the project, please continue to direct them to Larissa at Marshall White by email to larissa.rael@marshallwhite.com.au.

+ View More

Balwyn Park

7 Cherry Road
Balwyn
Builder:Cobild
Project Manager:M2 Management Group
Anticipated Completion Date:October 2021
Anticipated Settlement:October 2021

Project Update

August, 2021

Dear Purchaser,

We have outlined below the current status of the project at 7 Cherry Road, Balwyn.

On Level 1, the installation of Carpet and Balustrade Posts for the Balcony and Internal Corridor
walkway are currently underway.

The external Service Cupboard Meter Boxes and Pergola installation are nearly complete.
The Façade works are coming to completion.

The project is on track for Early October settlements. M2 will provide you with a firm date once we
are closer to the end of the project.

+ View More

Bloom

1240 Glen Huntly Road
Carnegie
Builder:Nantong Construction
Project Manager:Conrock
Anticipated Completion Date:Late 2021
Anticipated Settlement:Late 2021

Project Update

August, 2021

We have been advised by the vendor that they are progressing with construction onsite and are projected to complete construction within the next three months (subject to lockdowns, restrictions etc).

The vendor has also advised that you can visit the physical site at 1240-1248 Glen Huntly Road, Carnegie and request a site walkaround with the sire foreman.

Minter Ellison will be managing settlement and will in touch with purchasers in due course. Further photos and any updates to be provided from the developer as they progress.

As previously advised we have ceased involvement with the Bloom development, with the exception of updates on our construction portal which we will continue to share with you here on our portal.

+ View More

Boston

16 Boston Road
Balwyn
Builder:S&K Group
Project Manager:M2 Management Group
Anticipated Completion Date:Q4 2022
Anticipated Settlement:Q4 2022

Project Update

September, 2021

We are proud to provide you with an update on your upcoming new residence.

  • Piling Completed
  • Bored piers installed
  • In ground plumbing completed
  • Preparation and the installation of Capping beams to occur soon

Anticipated practical completion is quarter four of 2022.

+ View More

Botanica

488 Barkers Road
Hawthorn East
Builder:Austland Build
Project Manager:Austland Build
Anticipated Completion Date:Late 2022
Anticipated Settlement:Late 2022

Project Update

August, 2021

We are pleased to announce Botanica has sold out. Construction will start in September, demolition of the existing house will occur in the next 1-2 weeks, and then basement excavation closely after that.

The Developer has advised that a builder has been appointed, Austland Build, please see the link to check out their completed and in progress projects

www.austlandbuild.com.au

+ View More

Broadway

630 Glen Huntly Road
Caulfield South
Builder:Holm Park
Project Manager:INPG
Anticipated Completion Date:Late 2021
Anticipated Settlement:Late 2021

Project Update

August, 2021

As we are now in the final stages of pre-construction, we would like to provide an update to you on
the current project status and the tasks remaining to be closed out before construction commences on
site.

  • Unfortunately, due to Covid and extensive workload, the originally contracted builder had to rescind the construction contract that was due to commence works on site in June
  • After a new competitive tender period and a thorough review process and analysis completed
    on each tender submission, we have appointed a new builder called KSM Design & Construct
    who have extensive experience constructing similar types of projects in the bayside area
  • KSM have been personally recommended from the architect who has worked with them
    multiple times before.
  • We are currently working through updating the purchaser change requests and ensuring they
    are being incorporated into the final design documentation
  • The architect, structural engineer, civil engineer and services engineers are all working to
    provide the final detailed construction issue documentation that is required for the building
    permit
  • Protection Works Notices have needed to be re-issued to the adjoining owners in accordance
    with the requirements of the Building Act
  • The complete structural design has been finalised and dual certified by the structural
    engineers
  • All town planning permit conditions, drawings and reports have been endorsed by council
  • We are working closely with the builder to finalise all remaining items on the checklist
    provided by the building surveyor that must be provided in order for the building permit to be
    issued
  •  At this stage, we are anticipating that site establishment works (hoardings, site
    office/amenities, temporary power/water supply, site surveying, etc) will commence within the
    next 4 weeks followed shortly thereafter by construction of the foundation and car stacker pit
    works.
    We will continue to provide further updates in the coming weeks once firm dates have been agreed
    and confirmed between the design teams, the consultants, the builder and the developer.
+ View More

Candela

40 Upper Heidelberg Road
Ivanhoe
Builder:TBC
Project Manager:TBC
Anticipated Completion Date:Late 2023
Anticipated Settlement:Late 2023

Project Update

September, 2021

We are currently in the sales and marketing phase.

Whilst sales are occurring the development team is in discussions with builders and banks to bring Candela to life.

Construction updates will be provided quarterly.

Carrington Hill

101 Carrington Road
Box Hill
Builder:D5
Project Manager:BHC Property
Anticipated Completion Date:October 2021
Anticipated Settlement:October/November 2021

Project Update

September, 2021

Due to the government’s new restrictions announced on Monday night, all construction sites will be shut down for 2 weeks.

Also, the previously scheduled council’s final inspection got slightly delayed due to the recent Covid-19 outbreak in Box Hill.

Currently, council inspectors are being prioritised for vaccination in order to attend to the final inspection of Carrington Hill. Once the council completes the final inspection, we can then lodge for Titles to be registered.

Construction is already 98% completed and the builder is doing their final touches. The building team are in preparation to return to the site subject to government notices.

We are now expecting the settlement to be in late October or early November subject to the council’s inspections and the lifting of construction site restrictions.

In the meanwhile, please keep in contact with your banker and solicitors.

Please do not hesitate to contact James on 0499 799 771 or email settlement@skywardmanagement.com.au if you have any questions relating to this.

+ View More

Cascade

40 & 40a Whitehorse Road
Blackburn
Builder:Goldnest Construction
Project Manager:Skyward Management
Anticipated Completion Date:Late 2022
Anticipated Settlement:Late 2022

Project Update

August, 2021

We are pleased to advise you that the demolition works are progressing well and are due to complete soon.

We have secured Goldnest Construction as the project builder, they have completed several projects similar in size and are more than capable to deliver this project in a timely manner. We will be preparing the construction contract for signing and building permit in the coming weeks.

+ View More

Chevron One

38 Stanhill Drive
Surfers Paradise
Builder:Hutchinson Builders
Project Manager:TBC
Anticipated Completion Date:June 2023
Anticipated Settlement:June 2023

Project Update

August, 2021

We are pleased to announce the following Chevron One Residences;

– underground cabling works are now complete

– the on-site display suite will soon be moved to a new location ready for excavation works to commence.

 

+ View More

Contour

250 Wattletree Road
Malvern
Builder:Ironside
Project Manager:First Urban
Anticipated Completion Date:July 2022
Anticipated Settlement:August 2022

Project Update

September, 2021

Dear Purchaser

The design team are pleased to announce that Ironside are the appointed builders of Contour. With Ironside having worked collaboratively before with Ascui & Co and Marshall White Projects, we expect a seamless transition from an August commencement to an anticipated July – August 2022 completion. More to follow soon

Further update and site pics to come in due course from the developers.

+ View More

Custom

20 Station Street
Highett
Builder:Balmain & Co
Project Manager:M2 Management Group
Anticipated Completion Date:August 2022
Anticipated Settlement:August 2022

Project Update

August, 2021

We are pleased to share that construction is progressing well on site with builder Balmain & Co completing the piling in the first week of July, finishing up ahead of schedule.

Capping beam works have commenced, along with the construction of the retaining walls along the South and Southeast perimeter of the site. The hoarding installation is due to begin in the coming weeks, along with the first shotcrete spray.

+ View More

Daracombe

369-371 Cotham Rd
Kew
Builder:Pulitano Commercial Construction
Project Manager:N/A
Anticipated Completion Date:March 2022
Anticipated Settlement:March 2022

Project Update

August, 2021

We are pleased to pass on that the builder has been appointed for Daracombe. Pulitano Commercial Construction will build your new homes.

The builders have advised that they have started pilling, the anticipated Project completion will be March 2022 at this stage.

Further news and construction updates to come from the developer in due course.

 

+ View More

East Village Prahran

283-289 High Street
Prahran
Builder:Method Constructions
Project Manager:Prince Corporation
Anticipated Completion Date:October 2021
Anticipated Settlement:October 2021

Project Update

September, 2021

We write to update you on the current construction industry constraints and how this is affecting East Village Prahran.

The Covid work restrictions have significantly affected the construction industry, and like every other non-essential project in Melbourne, we have been impacted.

Progress slowed initially due to the Stage 4 Covid restrictions for building sites, limiting numbers to only 25% capacity of workers on site.

A further blow was yesterday’s announcement by the Victorian Government that construction will shut down in metropolitan Melbourne and other Local Government Areas currently in lockdown for two weeks from 11.59pm, Monday 20 September.

Prior to this announcement, the completion date was expected to be towards the end of November 2021, based on progress whilst working under Stage 4 restrictions.

We had a priority meeting with the Directors of Method Constructions last night, and I want to reassure you that they are working to minimize delays and are still committed to completing the project before the end of the year.

As the situation remains fluid it is very difficult to forecast a completion date with any certainty.

We apologize for any inconvenience caused, and will pass on any further information as it comes to hand.

We remain available to answer any specific questions you may have.

On a positive note we have received the Terrazzo Tiles from Italy, and the Natural Stone for the kitchens and bathrooms is expected to arrive at the Melbourne Docks this week.

Peter Mitrevski
Managing Director
peter.mitrevski@princecorp.com.au

+ View More

Gladstone Armadale

37 Gladstone Avenue
Armadale
Builder:TBC
Project Manager:TBC
Anticipated Completion Date:Late 2022
Anticipated Settlement:Late 2022

Project Update

September, 2021

We are currently in the sales and marketing phase.

Whilst sales are occurring the development team is in discussions with builders and banks to bring Gladstone Armadale to life.

Construction updates will be provided quarterly

Glenarm Square

1 Glenarm Road
Glen Iris
Builder:Hamilton Marino
Project Manager:N/A
Anticipated Completion Date:May 2022
Anticipated Settlement:May 2022

Project Update

July, 2021

Builder Hamilton Marino continues to make good progress onsite with the ground floor slab to be complete at the end of this month. Following this milestone the building structure will be visible coming out of the ground in the coming months.

DealCorp are currently working through the final communal amenity details and furniture selection with the interior and architecture teams.

Sales continue to progress well with strong interest and enquiry levels despite the recent Melbourne lockdowns.

Construction completion remains on track for mid 2022.

We look forward to keeping you up to date as key construction milestones are met.

Should you have any queries in the interim, please contact our sales manager:

Brett Hallam
0418 318 283
bhallam@dealcorp.com.au

Please also inform our settlement administrator if any of yours or your solicitor’s contact details change:

Madeleine Williams
mwilliams@dealcorp.com.au

 

+ View More

Greenwell

597 Burke Road
Camberwell
Builder:Creation Homes
Project Manager:Pomeroy Pacific
Anticipated Completion Date:November 2021
Anticipated Settlement:November 2021

Project Update

September, 2021

Dear Purchasers,

Hope you are well.

Unique Property Settlement (UPS) are pleased to advise that we have been appointed to work with you by developer in relation to the Settlement services as construction works continue at 597 Burke Road, Camberwell.

Due to current government restriction and construction progress, settlement is expected to commence late November 2021. ( For detailed information, please find the attached newsletter)

Our objective is to provide an efficient and seamless settlement of your townhouses. We will work alongside the developer, builder and yourself to coordinate valuers, solicitors and other service providers as a single point of contact that ensures your property settles smoothly.

From this point onwards, we will be communicating with you either by e-mails or phone calls to keep you updated with the construction progress, to arrange valuation inspection, pre-settlement inspection and so on.  Meanwhile, we will also explain the detailed settlement process to you and provide advice regarding the current property market dynamics and financing strategies.

Could you please provide us your contact number via e-mail?

Customer Relations Team

You will receive a call from either Felicia or Amanda who will be your point of contact should you have any queries in relation to your townhouse in the lead up to settlement.

NameFelicia                                                                                              Amanda

E-mailfelicia@upssettlement.com.au                                              amanda@upssettlement.com.au          

Mobile Number+61 450 706 566                                                         +61 413 115 380

 

+ View More

Hazel Hawthorn

368 Auburn Road
Hawthorn
Builder:Quadrant
Project Manager:TBA
Anticipated Completion Date:Mid 2022
Anticipated Settlement:Mid 2022

Project Update

August, 2021

Dear Purchasers,

We are happy to report the following works have been completed

Formwork deck for level 1 slab completed.
AFS walls for GF installed and will be poured on Wednesday.
Level 1 slab will be poured Monday 9th.
Level 1 AFS walls being delivered and install commencement on Wednesday 11th.

Aiming to pour level 2 slab end of August.

+ View More

Highmont

3 James Street
Bayswater
Builder:D5 Building Group
Project Manager:Skyward Management
Anticipated Completion Date:Mid 2022
Anticipated Settlement:Mid 2022

Project Update

September, 2021

We are pleased to share the construction progress for Highmont project.

The following is the progress of the works to date:

  • Inground drainage completed
  • The ground floor slab is predominately completed
  • AFS Rediwall is starting to take shape and steel installation are underway

As you may have already heard, all construction sites will be shut down for 2 weeks due to the government’s new restrictions announced on Monday night. We will continue to keep you updated on any change or progress on site.

Please see below photos taken from the site.

Skyward Management
Contact Charles Lou
Mobile 0431 786 862
Email cluo@skywardmanagement.com.au

+ View More

Hotham & Carlisle

99 Hotham Street
Balaclava
Builder:Paragon Development Group
Project Manager:Paragon Development Group
Anticipated Completion Date:October 2021
Anticipated Settlement:October 2021

Project Update

August, 2021

Joinery & marble have been installed to the Northern facing units. All cladding and screens to the northern facing units are now complete. The Car stacker structure is also complete.

Framing in the existing building and around the car stacker is underway. Feature curved cladding to start in the coming weeks.

Progress is continuing at a promising rate on site at 99 Hotham Street. Completion remains on track for October 2021.

For all Settlement enquiries please contact

Butterfield Conveyancing
Attn: Max
General Contact Mobile: 0412 65 82 65
info@butterfieldconveyancing.com

Further updates to come from the developer in due course.

+ View More

Hurstmon

3 Hurstmon Street
Malvern East
Builder:Kapitol Group
Project Manager:Codicote
Anticipated Completion Date:Late 2022
Anticipated Settlement:Late 2022

Project Update

August, 2021

Following a competitive construction tender, developer Landream in collaboration with project managers Codicote have today announced that high-end residential builders, Kapitol Group, have been awarded the $17 million plus construction contract to deliver Hurstmon, Malvern East. Construction due to commence in July.

“Landream always strives to engage local professionals where possible across our portfolio of projects and Hurstmon was no exception,” comments Mitchell Crawford, Senior Development Manager of Landream.

The project is set to generate work for over 450 local contractors during the construction program, along with a construction loan facility provided by Bank of Melbourne.

Kapitol Group is the builder behind Sarah Sands, a bespoke development comprising of 31 apartments on Sydney Road in Brunswick; the Church Missionary Society of Australia’s redevelopment at St Andrew’s Hall in Parkville; and also has construction underway for 20 premium apartments at Bedford Street in Collingwood.

Emphasis has been placed on the delivery and installation of the unique vertical rammed earth columns that line the front and west façade of the building.

“Rammed earth columns sit proudly on the façade of Hurstmon paying homage to the earthy tones of the site’s surrounds and defining each residence, allowing residents to have a clear sense of their home,” comments Tim Clarke, Director of Telha Clarke.

This enables the building to meld seamlessly into the local streetscape, which is filled with the abundant native greenery that Malvern East is known for.

“Traditionally only starring in luxury homes, museums, art galleries and wineries due to its bespoke nature; Hurstmon is one of the only residential developments in Victoria to feature this beautiful and sustainable natural building finish,” comments Mitchell.

In keeping with the theme of supporting local, the earth for the columns will be sourced and manufactured in the Victorian High Country through a family run business called Earth Structures, carefully selected by Landream due to their high level of expertise.

Earth Structures are responsible for many of the buildings in Victoria that feature rammed earth including the renowned Tarrawarra Museum of Art located at the Tarrawarra Estate winery in the Yarra Valley.

Hurstmon is scheduled for completion by end of 2022.

+ View More

Iramoo

7 Iramoo Street
Balwyn
Builder:Austland Build
Project Manager:TBC
Anticipated Completion Date:Mid 2022
Anticipated Settlement:Mid 2022

Project Update

August, 2021

Construction has now commenced at Iramoo.

Demolition of the original buildings has been completed, and the excavation of the basement has started on site.

Austland Build, please see the link to check out their completed and in progress projects

www.austlandbuild.com.au

+ View More

Luar

22-24 Pakington Street
St Kilda
Builder:Drakk Constructions
Project Manager:David Parsons
Anticipated Completion Date:October 2021
Anticipated Settlement:November/December 2021

Project Update

September, 2021

I am pleased to say we are still on track in accordance with the previous advice, i.e. there have been no delay events of any kind.

Completion of the building

• As the building reaches ‘Practical Completion’ (the stage when it can be occupied but for minor defects which can be rectified after occupancy) we will undertake defects inspections with purchasers so that they will have an opportunity to have any minor items rectified
• At around about the same time, the building surveyor (who issues building permits) will issue a Certificate of Occupancy
• Defects will then be rectified

Issue of titles

• In order to have the new titles issued, we need to obtain Statements of Compliance from service authorities such as electricity, water, drainage, sewer, NBN etc as well as council. This process obviously relies on timely responses from authorities which is outside of our control and can be variable
• This statement must be provided to the Titles office which will then issue titles.

As to timing, we are looking at:

• Practical Completion: early October
• Defect rectification, final clean etc: by late October
• Compliance: mid October to early November
• Settlements: mid November to early December

For all settlement valuation inspections please contact David Parsons 
M:  0407 983 241
P:  03 8676 9302
E:  
david@ppdm.com.au

+ View More

Luminess

27 Russell Street
Essendon
Builder:Drakk (Vic) Pty Ltd
Project Manager:J2 Projects
Anticipated Completion Date:October 2022
Anticipated Settlement:October 2022

Project Update

August, 2021

Please see below a summary of construction progress for August 2021;

  • Currently, construction progress is as follows;

  • B3 slab is to be poured this week

  • B2 formwork to commence

  • Walls to lift shaft and B3-B2 stairs to be set up

Should you have any further queries please contact

Jenny Lu
J2 Projects
Assistant Project Manager
Jenny@j2projects.com.au
+61 402 508 091

+ View More

Melfort

496 Glenferrie Road
Hawthorn
Builder:Pulitano Commercial Construction
Project Manager:HS Consortium
Anticipated Completion Date:February 2022
Anticipated Settlement:February 2022

Project Update

August, 2021

We are pleased to pass on the following update from the developer:

The roof will be installed the week commencing the 14th of June and progress continues well onsite.

Due to lockdown delays construction is now due for completion estimated for completion January /February 2022.

Further update to come from the developer in due course.

+ View More

Myrtle

203 Canterbury Road
Blackburn
Builder:Fynnan Pty Ltd
Project Manager:TBC
Anticipated Completion Date:TBC
Anticipated Settlement:TBC

Project Update

September, 2021

We are pleased to announce that construction has now commenced on site.

Construction updates will be provided quarterly.

Olea

50 Kambrook Road
Caulfield North
Builder:Balmain & Co
Project Manager:BNG Group
Anticipated Completion Date:Late 2021
Anticipated Settlement:Late 2021

Project Update

August, 2021

We are pleased to pass on the following update from the OLEA group:

Construction continues onsite as The building’s structure and roof have been completed. The Builder has now commenced installation of plasterboard, windows and building exterior wall. Installation of building services and lift are currently under progress. Kitchen cabinets and cupboards have been ordered and will arrived on site for installation.

A new photo of the exterior of the building is now available below

In the interim, we invite you to communicate BNG group on 1300 853 761 and ask to speak to Dina or email: Oleasales@bng.group for additional information.

For your journey Tom Hawkins will be your settlement co-ordinator. You can contact Tom on 03 8582 8972 or email to tom@settlement-solutions.com.au

+ View More

Parq

134-138 McKinnon Road
McKinnon
Builder:Fynnan Construction
Project Manager:Oxford Developments
Anticipated Completion Date:Qtr 1 2022
Anticipated Settlement:Qtr 1 2022

Project Update

September, 2021

Unfortunately we have been hit with harsh restrictions from the state government, the entire construction industry has lost 75% of staff. In saying that we have been able to maintain a tight ship and continue pushing this job the best we can.

We have designated a full time project manager and site manager to this project to ensure we stay in line with our schedule to the best of our ability.

Construction is moving fairly quickly, we are completely out of the ground now and the concrete pour for our ‘slab on ground’ is scheduled in for the first week of September.

Over the coming weeks, we will see the building sprout up very quickly, we are through the most complex stage of the build.

Once again I thank you and your patience through these uncertain times, we look forward to finishing this build just as much as you.

+ View More

Profile

1443 Dandenong Rd
Malvern East
Builder:Goldfields
Project Manager:M2
Anticipated Completion Date:September 2021
Anticipated Settlement:September 2021

Project Update

August,  2021

We are pleased to pass on the following update from the builder:

  • Stone benchtops all floors, all wet area tiles completed
  • Painting L2&3 ceilings
  • Common area lining
  • Basement ductwork
  • Cover L2 blueboard
  • External Render in progress
  • Joinery all floors
  • Plumber fit-off GF
  • Lift core cladding in progress
The majority of works have been completed for the interior and we are now progressing with cladding for the external facade. We look to finalize the majority of external work by end of this month. Due to covid lockdown, we have faced some delays from authorities as they have transitioned to working from home- we will continue to monitor if this will have any effect on the completion program. We are committed to delivering an outstanding project and appreciate the support of all our purchasers.

We are advised that the developer is anticipating September 2021 Practical Completion.

UPS Settlement firm for settlement liaison.
Amanda
amanda@upssettlement.com.au
0413 115 380
+ View More

Rose & Bird

30 Rosamond Rd
Maribyrnong
Builder:Creation Homes
Project Manager:Metro Property Management
Anticipated Completion Date:October 2021
Anticipated Settlement:October 2021

Project Update

August, 2021

Construction continues on site, and the team at Metro Property Development expect homes to be completed September 2021.

We will introduce you to our settlements team over the coming months who will take you through the settlement process and provide you with all the necessary information required to take possession of your new home.

Please contact Settlement Solutions for any valuation and purchaser inspections –

Tania Torres | Senior Settlement Coordinator

Property Settlement Solutions

P: +61 3 8582 8973  m:0400 332 306

E: tania@settlement-solutions.com.au

W: www.settlement-solutions.com.au

+ View More

Soligo

487 Whitehorse Road
Balwyn
Builder:Princi Property
Project Manager:TBC
Anticipated Completion Date:TBC
Anticipated Settlement:TBC

Project Update

August, 2021

We are currently in the process of obtaining the Building Permit.

Construction will be commencing 1 September 2021.

In the meantime, please visit the website below to view Princi’s past projects.

www.princi.property/

Ten to Twelve

10-12 Lindsay Street
Brighton
Builder:Cobild
Project Manager:Hub Property Group
Anticipated Completion Date:Qtr 2 2022
Anticipated Settlement:Qtr 2 2022

Project Update

September, 2021

Progress at Ten to Twelve is going exceptionally well!

Please see below key milestones achieved this month.

  • Stormwater street works have recommenced.
  • Window frame and glazing install to Ground Floor.
  • Piling complete for suspended footings for entry blockwork.
  • Basement rendering started (due to wet weather).
  • Waterproofing to roof area (continuing).
  • Stone cladding to front façade has commenced.

As we are continuing to progress on schedule, settlements are expected no later than Q2 2022.

If you have any questions please don’t hesitate to get in touch with Daniel Sergious at daniel@hubpg.com.au.

Kind regards,
Hub Property Group

+ View More

The Avenue

15 Landale Avenue
Croydon
Builder:First Construction
Project Manager:BHC Property
Anticipated Completion Date:Qtr 3 2022
Anticipated Settlement:Qtr 3 2022

Project Update

September, 2021

We are pleased to provide the progress achieved on site to date for The Avenue, Croydon.

  • Concrete slab is completed
  • Brickworks has been delivered on site. To commence after framing
  • Structural steel framing is anticipated to be installed soon
  • Light gauge steel to come after

There has been a delay with the steel framing due to increased demand. Construction completion is currently anticipated to be by Quarter 3 of 2022.

+ View More

Timeless

555 Burke Road
Camberwell
Builder:Balmain & Co
Project Manager:J2 Projects
Anticipated Completion Date:May 2022
Anticipated Settlement:May 2022

Project Update

September, 2021

We are pleased to provide an update on the Timeless Apartments.

• Level 3 slab poured.
• In-slab services installed to Level 2 and Level 3.
• Level 2 and 3 Precast installed.
• Level 3 LGS wall framing installed.
• Basement fire & mechanical services and lighting commenced

We shall keep you updated on progress in the coming months

+ View More

Two Eighty Waverley

280 Waverley Road
Malvern East
Builder:TBC
Project Manager:Shustin
Anticipated Completion Date:Late 2022
Anticipated Settlement:Late 2022

Project Update

August, 2021

We are currently in the sales and marketing phase.

Whilst sales are occurring the development team is in discussions with builders and banks to bring Two Eighty Waverley to life.

Construction updates will be provided quarterly.

Verse

18 -28 Wilkinson Road
Sunshine
Builder:Rise Constructions
Project Manager:Paragon Development Group
Anticipated Completion Date:October - November 2021
Anticipated Settlement:October - November 2021

Project Update

September, 2021

It is with great pleasure we share our latest construction update at VERSE:

The Northern block of townhouses (Lots 1-9) are in the final weeks with only finishing trades such as flooring, final paint touchups, landscaping & fencing to be completed before we can call for settlement.

Please see photos from site below.

We will be conducting stage settlements in blocks, with anticipated settlement dates below:

Northern Block (Lots 1-9) – Early October
Southern Block (Lots 20-30) – Middle of October
Middle Block (Lots 10-19) – Middle of November
East Block (Lots 31-37) – End of November

Please check the front page of your Contract of Sale to determine your lot number.

We will be sending regular updates to you as works progress on site.

We thank you for your patience and stay safe.

+ View More

Walmer

649 Victoria Street
Abbotsford
Builder:Hamilton Marino
Project Manager:TBC
Anticipated Completion Date:Qtr 4 2022
Anticipated Settlement:Qtr 4 2022

Project Update

August, 2021

Excavation works have continued on site at Walmer in preparation for the foundation piling and concrete footings, to erect the tower crane.

To allow the excavated material to be removed from site, over 70 truck movements per day are occurring to ensure the program is met for late 2022.

Despite the renewed lockdown, works are currently continuing onsite as per the building industry’s allowed guidelines

Our display apartment at 649 Victoria Street, Abbotsford, is available for inspection by private appointment.

We invite you to discover more about Melbourne’s most exciting riverside development

Construction updates will be provided quarterly.

+ View More

Wattle on the Park

2 Wattle Grove
McKinnon
Builder:Fynnan Constructions
Project Manager:KBMV
Anticipated Completion Date:January 2022
Anticipated Settlement:January 2022

Project Update

August, 2021

Coming out of the circuit breaker lockdown # 5 the progress on the building site continues with all trades working towards the highly anticipated lockup stage.

All the building has been covered with external scaffolding which will allow for brickwork and the exterior cladding  installation.

Now that the frame has finally been completed, the roofing will start to go on over the next two weeks.  This will make the building weather proof and we will no longer be at the mercy of nature’s elements. Electrical and plumbing (services) roughing-in have began in earnest.

Looking forward to the next 4 weeks where a lot of building progress is expected from our trusted building partners.

 

 

 

+ View More

For further enquiry or any issues, please contact:

Address: 1111 High Street Armadale VIC 3143
Email : georgie.lupson@marshallwhite.com.au
Phone : 03 9832 1197

X

X

Register for instant email alerts when a property matches your criteria.