It looks like we are still missing some information to finalise your profile. Please enter your phone number below to complete your account set up.

1 COVID19 Update

All properties
Builder:n/a
Project Manager:n/a
Anticipated Completion Date:
Anticipated Settlement:

Project Update

Dear Purchasers

By now you’re hopefully aware that the construction climate has now returned to some form of a long awaited normalcy.

Builders can now fully understand the impact of the stage four lockdown and start to plan ahead with confidence in an attempt to make up for lost time . Not all projects however have been delayed so its important you track your own individual project through our Marshall White Projects  portal ensuring your best prepared for a pending settlement.

As always, our concierge service is available to you (on the hours below) to take your calls or email inquiry.

Mondays 11.00 a.m. – 3.30 p.m., Tuesdays 9.30 a.m. – 1.00 p.m. and Thursdays.11.00 a.m. – 4 .00 p.m.

We look forward to helping you into your exciting new apartment or townhome at an early date – thank you again for allowing us to be of service to your property needs.

+ View More

1975

1975 Malvern Road
Malvern East
Builder:First Construction
Project Manager:BHC Group
Anticipated Completion Date:October 2021
Anticipated Settlement:November 2021

Project Update

February, 2021

We are pleased to provide the progress achieved on-site to date for 1975, Malvern East.

– Framing: 95% Completed

– Steelwork: 100% Completed

– Masonry works: 40% Completed

– Plumbing and electrical rough in has commenced

Project completion is still on track to be achieved by October 2021. Settlement is anticipated to be sometime in November 2021.
It is recommended start planning about finance at settlement.
Please do not underestimate the amount of time required to complete the finance process to ensure you are organized for a smooth and timely settlement.

We are pleased to attached photos taken from the site, showing the progress of the works to date.

We shall keep you updated on progress in the coming months and look forward to sharing regular updates on your future home at each milestone reached.

 

+ View More

71 Station Street

71-73 Station Street
Fairfield
Builder:Halecorp
Project Manager:Codicote
Anticipated Completion Date:Q1 2022
Anticipated Settlement:Q1 2022

Project Update

February, 2021

The retaining wall part has been finished,  concreting part of the bottom car park basement has commenced and the civil will commence soon.

Construction continues to progress well.

At this stage we are advised the developers are targeting Q1 2022 for completion.

Updated photos attached.

Further updates to come in due course from the developer.

+ View More

835

835 High Street
Armadale
Builder:Flux
Project Manager:TBC
Anticipated Completion Date:Q3 2021
Anticipated Settlement:Q3 2021

Project Update

December, 2020

We are pleased to pass on the following update from the developer regarding 835 High Street, Armadale:

We hope you and your family are well and are planning a well deserved break after a trying 2020.

We are very fortunate that the team at Flux have been relatively unhindered on site and have made huge progress over the last few months. Everything on site to date has been clinical, with the basement now completely excavated, shotcrete basement walls completed and the tower crane erected; now forming part of the Armadale skyline. Flux hope to have both the basement slab and first suspended slab (Basement 1) poured this year and early in the new year they will begin works on the upper levels, which is very exciting. We encourage you to drive past the site whenever you can, as the building will begin to take shape at a rapid rate.

The tower crane was commissioned last week and is already in full swing. Erecting the crane is a huge milestone for the project and we are happy to report everything went exactly according to plan.

We are in a great position coming into the new year and look forward to another very busy year on site.

We wish you and your family a happy holiday and we look forward to the next update in early 2021. Please feel free to get in touch should you have any queries.

+ View More

Aintree Park

1432-1436 Malvern Rd
Glen Iris
Builder:Samssons Projects
Project Manager:TBA
Anticipated Completion Date:April/ May 2021
Anticipated Settlement:April/ May 2021

Project Update

March, 2021

We are advised from the developer that anticipated completion date at this stage is on track for April/ May 2021.

 

Please contact Sarah Lewis from Sampssons Projects for all settlement enquiries
email sarah@samssons.com.au

Further updates to come from the developer in due course.

+ View More

Anderson Park

585 Burke Road
Camberwell
Builder:Ironside
Project Manager:Nash Project Management
Anticipated Completion Date:May 2021
Anticipated Settlement:May 2021

Project Update

February, 2021

Please find the below update for Anderson Park from the developer:

  • The first apartment has just been completed
  • Ground Floor Apartments have now received their first coat of paint and joinery installation has started.
    • Joinery is being provided from a local manufacturer and we are particularly happy with the quality of what’s been received
  • Wall + Ceiling Sheeting is progressing through the building
  • Bathroom waterproofing and tiling works have just commenced
  • Scaffold to the building exterior is completely installed, allowing for installation of façade feature prick and rendered cladding panels, which is now progressing nicely
  • Installation of the building lift, by the team at Schindler, has been underway for the last 2 weeks
  • Roof mounted plant (AC Units, Hot Water, Solar Panels) are being installed

All in all things progressing very well and we remain on track to have Owners into their apartments late Q2 2021

 

 

+ View More

Arcade

393 Burwood Road
Hawthorn
Builder:TBC
Project Manager:First Urban
Anticipated Completion Date:Mid 2022
Anticipated Settlement:Mid 2022

Project Update

February, 2021

We are currently in the sales and marketing phase.

Whilst sales are occurring the development team is in discussions with builders and banks to bring Ascot Place to life.

Construction updates will be provided quarterly.

+ View More

Ascot Place

9 Newsom Street
Ascot Vale
Builder:TBC
Project Manager:TBC
Anticipated Completion Date:2023
Anticipated Settlement:2023

Project Update

February, 2021

We are currently in the sales and marketing phase.

Whilst sales are occurring the development team is in discussions with builders and banks to bring Ascot Place to life.

Construction updates will be provided quarterly.

+ View More

Balwyn Park

7 Cherry Road
Balwyn
Builder:Cobild
Project Manager:M2mg
Anticipated Completion Date:October 2021
Anticipated Settlement:October 2021

Project Update

February, 2021

We pleased to pass on the below update from the developer:

Construction is underway –  there are no delays to the plan at this stage and progress continues on site.

A series of updated pictures are included and a further construction update to come.

+ View More

Beckworth

184-186 Tooronga Road
Glen Iris
Builder:Harris HMC
Project Manager:Point Polaris
Anticipated Completion Date:Late March 2021
Anticipated Settlement:Late March 2021

Project Update

December, 2020

Please find the latest update from the developer below:

At this stage, the anticipated settlement date is still mid to late March.

By the end of this month, we should be able to achieve the following milestones

  • Roof and external cladding
  • Timber flooring and carpet to Level 1
  • Joinery Installation to Level 1 commenced
  • Plastering to level 2

 

Chris Yang

Project Development Coordinator

Point Polaris

L19, 390 St Kilda Road
Melbourne VIC 3004

P:  +61 3 8866 8888 | M: +61 430 068 166

E:  chris.yang@pointpolaris.com.au

W: www.pointpolaris.com.au

Further updates to come from the developer in due course.

+ View More

Bespoke

1394 Malvern Road
Glen Iris
Builder:Manresa Constructions
Project Manager:TBA
Anticipated Completion Date:Mar 2021
Anticipated Settlement:Mar 2021

Project Update

February, 2021

Due to the covid-19 restrictions,  Completion is likely be in March 2021.

KIN Property is the settlement coordinator for Bespoke Apartments and is in touch with purchasers directly.

If any purchasers have any settlement queries, please contact Netta via email at: bespokeapartments@kinproperty.com.au

 

+ View More

Bloom

1240 Glen Huntly Road
Carnegie
Builder:Nantong Construction
Project Manager:Conrock
Anticipated Completion Date:April 2021
Anticipated Settlement:April 2021

Project Update

February, 2021

We are pleased to pass on an update for Bloom; 1240 Glen Huntly Road, Carnegie. We are advised that construction has continued over the past few months well and the builders advise that they are pushing and are hoping to be close to completion in April. That is what site is telling me. Minter Ellison will be managing Settlement and will be in touch with purchasers in due course. Further photos and any updates to be provided from the developer as they progress.

For those who require additional information, the builder (Sam) or Aaron is available on site to assist with most queries.

As previously advised we have ceased involvement with the Bloom development, with the exception of updates on our construction portal which we will continue to share with you here on the portal.

 

+ View More

Boston

16 Balwyn Ave
Balwyn
Builder:TBC
Project Manager:M2
Anticipated Completion Date:Q4 2021
Anticipated Settlement:Q4 2021

Project Update

March, 2021

Demolition commenced Friday 27th February please continue to check this portal for further updates.

Whilst sales are occurring the development team is in discussions with builders and banks to bring Boston to life.

Construction updates will be provided quarterly.

+ View More

Broadway

630 Glen Huntly Road
Caulfield South
Builder:Holm Park
Project Manager:INPG
Anticipated Completion Date:Late 2021
Anticipated Settlement:Late 2021

Project Update

March, 2021

We would like update you on the progress on your new home at Broadway.

The developer and the appointed builder are currently in the process of obtaining all the relevant consents from the authorities. Commencement of demolition has been delayed due to the Relevant Authorities required works taking longer than advised, this is due to the current backlog of projects during the COVID-19 restrictions. Although, with persistent correspondence from the development team the power authority is now providing a clearer timeframe, with our nominated electrician scheduled to undertake works next week to progress with disconnecting power required during Construction. The development team continue to work closely with the Relevant Authorities to complete their respective works, which will enable demolition and construction to closely follow. Demolition of the site is planned for March.

Further updates and images to come from the developer in due course.

+ View More

Carrington Hill

101 Carrington Road
Box Hill
Builder:D5
Project Manager:BHC Property
Anticipated Completion Date:Q3 2021
Anticipated Settlement:Q3 2021

Project Update

February, 2021

We are pleased to provide the below project update for Carrington Hill
Building C – 80% complete. Awaiting joinery and internal finishes to be installed.
Building B – 60% complete. Expecting to be locked up with glazing in a few months. Internal services rough-ins are progressing simultaneously.
Building A – 40% complete. Expecting to complete framing in the next month

For more live updates, please visit our project management company Instagram https://www.instagram.com/skywardmanagement/

We will continue to provide you with regular construction updates leading up to settlement.

The developer will be in touch in due course with further updates.

 

+ View More

Central Park

2A Nyora Street
Malvern East
Builder:Figurehead
Project Manager:Pax Project Management
Anticipated Completion Date:March 2021
Anticipated Settlement:April 2021

Project Update

March, 2021

We are pleased to announce that your apartment is now ready to accept bank valuation bookings. Please see booking dates listed below:

Ground floor & level 1 commencing Thursday 11th March 2021.
Level 2 commencing Monday 15th March 2021.

If your bank requires a valuation inspection to be undertaken, please provide them with my contact details to arrange access for the valuer:

Jackie Zandveld
M: 0438 812 800
E: customercare@roulston.com.au

If you have not already sent your broker or financier details to the Settlement Team, please do so at your earliest convenience so we can keep them updated with settlement timing.

Purchaser Inspections:
When your apartment at Central Park is complete and access has been confirmed, we will invite you to your Pre-Settlement Inspection. This will be your only opportunity to view your apartment prior to settlement.  We are now anticipating Pre-Settlement Inspections to commence late-March.  We will contact you again shortly to confirm timings and arrange a convenient time for you to inspect prior to your settlement.

+ View More

Chevron One

38 Stanhill Drive
Surfers Paradise
Builder:Hutchinson Builders
Project Manager:TBC
Anticipated Completion Date:June 2023
Anticipated Settlement:June 2023

Project Update

January, 2021

We are pleased to announce the commencement of underground electrical works at Chevron One Residences.

The works, which commenced on site last week, are the first step in the construction programme and will consist of trenching and excavation, paving the way for new electrical services to be installed.

+ View More

Contour

250 Wattletree Road
Malvern
Builder:TBC
Project Manager:First Urban
Anticipated Completion Date:Q2 2022
Anticipated Settlement:Q2 2022

Project Update

February, 2021

Demolition work is complete on-site. Please see photos attached.

Further update and site pics to come in due course from the developers.

Custom

20 Station Street
Highett
Builder:TBC
Project Manager:TBC
Anticipated Completion Date:Q2 2022
Anticipated Settlement:Q2 2022

Project Update

February, 2021

We are currently in the sales and marketing phase.

Whilst sales are occurring the development team is in discussions with builders and banks to bring Custom to life.

Construction updates will be provided quarterly.

+ View More

Daracombe

369-371 Cotham Rd
Kew
Builder:Pulitano Commercial Construction
Project Manager:TBA
Anticipated Completion Date:March 2022
Anticipated Settlement:March 2022

Project Update

February, 2021

We are pleased to pass on that the builder has been appointed for Daracombe. Pulitano Commercial Construction will build your new homes.

The builders have advised that they have started pilling, the anticipated Project completion will be March 2022 at this stage.

Further news and construction updates to come from the developer in due course.

 

+ View More

East End Ringwood

30 Maroondah Highway
Ringwood
Builder:TBC
Project Manager:TBC
Anticipated Completion Date:Q1 2023
Anticipated Settlement:TBA

Project Update

February, 2021

We are currently in the sales and marketing phase.

Whilst sales are occurring the development team is in discussions with builders and banks to bring East End Ringwood to life.

Construction updates will be provided quarterly.

+ View More

East Village Prahran

283-289 High Street
Prahran
Builder:Method Constructions
Project Manager:Prince Corporation
Anticipated Completion Date:Late August 2021
Anticipated Settlement:Late August 2021

Project Update

February, 2021

Construction has had some delays in construction due to some suppliers and manufacturers that were affected by the pandemic.

At this stage completion is expected late August 2021.

The directors at Method Constructions are still confident that we will be able to make up some time, particularly by engaging mainly local manufacturers that are less reliant on shipping and border restrictions.

All basement retention works have been completed including piling and anchoring, the bulk excavation down to the bottom of the second basement has been completed and, the concrete has been poured for the lift core, and crane base.

Currently the civil and drainage works of the lower basement are being done, as seen in the attached photo.

 

+ View More

Gardenia Park

8 Genista Avenue
Boronia
Builder:Batbuild
Project Manager:BHC Property
Anticipated Completion Date:May 2021
Anticipated Settlement:June 2021

Project Update

February, 2021

We are pleased to provide the progress achieved on-site to date for Gardenia Park.
– External claddings, 95% completed
– Plumbing and electrical rough in, 100% completed
– Plasterboard and insulation installation, 70% completed
– Internal doors installation, 40% completed
– Waterproofing to wet areas, 40% completed
– External hard landscape works will commence next week

Completion is currently forecasted to be in late May 2021.
We anticipate settlement to take place sometime in June 2021.

Please note timings are always anticipated and an exact settlement date will not be known until the Plan of Subdivision has been registered with the Titles Office and the Certificate of Occupancy achieved, and settlement is called. Our solicitors typically provide 2 weeks’ notice in advance for settlement date.

It is recommended to commence the finance process now if you require one. Please do not underestimate the amount of time required to complete the finance process to ensure you are organized for a smooth and timely settlement.

We are pleased to introduce Skyward Settlement Management who will be assisting with settlement at Gardenia Park. Danny or James will be in touch to co-ordinate bank finance valuations (if required), pre-settlement inspections and any other queries you may have to ensure smooth settlement.

We are pleased to attached photos taken from the site this week, showing the progress to date.

 

+ View More

Glenarm Square

1 Glenarm Road
Glen Iris
Builder:Hamilton Marino
Project Manager:TBC
Anticipated Completion Date:Q1 2022
Anticipated Settlement:Q1 2022

Project Update

February, 2021

DealCorp are pleased to share that appointed builder, Hamilton Marino have completed the piling works onsite with major excavation works to follow in the coming months.

The sales team have seen a great start to 2021 with record sales and interest in the project.

Should you have any queries in the interim, please contact our sales manager, Brett Hallam:

0418 318 283
bhallam@dealcorp.com.au

 

 

+ View More

Greenwell

597 Burke Road
Camberwell
Builder:Creation Homes
Project Manager:Pomeroy Pacific
Anticipated Completion Date:Late 2021
Anticipated Settlement:Late 2021

Project Update

January, 2021

We are pleased to pass on the following update from the developer below:

  • Basement stripped
  • GF and FF structural steel complete
  • GF frames to TH 6-10
  • Concrete stairs poured to middle section (incl emergency stairs )

Further updates to come in due course.

 

+ View More

Hazel Hawthorn

368 Auburn Road
Hawthorn
Builder:Quadrant
Project Manager:Fraser from APD Projects
Anticipated Completion Date:Mid 2022
Anticipated Settlement:Mid 2022

Project Update

March, 2021

We are pleased to announce that council plans have been approved and construction will be commencing on site this week.

Helm

300 Burwood Road
Hawthorn
Builder:FourSquare
Project Manager:TBA
Anticipated Completion Date:March 2021
Anticipated Settlement:March 2021

Project Update

February, 2021

We are expecting an update from the developer very soon, however are advised in the meantime that Settlement is expected in mid March 2021.

For any queries please do not hesitate to contact Danielle Stukenborg ‎[DStukenborg@mcdb.com.au]‎

Previous update below:

Dear Helm Apartment Owner,

If you have driven past HELM in the last couple of weeks you will note that the external façade of the building has been completed, however there are a few panels of glass that still need to be inserted.

The entrance, apart from the staining of the front door, is virtually completed – other than one final application of render.  We have attached some photos for you so you can see the welcome you will receive as you arrive home to the HELM building!  There will be protective floor coverings in the reception area whilst construction traffic continues.

Internally, the building is approximately 90% complete.  The Builders – FourSQ – are closing for Christmas on 22 December 2020, and are scheduled to recommence on 4th January 2021.

The anticipated inspection dates and completion dates as referenced in our last Construction Update ( No. 12) remain the same. “At this point, we anticipate being able to welcome all Purchasers for your own personal inspections of your respective Apartment in the week of 23 – 30th January 2021, with Settlement then likely to take place around the first-second week of February 2021.”

It is fair to say the external appearance of the Building looks amazing and, when internal works are complete, it will be equally as breathtaking.

We have organised an independent organisation, Property Settlement Solutions, to conduct with you your pre-settlement inspection.  Our contact at Property Settlement Solutions is Zoe Mills, who is very experienced in these matters.  Any defects identified during the inspection will be included in the report she prepares which will be provided to all parties ( Builder, Developer and you, the Purchaser) which then, subject to review and acceptance by the Builder, those defects will be attended to and completed prior to settlement.

We will provide you with her contact details in the New Year.

Lastly, it has been our pleasure assisting each of you throughout the Construction Process and we thank you for your on-going support and understanding now that we are entering the final phase of the build.  From all of us at the Delmo Group, we wish you and yours a wonderful, safe Festive Season and a joyous start to 2021.

Please do not hesitate to contact Danielle if you have any questions. Danielle Stukenborg ‎[DStukenborg@mcdb.com.au]‎

+ View More

Highmont

3 James Street
Bayswater
Builder:D5 Building Group
Project Manager:Skyward
Anticipated Completion Date:Q4 2021
Anticipated Settlement:Q4 2021

Project Update

February, 2021

The Developer has advised that a builder has been appointed,  D5 Building Group, please click link and check out their completed and in progress projects. https://d5build.com.au/

Demolition has now commenced. Further updates to be provided by the developer in due course.

+ View More

Hotham

99 Hotham Street
Balaclava
Builder:Paragon Development Group
Project Manager:Paragon Development Group
Anticipated Completion Date:Early - Mid 2021
Anticipated Settlement:Early - Mid 2021

Project Update

February, 2021

Progress is continuing at a promising rate on site at 99 Hotham Street. Completion remains on track for mid 2021.

Further updates to come from the developer in due course.

Hudson Green

6 Hudson Street
Caulfield North
Builder:Shustin
Project Manager:Shustin
Anticipated Completion Date:Mid March 2021
Anticipated Settlement:March 2021

Project Update

February, 2021

Please find attached the update from the developer:

2020 has been a trying year for all of us, but despite all the challenges we have been able to continue to focus on completing Hudson Green to the highest level of craftsmanship.

With joinery nearly complete, internal fitments are progressing well and it is starting to feel more and more like home.

External works are taking huge strides, with tiling and fencing complete, we will be starting landscaping in the coming weeks. The front façade is coming along with the hope to complete all common area works over the next month.

On site works are completed to have all utilities connected with connections to take place within next few weeks. We are aware that all major utility companies are overwhelmed by post COVID lockdown demand for new connections, but we remain optimistic to achieve our targets.

Interior construction: We are progressing with submission of required documentation to have the Plan of Subdivision approved by the relevant authority and will be hoping to avoid any lengthy delays due to the backlog of applications currently experienced by all local councils.

If you have any queries please do not hesitate to contact us on 9530 6800
or via email info@shustin.com

Photos included show the progress of the site.

Should you have any queries please contact us on 9530 6800 or info@shustin.com

 

+ View More

Hurstmon

3 Hurstmon Street
Malvern East
Builder:TBC
Project Manager:Codicote
Anticipated Completion Date:Q4 2022
Anticipated Settlement:Q4 2022

Project Update

February, 2021

We are currently in the sales and marketing phase.

Whilst sales are occurring the development team is in discussions with builders and banks to bring Hurstmon to life.

Construction updates will be provided quarterly.

+ View More

Iramoo

7 Iramoo Street
Balwyn
Builder:TBC
Project Manager:TBC
Anticipated Completion Date:Mid 2022
Anticipated Settlement:Mid 2022

Project Update

February, 2021

The Developer has advised that a builder has been appointed, Lang and Associates, please click link and check out their completed and in progress projects. www.langandassociates.com.au

+ View More

Lothian Street

141 Arden Street
North Melbourne
Builder:Bear Projects
Project Manager:Exelon Projects
Anticipated Completion Date:November 2020
Anticipated Settlement:November 2020

Project Update

February, 2021

We are now in the process of registering titles with the land titles office, having recently received some key council approvals. We are optimistic we can proceed with calling for settlement late February.

As you know our builder is experiencing some delays on site, and we are working with them to close out the project as soon as possible.

If you need to get in touch or have any queries, I will be available by phone to discuss any matters relating to settlement.

Settlement will be managed by Luke Melican who can be contacted on 0448 745 544 with any queries.

+ View More

Luar

22-24 Pakington Street
St Kilda
Builder:Drakk Constructions
Project Manager:David Parsons
Anticipated Completion Date:Q2 2021
Anticipated Settlement:Q2 2021

Project Update

February, 2021

Since our last update, construction has continued at a very pleasing pace. As we have advised previously, now that factors largely beyond our control such as contamination and ground water have been resolved, we have lost virtually no time.  Any delays caused by weather (heat or rain) or COVID-19 for instance have been made up and our target remains for construction and settlements to be completed in the 3rd quarter of this year. On site, the structure is complete and the roof has been installed. Glazing, services rough – in and plastering is underway from the ground level up.

+ View More

Luminess

27 Russell Street
Essendon
Builder:TBC
Project Manager:TBC
Anticipated Completion Date:Q4 2021
Anticipated Settlement:Q4 2021

Project Update

December, 2020

We have been provided the following update from the developer:

I am pleased to advise after spending a protracted amount of time with council to meet some new legislation around parking requirements, we now have our plan endorsed.

We have also appointed a builder on an early works contract and have all our building permits in place.

You will see some early work over the next month, with construction commencing in earnest in the next 8 weeks.

Obviously this is assuming that the government restrictions relating to Covid19 do not further impact our program.

Should you have any further concerns, you can contact Lee, Development manager on lee@urbanpropertyfinance.com.au or call 0418 555 265

+ View More

Melfort

496 Glenferrie Road
Hawthorn
Builder:Pulitano Commercial Construction
Project Manager:HS Consortium
Anticipated Completion Date:Q2 2021
Anticipated Settlement:Q2 2021

Project Update

February, 2021

We are pleased to pass on the following update from the developer:

The crane has been erected, the Basement carpark complete and the First level slab poured and progress continues well onsite.

Construction is on track for completion in September 2021

Further update to come from the developer in due course.

 

+ View More

Olea

50 Kambrook Road
Caulfield North
Builder:Balmain & Co
Project Manager:BNG Group
Anticipated Completion Date:Late 2021
Anticipated Settlement:Late 2021

Project Update

February, 2021

We are pleased to pass on the following update from the OLEA group:

The Project of the Olea Residences (44-54 Kambrook Rd, Caulfield North) is currently under construction. The anticipated completion date is the end of 2021.

As previously advised Marshall White Projects is no longer the sales agent for OLEA however the project will however remain on our construction portal with quarterly updates and some site photos supplied by BNG group.

Please see latest photos attached.

In the interim, we invite you to communicate BNG group on 1300 853 761 and ask to speak to Dina or email: Oleasales@bng.group for additional information.

 

+ View More

Parq

134-138 McKinnon Road
McKinnon
Builder:Fynnan Construction
Project Manager:Oxford Developments
Anticipated Completion Date:November 2021
Anticipated Settlement:November 2021

Project Update

February 2021

 

After commencement of construction last year, we pushed through the Christmas break only stopping work for the main public holidays.

We have not completed our plumbing civil works to 95%. The plumbers will be wrapped up in the ground next week.

The next stage of the construction is the excavation which will begin next week, this process will take approximately 4 weeks.

When our excavation is complete the building will sprout out of the ground pretty quickly as our focus will be on the concrete structural walls.

+ View More

Profile

1443 Dandenong Rd
Malvern East
Builder:Goldfields
Project Manager:M2
Anticipated Completion Date:July 2021
Anticipated Settlement:August 2021

Project Update

February, 2021

We are pleased to pass on the following update from the builder:

  • All structural completed
    • Pour main entry stairs and stairs lobby to basement
    • Metal wall frame to level 3
    • External wall frames GF and level 1
    • Plumbers complete stacks and drains to GF
    • Fire service rough-in to GF and basement
    • Fire-rated plaster to external walls and GF party walls
    • Hydraulic, electrical and mechanical rough-in to start on level 1
    • Start windows to GF

We are advised that the developer is anticipating late July- Aug 2021 Practical Completion.

+ View More

Rose & Bird

30 Rosamond Rd
Maribyrnong
Builder:Creation Homes
Project Manager:Metro Property Management
Anticipated Completion Date:Early - Mid 2021
Anticipated Settlement:Early - Mid 2021

Project Update

February, 2021

Construction continues on site, and the team at Metro Property Development expect homes to be ready to settle progressively from early 2021 to late 2021.

We will introduce you to our settlements team over the coming months who will take you through the settlement process and provide you with all the necessary information required to take possession of your new home.

Please contact Settlement Solutions for any valuation and purchaser inspections –

Tania Torres | Senior Settlement Coordinator

Property Settlement Solutions

P: +61 3 8582 8973  m:0400 332 306

E: tania@settlement-solutions.com.au

W: www.settlement-solutions.com.au

+ View More

St James Park

1A Yarra St
Hawthorn
Builder:Marcus Group
Project Manager:TBA
Anticipated Completion Date:March 2021
Anticipated Settlement:March 2021

Project Update

February, 2021

Following the Victorian Government’s snap lockdown decision announced last Friday, construction at St James Park has returned to full capacity. Apartment joinery installation is now complete, with the Signorino natural stone mostly complete to kitchens, bathrooms and living rooms. The Miele kitchen appliances have now been delivered to site and have commenced installation to all apartments, in addition to the BBQ’s to all apartment’s balconies and rooftops. Landscaping work is now also complete to all balcony and rooftop planter boxes.

The residential lobby area is nearing completion with all stone flooring and carpet installed. Currently, the defecting process is now occurring with builder working to ensure all apartments at St James Park are delivered to highest possible level. We are still forecasting settlement for March 2021; however, this will largely be dictated and subject to final authority approval.

Our Customer Relations Team at Catalyst Settlements will continue to be in touch and will be providing further information soon regarding the upcoming purchaser and valuation inspections. In the meantime, they will be your best point of contact for all your settlement related questions.

+ View More

Surrey Gardens

288 Canterbury Road
Surrey Hills
Builder:Stosius Constructions
Project Manager:Nicky Keating
Anticipated Completion Date:April 2021
Anticipated Settlement:April 2021

Project Update

February, 2021

Construction work is progressing on site at Surrey Gardens, within the COVID-19 guidelines. We are currently able to have a more contractors on site with the slight easing of restrictions.

We anticipate completion around March 2021. However, this date may vary with the ever changing government restrictions.

Please contact Nicky Keating for any valuation inspection bookings on 0412 646 375

+ View More

Tailor

481-491 Victoria St
West Melbourne
Builder:Manresa Constructions
Project Manager:TBA
Anticipated Completion Date:August 2021
Anticipated Settlement:August 2021

Project Update

March, 2021

Structural work is now complete and the crane is no longer needed and off-site with the team at Manresa now firmly focused on façade and interior works. The task of hand laying almost 40,000 bricks has begun on the Victoria Street and Silk Place façade. Stud work is complete on lower levels and plastering is soon to begin. We anticipate building completion to be handed over in July this year which will equate to settlements in August.

Construction updates will be provided quarterly.

+ View More

Ten to Twelve

10- 12 Lindsay Street
Brighton
Builder:Cobild
Project Manager:Hub PG
Anticipated Completion Date:Early 2022
Anticipated Settlement:Early 2022

Project Update

February, 2021

Cobild have hit the ground running in 2021 and construction at Ten To Twelve, Brighton is off to a great start.

We are pleased to give you the following progress update:

  • Basement excavation is nearing completion and construction of the retaining walls is underway.
  • All remaining soil from the excavation will be removed from site by end of today.
  • In-ground services are due to start next week.
  • Pad footings and steel installation commencing next week.

Based on the current progress, settlements are expected no later than Q2 of 2022.

If you have any questions please don’t hesitate to get in touch with Daniel Sergious at daniel@hubpg.com.au.

 

+ View More

Timeless

555 Burke Road
Camberwell
Builder:Balmain & Co
Project Manager:J2 Projects
Anticipated Completion Date:May 2022
Anticipated Settlement:May 2022

Project Update

February, 2021

We are pleased to pass on to our purchasers that the builder Balmain & Co. have commenced construction and further updates and news to come in due course from the developer.

Verse

18 -28 Wilkinson Road
Sunshine
Builder:Rise Constructions
Project Manager:Paragon Development Group
Anticipated Completion Date:Q2 2021
Anticipated Settlement:Q2 2021

Project Update

February, 2021

We are advised that the construction team are looking to complete all frames to the Southern townhouses before Christmas.

Will start the mid-block frames shortly.

The frames for the East block townhouses will start Mid-Jan 2021.

Still on track for middle of 2021 completion.

We will provide a further update in due course. Latest photos attached.

+ View More

Wattle on the Park

2 Wattle Grove
McKinnon
Builder:Fynnan
Project Manager:KBMV
Anticipated Completion Date:Late 2021
Anticipated Settlement:Late 2021

Project Update

February, 2021

We are pleased to announce that Fynnan Constructions has been appointed as the builder for Wattle on the Park. Work has now commenced on site with slab now complete.

Thankyou for your patience and we will pass any further update on as we are provided it.

 

 

 

+ View More

Westend (Adderly, The Foundry, Spencer, Mailhouse)

185 Rosslyn Street
West Melbourne
Builder:Hacer
Project Manager:Urban
Anticipated Completion Date:Mid-Dec 2020
Anticipated Settlement:Mid-Dec 2020

Project Update

February, 2021

If you require finance to settle your apartment your lender may require a bank valuation inspection to be carried out in order to complete the loan application.

Valuers must contact Tom Hawkins on 03 8582 8972 or email tom@settlement-solutions.com.au to make an appointment.

* Please note that these inspections are for bank valuers only. 

Your new address and proposed settlement dates are listed as follows:

Building/Location New Address Approved by Melbourne City Council Proposed Settlement Date
The Main Arcade Wominjeka Avenue Due for Completion in April 2021
The Public Park West End Square Due for Completion in April 2021
Building 2, Adderley 112 Adderley Street, West Melbourne Settled
Building 3, Mailhouse 5 Wominjeka Walk, West Melbourne Late March 2021
Building 4, Foundry 25 Wominjeka Walk, West Melbourne Settled
Building 5, Spencer 10 Wominjeka Walk, West Melbourne Late March 2021
Building 1, Adina 221 Rosslyn Street, West Melbourne End of November 2020

It is important that your finance application is well underway if required in order to complete the process in time for anticpated settlement in Late March. If you have not already started your finance process, you must contact your finance broker or lender immediately. if you have not appointed a broker and require assistance with your settlement please feel free to contact one of the West End recommended brokers below:

Simon Smith – eChoice 
0411 225 445 | simon@sshl.com.au

John Cassar – Invictus Finance Solutions
03 9486 7888 | 0414 449 414 | john@invictusfinance.com.au | www.invictusfinance.com.au

Vutha Thach – Comparo (Part of Auto Loans Group)
1300 301 051 | 0424 026 966 | Vutha.thach@comparo.com.au | www.comparo.com.au/

Jing Liang – BC Securities – Specialising in non-residents  
614 38 637 337 | Jliang@bcsecurities.com.au |  WeChat: Jing8629panda

Should you have any further questions about your settlement please feel free to contact myself or Charles (Mandarin).

Regards,

Tom Hawkins | Settlement Co-ordinator
P: +61 3 8582 8972
E: tom@settlement-solutions.com.au

Charles Liu | International Support
电话: +61 415 266 621 | 微信: pss90363383
邮箱: support@settlement-solutions.com.au

 

+ View More

For further enquiry or any issues, please contact:

Address: 1111 High Street Armadale VIC 3143
Email : georgie.lupson@marshallwhite.com.au
Phone : 03 9832 1197

X

X

Register for instant email alerts when a property matches your criteria.