1975

1975 Malvern Road
Malvern East
Builder:TBA
Project Manager:BHC Group
Anticipated Completion Date:Mid 2020
Expected Settlement:Mid 2020

Project Update

We are currently in the sales and marketing phase.

 Whilst sales are occurring the development team is in discussions with builders and banks to bring 1975 to life.

 Construction updates will be provided quarterly.

+ View More

232 Wattletree

232 Wattletree Road
Malvern
Builder:Cobild
Project Manager:Neoscape
Anticipated Completion Date:September 2019
Expected Settlement:September 2019

Project Update

We are pleased to provide the following update from the developer, Fortis Construction Group:

The removal of all formwork and propping has now been completed. You will see from the photo included that the steel framing to the upper level is now on the verge of completion. The stud wall set out has been completed to the Ground Floor, with commencement to Level 1 now underway.

The developer will continue to update you each month as well as provide you with important information regarding settlement arrangements as the building approaches completion. At this stage Cobild are still on schedule to complete construction in September 2019.

Fortis Development Group provides monthly eDM’s. Please contact us if you have not received this.

Regular videos and updates are also put on up the on Instagram story- follow @fortisdg and click on the “232 Wattletree” button www.instagram.com/fortisdg/.

 

+ View More

525 High

525 High Street
Prahran
Builder:Arc 3
Project Manager:Goldfields Group
Anticipated Completion Date:March 2019
Expected Settlement:Early 2019

Project Update

By now, your lender’s valuer should have contacted Erin to arrange your finance valuation for your new home. Additionally, if you haven’t already done so, please ensure you contact Erin to arrange your pre-settlement inspection.

We are pleased to advise that Tideways will be your Owners Corporation Manager. They will be in touch in the coming week with information relating to utility and service connections, the car stacker system and the coordination of moving into the building following settlement.

We advise that our builder Arc3 are advising the following completion dates:
Statement of Compliance — Mid-March
Occupancy Permit — Mid-March
Titles — Mid-Late March
Calling for Settlements — Late March

We have been contacted by a number of purchasers about arranging ‘immediate’ settlements post titles being issued, should you wish to request an earlier settlement, please advise Erin ASAP.

We look forward to meeting you onsite throughout March to view not only the impressive building, but also each of your stunning apartments.

Contact  Erin Moore from Goldfields with any Settlement enquiries:  erin@goldfieldsgroup.com.au P) 0401581933

 

 

+ View More

818 Caulfield Residences

818 Glenhuntly Road
Caulfield South
Builder:Cobild
Project Manager:TBA
Anticipated Completion Date:Early 2020
Expected Settlement:Early 2020

Project Update

We would like to take this opportunity to assure you that although you may not see activity on the site as yet, behind the scenes works are underway and progressing well. These works form part of the original 17 month timeframe provided in our last update, which include:

  • Finalisation of the Works Protection Notice
  • Final documentation for the Building Permit
  • Council approval for dewatering

Please rest assured that project financing is in place, Cobild are engaged on the project and we are moving forward with the 17 month timeline remaining the same.

We look forward to providing you with a further update in due course.

 

+ View More

Aintree Park

1432-1436 Malvern Rd
Glen Iris
Builder:Samssons Projects
Project Manager:TBA
Anticipated Completion Date:Early 2020
Expected Settlement:Early 2020

Project Update

We are currently in the sales and marketing phase.

Whilst sales are occurring the development team is in discussions with builders and banks to bring Aintree Park to life.

Construction updates will be provided quarterly.

Akora

5-7 Kooyong Road
Armadale
Builder:Ironside
Project Manager:Nash Management
Anticipated Completion Date:Mid-Late 2019
Expected Settlement:Mid-Late 2019

Project Update

A Word from the Project Team

If you have been past the site recently you will know that there has been some great progress with a substantial component of the structure already in place.

IRONSIDE have not let the Melbourne weather get in the way of progress so will take a well earned break over Christmas from this Friday. Works will recommence in middle of January.

The project team are still reviewing purchaser changes with pricing to be finalised shortly. We will expect pricing to be provide to the purchaser sometime in the new year. This is only in regard to request that were outside the purchasers contract. We appreciate your patience in regards to this matter.

Construction Progress

October through to December have seen excavation works completed and the commencement of the concrete structure.

Basement structure has been finished and a major milestone was accomplished last week when the ground floor slab was poured. It is an exciting time for everyone when you can start to see works above ground.

First floor slab will be poured shortly after construction commences in the new year.

 

+ View More

Allegra

1538 – 1540 High Street
Glen Iris
Builder:TBA
Project Manager:Nash Project Management
Anticipated Completion Date:Mid 2020
Expected Settlement:Mid 2020

Project Update

We are currently in the sales and marketing phase.

Whilst sales are occurring the development team is in discussions with builders and banks to bring Allegra to life.

Construction updates will be provided quarterly.

Altus

260 -262 Burwood Hwy
Burwood
Builder:Iurada Construction
Project Manager:BHC Property
Anticipated Completion Date:Late 2019
Expected Settlement:Late 2019

Project Update

The developer is pleased to provide you with the progress achieved on site so far:

Basement retention has been completed 100%. Concrete structure has been completed 33% and the first-floor slab will be poured in late Feb.

Currently anticipating a November / December 2019 completion time.

We will keep you posted as we progress through the next phase.

+ View More

Arcadian

511 Dandenong Road
Armadale
Builder:Charles Edgar
Project Manager:Samssons Projects
Anticipated Completion Date:Mid-late 2019
Expected Settlement:Mid-late 2019

Project Update

The developer has advised that it has been a busy and productive past few months on-site. The builder is working towards forming level 1 as per picture (attached) and hope it have it poured by the beginning of March.

Lock up should be around mid May, and completion is anticipated for Mid Oct 2019. The developer doesn’t anticipate any delays from all sides of the project.

Attached is a photo of the ramp and ground floor slab.

 

+ View More

Ashton Park

338 Burwood Hwy
Burwood
Builder:Iurada Construction
Project Manager:BHC Property
Anticipated Completion Date:Mid 2019
Expected Settlement:Mid 2019

Project Update

We are pleased to update you on the construction status for 338-340 Burwood Highway, Burwood.

Structural steel has now been completed 100%.
Windows have been installed 80%.
Hydraulic services have been completed 63%.
United energy statement of compliance has been received.

Due to the extreme weather, we are currently anticipating a May/June completion time.
We will keep you posted as we progress through the next phase

+ View More

Ballantyne

1693 – 1697 Malvern Road
Glen Iris
Builder:Citi-Con
Project Manager:Charter Keck Cramer
Anticipated Completion Date:Early 2019
Expected Settlement:Early 2019

Project Update

We acknowledge that the revised dates for completion provided over past correspondence may be causing inconvenience and frustration.

Unfortunately, the delays have been out of Waleta Groups control.

There have been a number hold ups at Council with receiving the Statement of Compliance, so that the Plan of Subdivision could progress to the Land Titles Office for registration.

The documents for The Ballantyne were passed internally at council to three different officers, due to their staff leave arrangements. Waleta Group is pushing council to have the documents reviewed and endorsed urgently.

As you can imagine, the developer would like to see the townhouses settled as soon as possible, whilst still ensuring that they are finished in the highest standard possible.

We hope to provide you with an updated anticipated completion date for both stages shortly.

In the meantime, please do not hesitate to contact Monique Maclean from Property Settlement Solutions on 03 8582 8972 or email monique@settlement-solutions.com.au.

+ View More

Balmoral

1571 Malvern Road
Glen Iris
Builder:Cobild
Project Manager:Neoscape
Anticipated Completion Date:September 2019
Expected Settlement:Mid-late 2019

Project Update

We are pleased to provide the following update from the developer on the progress of Balmoral at 1571-1573 Malvern Road, Glen Iris.

The removal of all formwork and propping has now been completed. You will see from the photo above that the steel framing to the upper level is now on the verge of completion. The stud wall set out has just commenced to the Ground Floor.

We will continue to provide monthly updates from the developer, as well as include important information regarding settlement arrangements as the building approaches completion. At this stage Cobild are still on schedule to complete construction in September 2019.

+ View More

Beckworth

184-186 Tooronga Road
Glen Iris
Builder:TBA
Project Manager:TBA
Anticipated Completion Date:Mid 2020
Expected Settlement:Mid 2020

Project Update

We are currently in the sales and marketing phase.

Whilst sales are occurring the development team is in discussions with builders and banks to bring The Beckworth to life.

Construction updates will be provided quarterly.

 

Bespoke

1394 Malvern Road
Glen Iris
Builder:Drive Construction
Project Manager:
Anticipated Completion Date:Late 2019
Expected Settlement:Late 2019

Project Update

We can now advise that the previously appointed builder had only recently informed our client of their inability to deliver your apartment within an acceptable time frame.

Rather than accept this, the developer has quickly recommenced the process of appointing a new builder to importantly assure you of delivering your apartment to you within the earliest possible time frame and without compromising quality.

A new builder’s appointment will be announced early next month and then construction is anticipated to recommence by May/June.

The developer would like to thank you in anticipation of your continued patience and has undertaken to provide us with further updates upon a new builders appointment.

 

+ View More

Bloom

1240 Glen Huntly Road
Carnegie
Builder:Nantong Construction
Project Manager:Sam Segman
Anticipated Completion Date:Q3 2019
Expected Settlement:Mid-late 2019

Project Update

Bloom Glenhuntly is pleased to report that construction on site is continuing to progress well with the structure now taking form.

Two basements are complete now and the team is working on finishing the Ground slab by the end of the month.
Plumbing, Electrical, Fire and Mechanical Services have started their works.

Installation of walls for the ground floor is planned for the month of March with all the panels ready for installation.

Blooms practical completion date is currently anticipated for September 2019 with Settlement expected shortly after.

+ View More

Botanical

16 Spring Road
Malvern
Builder:Hamilton Marino
Project Manager:
Anticipated Completion Date:Early-Mid 2020
Expected Settlement:Mid 2020

Project Update

We are currently in the sales and marketing phase.

 Whilst sales are occurring the development team is in discussions with builders and banks to bring the Botanical to life

 

Construction updates will be provided quarterly.

 

+ View More

Centenary Apartments

817-819 Centre Road
Bentleigh East
Builder:Valeo Construction
Project Manager:Valeo Construction
Anticipated Completion Date:January 2019
Expected Settlement:February 2019

Project Update

Valeo Construction is pleased to advise that the building has reached practical completion.

Please be advised that Titles have been registered & the Certificate of Occupancy obtained and settlement s due on the 14th February.

East End

20 Canterbury Road
Blackburn South
Builder:Carelli Construction
Project Manager:JPS Projects
Anticipated Completion Date:Mid- late 2019
Expected Settlement:Mid- late 2019

Project Update

The delivery of the East End Apartments is now well into the construction phase. Carelli Construction completed the basement works by the end of last year as planned. They are now focused on the construction of the basement lift shaft and the large ground level concrete slab. Once the ground level concrete slab is complete the next major mile stone will be to complete the above ground concrete and steel super structure.

The super structural is scheduled for completion just after Easter.
There still isn’t much to see yet because most of the work is underground, although below are a few pictures of the ground slab formwork and steel reinforcement. Looking forward as construction works continues, we will begin sending more pictures and news of the projects progress in our quarterly updates.

Anticipated date of Completion at this stage is on track for October 2019

+ View More

East Grove

2a Kenilworth Grove
Glen Iris
Builder:Cobild
Project Manager:Neoscape
Anticipated Completion Date:Early 2020
Expected Settlement:Early 2020

Project Update

We are pleased to provide the update from the Developer Fortis Construction Group within East Grove:

This week we had an extra special site visit to East Grove, where we celebrated turning of the soil with our award winning builder – Cobild. We were also joined by the teams at Ewert Leaf and Neoscape, Bulk excavation of the basement is now underway.

The developer will continue to send out monthly eDM’s, as well as provide important information about settlement arrangements. If you do not receive these please let us know.

+ View More

Eastbridge

833 High Street
Kew East
Builder:D5 Building Group
Project Manager:BHC Property
Anticipated Completion Date:Mid- late 2020
Expected Settlement:Mid-late 2020

Project Update

The appointed builder D5 Building Group has completed some sewer works at the rear of the property in preparation for the construction of the new townhouses.

Hoarding fence and temporary power to site is currently underway. There are a few authority and council approvals that are still pending approval before the builder can commence construction of the basement.

Majority of the purchaser changes are finally confirmed and already documented in the working drawings.

The project team is currently finalizing their building permit drawings and ensuring building codes compliances are met.

The developer is eager to get the construction underway as soon as possible.

Further updates to come in due course.

Practical completion is anticipated to be by third quarter of 2020.

+ View More

Emerald Grove

66 Stanley Rd
Keysborough
Builder:Fynnan Construction
Project Manager:N/A
Anticipated Completion Date:Late 2019
Expected Settlement:Late 2019

Project Update

Construction Commenced!

The developer is excited to announce that construction has started at Emerald Grove.
Civil work is ongoing underground and structural works will be starting soon.

Further updates to come in due course.

Form

21 Riversdale Road
Hawthorn
Builder:Cobild
Project Manager:Pax Project Management
Anticipated Completion Date:Mid- late 2019
Expected Settlement:Mid - late 2019

Project Update

2019 is off to a fantastic start on site at 21 Riversdale Road.
Our builders Cobild have officially topped out meaning key structural works are now complete.
A number of the external off-form concrete walls have been poured and are looking crisp. You will see this in the section above the carpark entry and also blade wall to the main entrance.

Furthermore, external glass doors to apartments have commenced installation as well as internal wall partition set outs are being placed and mechanical, electrical and hydraulic rough ins are well underway.
We have recently placed orders for our unique recycled timber from Just Eco and also the stunning stone from Signorino.
Our construction program is still tracking well with practical completion likely to be falling early October 2019.

+ View More

Hank

5-9 Hanke Road
Doncaster
Builder:Stemcom
Project Manager:Nash Management
Anticipated Completion Date:Early 2019
Expected Settlement:Early 2019

Project Update

UPS Settlement will be facilitating the Settlement and Valuation Inspection process.

Please inform your Finance representative to contact the Settlement Team ASAP to make an appointment for the valuation inspection if you have not done so already.

 To book in your Valuation Inspection your Bank will need to contact Amanda Wang on 0413 115 380 or via email: amanda@upssettlement.com.au 

Amanda is also overseeing the settlement process and any queries about this can be directed to her.

At this stage completion is on track with Settlement anticipated for early May.

 

 

 

+ View More

Hello

82 Hawdon Street
Heidleberg
Builder:Valeo Construction
Project Manager:
Anticipated Completion Date:Early 2019
Expected Settlement:Early 2019

Project Update

At this point in time, we are advised: that the builder Valeo are advising completion by end of March 2019. Accordingly, settlements should take place by end of April 2019.

Accordingly, rather than advise of a time at this stage, the Developer will advise and will notify all parties towards the above date and will reschedule appropriate inspection times with you.

He sincerely apologizes for this inconvenience, but assure you we will work with you and your valuers to facilitate your inspection.

Please email Ted Kirsh <retrohouse@bigpond.com> for any issues with this.

+ View More

Helm

300 Burwood Road
Hawthorn
Builder:Buildcept
Project Manager:TBA
Anticipated Completion Date:Early 2020
Expected Settlement:Early 2020

Project Update

Happy News!  We are very pleased to confirm that Buildcept have been formally engaged as the Builder for the HELM Apartments, and they have been on-site this week to finalise their Formal Planning in readiness for physical works to commence 9th January 2019.

Formal Planning has included designing and ordering of the tilt slabs, and final planning of the formal structure (e.g. Glass), so that everything will be in place for works to commence “full steam ahead” without delay.

Please do not hesitate to contact us with any questions you may have, and we wish you and yours a wonderful and safe Festive Season and New Year!

We look forward to providing you further HELM Construction updates in 2019.

Getting Ready for Settlement

If you are still investigating your finance options, we encourage you to contact Jarrod Hodges, Finance Manager at Hawthorn Finance, the multi-award winning lending and finance division of McLean Delmo Bentleys.

Jarrod will be able to assist you in every step of your finance application, doing the hard work for you to efficiently deliver tailored, cost-effective loan options to benefit you. Hawthorn Finance has strong networks and experience in dealing with over 30 different financiers, providing the purchasing power and Jarrod’s negotiating skills to enable you to obtain a better financial outcome than if you approached the banks of lending institutions directly.

Please contact Jarrod to discuss your financing options on jhodges@mcdb.com.au, or on his mobile, 0447 596 436.

+ View More

Highgreen

1457 High Street
Glen Iris
Builder:Ironside
Project Manager:VPP
Anticipated Completion Date:Mid 2020
Expected Settlement:Mid 2020

Project Update

Demolition is complete.

The pilling for the basement has been completed and the builder is currently doing bulk excavation for basement.

A further update will be provided direct to purchasers in due course.

It’s anticipated completion will be in the 2nd quarter of 2020.

 

 

+ View More

Hotham

99 Hotham Street
Balaclava
Builder:Paragon Development Group
Project Manager:Paragon Development Group
Anticipated Completion Date:Mid 2020
Expected Settlement:Mid 2020

Project Update

We are currently in the sales and marketing phase.

 Whilst sales are occurring the development team is in discussions with builders and banks to bring Hotham to life.

 Construction updates will be provided quarterly.

+ View More

Howard West

3-11 Howard Street
West Melbourne
Builder:Sinjen Pty Ltd
Project Manager:Pomeroy Pacific
Anticipated Completion Date:Early 2020
Expected Settlement:Early 2020

Project Update

The demolition works on site have been completed and temporary bracing of the apartment block has been completed. Excavation of the parking garage and car stacker pit has also been completed.

Footings for the car stacker have been poured and the plumbing rough‐in for this area have also been completed (comprising the stormwater retention and stacker drainage pits).

Due to the unseasonable rain events in December, the basement slab will be poured in January.

There is no change to the schedule from the July 2018 update and completion is targeted for January 2020. As progress continues, we will keep you informed of any improvements to the schedule.

 

Pics attached 1,2,3 explanations as follows:

  1. The demolition of the brick walls of the old office wings have all been
    completed. Temporary retention of the apartment building has been completed.
  2. The car stacker pit footings and stormwater pits have been completed.
  3. Ground and first floors have been demolished and ready for new slab.
+ View More

Jackson Street

11 Jackson Street
St Kilda
Builder:Cobild
Project Manager:James Beresford
Anticipated Completion Date:Mid 2019
Expected Settlement:Q3 2019

Project Update

The Jackson Street team are pleased to provide the following update in relation to the construction progress:

We are currently mid-way through framing, wall services and glazing installation on all apartment floors. Planter boxes are also underway and we are aiming to have the building closed up in the next month allowing for the completion of internal fit out works.

Jackson Street construction is still aimed for completion in Quarter 2, 2019.

Jackson Street settlement is scheduled for Quarter 3, 2019.

 

+ View More

Lawson

39 Lawson Street
Hawthorn East
Builder:D5 Building Group
Project Manager:BHC Property
Anticipated Completion Date:Early 2020
Expected Settlement:Early 2020

Project Update

We are excited to announce that construction has now commenced at Lawson with D5 Building Group. New photos attached to show the onsite progress.

We look forward to providing you further update in the coming months.

Lawson, March 2019

+ View More

Luar

22-24 Pakington Street
St Kilda
Builder:Drakk Constructions
Project Manager:David Parsons
Anticipated Completion Date:Early - mid 2020
Expected Settlement:Early - mid 2020

Project Update

The developer is pleased to advise that they have engaged Drakk Constructions to build Luar apartments.

Drakk are now preparing to mobilise and take control of the site.

In the meantime, demolition is programmed to commence in the next week or so. They are awaiting council approval of traffic management plans which is required before they can commence this work.

Demolition is expected to be completed within 2 months and construction to be complete Q3 next year.

We will further update this page in due course. Thanks for your patience.

+ View More

Malvern Residences

1186-1188 Malvern Rd
Malvern
Builder:Cobild
Project Manager:TBA
Anticipated Completion Date:Late 2019
Expected Settlement:Early 2020

Project Update

The developer would like to provide the purchasers with the following updates:

1.Construction-Cobild Construction

First Melbourne Developments (FMD) have been working with Cobild and its consultants for last three or so months on all Preliminary matters with respect to the Malvern Residences build.

As a matter of update as you can see by the photos attached that the site buildings have all been demolished leaving a clean site for construction works to commence .

2.Purchaser Change Requests

The developer have several purchasers that have requested changes during and subsequent to the sales campaign. These are currently being costed by  Cobild Construction.

These costings will then be distributed to the respective purchasers for their consideration. If required the purchaser, builder and FMD will meet to discuss these changes.

Update: Feb 21 2019 – Site works are commencing next week. We will provide further update then.

+ View More

McKinely Residences

171 Wattletree Road
Malvern
Builder:Ironside
Project Manager:Pomeroy Pacific
Anticipated Completion Date:Late 2019
Expected Settlement:Late 2019

Project Update

Construction for McKinley Residences is booming ahead. Ironside Construction has made significant process over the past few weeks and is confident that handover will be achieved by late 2019.

Recent site Works include:
• Ground floor and Level 1 fully formed up and concrete Slab 100% completed
• Construction of Level 2 walls and formwork has commenced
• Trade procurement is on schedule at approximately 60% complete

At this stage construction completion at McKinley Residences is anticipated to occur in Late 2019, with settlement to follow shortly thereafter.

If you have any queries in regards to settlement of your apartment, please do not hesitate to contact Bella Brown from Property Settlement Solutions on 03 8582 8979 or email bella@settlement-solutions.com.au

 

+ View More

Nelson St

Eden Sq, Garden Sq, Yarra Sq, Yarra Townhouse; 42-58 Nelson Street
Ringwood
Builder:Hamilton Marino
Project Manager:Sunstone
Anticipated Completion Date:Early 2019
Expected Settlement:Early 2019

Project Update

Works continue to progress well for the apartments and townhouses at Nelson Street.

Purchasers will soon receive notice about final inspections which they hope will commence from the 15th February onwards.

Further info on this to follow directly from the Settlement Coordinator.

After final inspections are complete, there are finishing works, a number of steps and documentation that needs to be processed with authorities.  Therefore we anticipate settlement to be in March but it is dependent on a number of factors.

We thank you for your patience and plan to update you again soon.

+ View More

Newman

2 Newman Ave
Carnegie
Builder:Steller
Project Manager:Steller
Anticipated Completion Date:End 2019
Expected Settlement:End 2019

Project Update

Feb 2019

Construction commenced late last year and completion is anticipated in the 2nd half of 2019

Further construction updates will be provided quarterly.

Oakdon

2a Scott Grove
Glen Iris
Builder:Liberty Builders
Project Manager:Locandro Group
Anticipated Completion Date:Mid 2019
Expected Settlement:Mid 2019

Project Update

The developer advises us that the construction continues to progress well and that there are regular photography updates on their instagram account @tas_oakdon.

A more formal update will be provided to purchasers during the month of March with regards to progress and in preparation for settlement.

If you have any issues and would like to speak with the Project Manager directly, please contact Anna Duong or Dominic Locandro on 9826 9908

+ View More

Olea

50 Kambrook Road
Caulfield North
Builder:TBA
Project Manager:BNG Group
Anticipated Completion Date:Mid 2020
Expected Settlement:Mid 2020

Project Update

We are currently in the sales and marketing phase.

 Whilst sales are occurring the development team is in discussions with builders and banks to bring Olea to life.

 Construction updates will be provided quarterly.

+ View More

Parkfield

88 Dunblane Rd
Noble Park
Builder:Saw Constructions
Project Manager:BHC Property
Anticipated Completion Date:End 2019
Expected Settlement:Late 2019

Project Update

The developer has advised us the following update:

Construction commenced in Oct 2018.

The builder has completed 90% of the earthworks, nearly 70% of the drainage works and 70% of the electricity mains.

We will continue to provide updates in due course.

 

Pelham

54 Wattletree Road
Armadale
Builder:Figurehead
Project Manager:Pax
Anticipated Completion Date:Mid-late 2019
Expected Settlement:Mid-late 2019

Project Update

We are pleased to pass on the developers latest Pelham settlement update:

Internally, the plaster works are now complete, and painting is underway. The joinery install has commenced, as well as the bathroom tiling.  Externally, the structure and roof have been completed, and the installation of the windows is well underway.  The brick installation has commenced as well as the timber soffit linings.

The target completion date remains on track for August 2019 with settlements shortly thereafter. We will provide more detailed timings as we move closer to completion.

We will continue to keep you up to date with progress over the forthcoming months.

Finance Arrangements:

With the banks making their assessment criteria far more onerous in recent times, unfortunately some loan approvals are taking much longer than they used to.

If you require finance, rather than trying to do it all alone, have a chat with one of the finance experts at Entourage Finance. They help you navigate the current lending market, not only finding you the best deal for your loan but ensuring your approval happens smoothly and well before your settlement.

Get in touch with Damien Roylance from Entourage Finance on 03 9421 1651 or email info@entourage.com.au.

 

Window Furnishings

Clearview Sun Control has been permitted exclusive pre-settlement access to Pelham in order to provide you with a window furnishing quote specific to your apartment.

Please refer to the attached quotation for your consideration.  Note that installation will occur after settlement.

Should you have any queries in relation to the quotation, please contact Clearview Sun Control directly on 03 9819 1144 or info@clearviewsuncontrol.com.au.

+ View More

Rostrevor Parade

97 Rostrevor Parade
Mont Albert North
Builder:TBA
Project Manager:TBA
Anticipated Completion Date:Mid 2020
Expected Settlement:Mid 2020

Project Update

We are currently in the sales and marketing phase.

 Whilst sales are occurring the development team is in discussions with builders and banks to bring Rostrevor Parade to life

 Construction updates will be provided quarterly.

+ View More

Royal Ascot

2 Mascoma Street
Ascot Vale
Builder:Marcus Group (A subsidiary of ABD Group)
Project Manager:Pomeroy Pacific
Anticipated Completion Date:Mid 2020
Expected Settlement:Mid 2020

Project Update

Works have started on site with the builder commencing site prep and the removal of contamination. The electrical substation works have been finally commissioned by Jemena. Over the coming weeks you will start to see the building activity ramp up as the builder fully mobilises to site.

McLaren Developments in conjunction with Pomeroy Pacific are committed to delivering Royal Ascot apartments for you and appreciate your continued patience as they push forward through the build.

Further updates will be provided in due course.

+ View More

Saint George

9-13 St Georges Avenue
Bentleigh East
Builder:Carelli Construction
Project Manager:
Anticipated Completion Date:Early 2019
Expected Settlement:Early 2019

Project Update

Construction at Saint George continues to progress well. Carelli Construction has now staged the Townhouses into front and rear groups – enabling greater efficiencies of trades on site.

At this stage completion is aiming for Q1 2019. All purchasers are able to email the dedicated project email addresses to receive further updates directly from Samuel Property: saintgeorge@samuel.com.au

+ View More

St James

1A Yarra St
Hawthorn
Builder:Marcus Group
Project Manager:TBA
Anticipated Completion Date:Q3 2020
Expected Settlement:Q3 2020

Project Update

We are currently in the sales and marketing phase.

Whilst sales are occurring the development team is in discussions with builders and banks to bring St James Park to life.

Construction updates will be provided quarterly.

The Anderson

791-795 Toorak Road
Hawthorn East
Builder:Cobild
Project Manager:Cobild
Anticipated Completion Date:Mid-late 2019
Expected Settlement:Mid-late 2019

Project Update

We are pleased to provide the following update for the Anderson;

  • Fit-out has commenced.
  • Structure is completed
  • Building is Weather Tight
  • Façade 50% complete
  • Scheduled completion on track Q4 2019

Please see picture included.

At this stage anticipated completion is August 2019.

+ View More

The Davis

1A Davis Avenue
Camberwell
Builder:D5 Building Group
Project Manager:BHC Property
Anticipated Completion Date:Mid-late 2019
Expected Settlement:Mid-late 2019

Project Update

As @ 28th Feb 2019 the developer advises that:

  • Electrical and plumbing roughing in at 90% complete.– Internal framing 95 % completed. Plastering to commence soon.

    – External cladding and rendering underway at 60%.

    – External ground works underway.

    – Window frames all in. Glazing installation to commence next week.

    – Lock up stage is anticipated to be achieved by end of March.

    With the current construction progress, practical completion is anticipated in July 2019 and settlement is anticipated to take place in August 2019.

    We look forward to providing you further update in the coming months.

Further updates here: http://www.bhcproperty.com/the-davis-dec-2018/

+ View More

The Kent

382 Burwood Rd
Hawthorn
Builder:Cobild
Project Manager:HS Consortium
Anticipated Completion Date:Early 2020
Expected Settlement:Early 2020

Project Update

Demolition has commenced on site, clearing the way for site and structural works to take place.

Below you will see some photos taken at the soil turning ceremony. This is the formal handing over of the site to Cobild.

At this stage construction completion at The Kent is anticipated to occur in March/April 2020, with settlement to follow shortly thereafter.

Further updates will be issued with more accurate information on settlement dates as we get closer to this time.

If you have any queries in regards to settlement of your residence, please do not hesitate to contact Monique Maclean from Property Settlement Solutions on 03 8582 8972 or email monique@settlement-solutions.com.au.

+ View More

The Porter

1375 Burke Road
Kew East
Builder:KPA Property
Project Manager:Cold Fusion Capital
Anticipated Completion Date:May 2019
Expected Settlement:May 2019

Project Update

The developer is pleased to advise that the concrete structure is now complete.
The construction of the final level has commenced and will be completed by the end of January.

The windows and facade installation has also begun and will be completed by mid-February.

The Construction team will be working hard in the New Year to reach completion in April 2019 and settlement commencement in early May 2019.

+ View More

The Regent

3 Whitehorse Road
Blackburn
Builder:Sycom Construction
Project Manager:TBA
Anticipated Completion Date:Late 2019
Expected Settlement:Late 2019

Project Update

The developer has provided us with the following update:

Civil works (the installation of the main sewer infrastructure to the site) at the Regent Townhouses development is almost complete. Although slower than originally anticipated (due to the difficulty in boring the 110 metres of main sewer line as well as delayed approvals from Yarra Valley Water), Adept Drainage are now in the process of finalising all sewer connections and are aiming to complete works by early March.

Our main Contractor (Sycom Constructions) is in detailed negotiations with all early works contractors to commence works. At this stage the early works building permit (which will include detailed excavation, the installation of all in ground services and the
preparation of all interconnecting roads in readiness for the townhouse construction) will be issued in late March.
Works on site will commence shortly thereafter in March 2019.

We will continue to provide construction updates over the life of the project.

+ View More

The Rise

179 Blackburn Road
Doncaster East
Builder:Cobild
Project Manager:Nash Management
Anticipated Completion Date:March 2019
Expected Settlement:April 2019

Project Update

We are advised by the developer that things are continuing to progress well.

At this stage completion of Rise is anticipated for late March and settlements in early April.

If you have further queries or concerns please do not hesitate to contact Bella Brown from Property Settlement Solutions on +613 8582 8979 or email bella@settlement-solutions.com.au

 

+ View More

The Royal

670-676 Glen Huntly Road
Caulfield South
Builder:Buildcept
Project Manager:TBA
Anticipated Completion Date:July 2019
Expected Settlement:July 2019

Project Update

With both basements form work and propping being stripped out, focus is now on construction of the apartments and retails space above ground.
Ground & First floor slabs have now been completed and preparation of structural columns & form work for second floor slab is well under way.

Level 3 slab has been poured and builders continue to make good progress.

BuildCept are well on track to achieving practical completion for July 2019.

Photos attached.

+ View More

Timeless

45 Orrong Road
Elsternwick
Builder:Cobild
Project Manager:Pax Project Management
Anticipated Completion Date:March 2019
Expected Settlement:March 2019

Project Update

The developer can’t wait for purchasers to call 45 Orrong Road home.

With settlement fast approaching, we have engaged the experts from “Settlement Solutions” to assist purchasers with the particulars surrounding the settlement process .We have used the SS team on previous projects and they are more than obliging to assist you with any query or request.

Settlement solutions should have been in touch with all purchasers so please contact Bella (below) if you haven’t heard anymore!

For any other Settlement enquiries please contact Bella Brown – Assistant Project Manager, +61 3 8582 8979 email: bella@settlement-solutions.com.au.

+ View More

Viola

390 Upper Heidelberg Road
Ivanhoe
Builder:JG King Projects
Project Manager:Nash Management
Anticipated Completion Date:Mid-late 2019
Expected Settlement:Mid-late 2019

Project Update

Over December and January, slabs were poured on the Southern boundary properties. This followed a period of screw pilling preparation during November/December. Preparation also begun on slab work for the Northern boundary lots. We anticipate these slabs will be finalised by mid-February.

During the same period, structural frame construction will begin on the Southern lots, where slabs have been poured. This will allow construction to continue at different stages on each side of the property.

By the next update, you can expect to see steel structural frames in place on some lots. This will make way for timber frame construction in preparation for door and window installation.

+ View More

Walpole

40 Walpole Street
Kew
Builder:Cobild
Project Manager:Hub Property Group
Anticipated Completion Date:Early 2019
Expected Settlement:Early 2019

Project Update

We are pleased to advise that we are expecting to be in receipt of the Occupancy Permit within the next week or so and that settlement will occur in mid-March.

FINANCE REMINDER

If you require finance to settle your townhouse and you haven’t already, we highly recommend that you contact your preferred lender to begin the approval process.

We are able to facilitate valuation inspections from this time on. Please contact Sophie Hensman at sophie@hubpg.com.au or on 0409 384 382 if you would like to arrange a valuation inspection.

Please note that no settlement extensions will be granted. Penalty interest will apply immediately for any settlements overdue and the Vendor reserves all its rights under the Contract of Sale to issue Default Notices.

PURCHASER INSPECTIONS

At this stage we anticipate that we will be able to facilitate purchaser inspections towards the end of the first week of March.

Inspections will be 30 minutes long and will be conducted between the hours of 8:30am and 3pm, we will commence booking appointments once settlement has been called.

MOVE IN INFORMATION

For any information regarding the move in process, please refer to this document, or get in touch with Project Manager, Sophie Hensman on 0409 384 382 or sophie@hubpg.com.au

+ View More

Westend (Adderly, The Foundry, Spencer, Mailhouse)

185 Rosslyn Street
West Melbourne
Builder:TBA
Project Manager:Urban
Anticipated Completion Date:Early 2020
Expected Settlement:Early 2020

Project Update

The developers advise that demolition is complete. Excavation and piling has officially commenced! It took longer than expected to obtain the building permit, however this has been achieved. Works are currently being undertaken by Nick and his team at LTE Excavations. It is a big job, spanning a block of nearly 1 hectare and comprising four separate apartment buildings and an on-site hotel, but everything is tracking well so far. With excavation now underway, all works are set to be completed in 2020, with Foundry and the Adina Hotel buildings to be completed first.

• Details of West End’s builder and terms have been agreed with West End’s Construction financier and once documentation has been finalised, an announcement will be made

Construction is starting to ramp up at West End as the first of 4 bright red coloured cranes is being erected.

+ View More

Windsor Terrace

168 High Street
Prahran
Builder:Balmain Construction
Project Manager:Hub Property Group
Anticipated Completion Date:May 2019
Expected Settlement:June 2019

Project Update

Construction is progressing well and is on track for completion mid-May with Settlement expected for June 2019.

For further enquiry or any issues, please contact:

Amy Bennison
Email : amy.bennison@marshallwhite.com.au
phone : 03 9832 1278

Please note our Concierge office hours are:

9.30 – 4.30pm on Tuesdays and Thursdays, and from
9.30 – 3pm on Fridays.

X

X

Register for instant email alerts when a property matches your criteria.