Project Update

Dear Purchasers

By now you’re hopefully aware that the construction climate has now returned to some form of a long awaited normalcy.

Builders can now fully understand the impact of the stage four lockdown and start to plan ahead with confidence in an attempt to make up for lost time . Not all projects however have been delayed so its important you track your own individual project through our Marshall White Projects  portal ensuring your best prepared for a pending settlement.

As always, our concierge service is available to you (on the hours below) to take your calls or email inquiry.

Mondays 11.00 a.m. – 3.30 p.m., Tuesdays 9.30 a.m. – 1.00 p.m. and Thursdays.11.00 a.m. – 4 .00 p.m.

We look forward to helping you into your exciting new apartment or townhome at an early date – thank you again for allowing us to be of service to your property needs.

+ View More

1975

1975 Malvern Road
Malvern East
Builder:First Construction
Project Manager:BHC Group
Anticipated Completion Date:Q3 2021
Anticipated Settlement:Q3 2021

Project Update

September, 2020

We are pleased to provide the below progress achieved on-site to date for 1975, Malvern East from the developer:

  • Underground electricals – 100% completed
  • Drainage – 90% completed
  • Concrete slab 30% completed
  • Framing to some of the townhouses is anticipated to commence in early Sept.

Project completion is anticipated to be achieved by October 2021.

We are pleased to attached photos taken from the site this week, showing the progress of the groundworks to date.

We shall keep you updated on progress in the coming months and look forward to sharing regular updates on your future home at each milestone reached.

+ View More

71 Station Street

71-73 Station Street
Fairfield
Builder:Halecorp
Project Manager:Codicote
Anticipated Completion Date:Q3 2021
Anticipated Settlement:Q3 2021

Project Update

October, 2020

Building permit has been held up with council, now waiting for surveyor stamp plans and almost good to go.

Hoping to start on site this month, vacant block is next door with the site office set up, piling next week.

They are anticipating a 14 month build time, so at this targeting Q1 2022 for completion.

Photos attached.

Further updates to come in due course from the developer.

+ View More

835

835 High Street
Armadale
Builder:Flux
Project Manager:TBC
Anticipated Completion Date:Q3 2021
Anticipated Settlement:Q3 2021

Project Update

December, 2020

We are pleased to pass on the following update from the developer regarding 835 High Street, Armadale:

We hope you and your family are well and are planning a well deserved break after a trying 2020.

We are very fortunate that the team at Flux have been relatively unhindered on site and have made huge progress over the last few months. Everything on site to date has been clinical, with the basement now completely excavated, shotcrete basement walls completed and the tower crane erected; now forming part of the Armadale skyline. Flux hope to have both the basement slab and first suspended slab (Basement 1) poured this year and early in the new year they will begin works on the upper levels, which is very exciting. We encourage you to drive past the site whenever you can, as the building will begin to take shape at a rapid rate.

The tower crane was commissioned last week and is already in full swing. Erecting the crane is a huge milestone for the project and we are happy to report everything went exactly according to plan.

We are in a great position coming into the new year and look forward to another very busy year on site.

We wish you and your family a happy holiday and we look forward to the next update in early 2021. Please feel free to get in touch should you have any queries.

+ View More

Aintree Park

1432-1436 Malvern Rd
Glen Iris
Builder:Samssons Projects
Project Manager:TBA
Anticipated Completion Date:April/ May 2021
Anticipated Settlement:April/ May 2021

Project Update

September, 2020

We are advised from the developer that anticipated completion date at this stage is on track for April/ May 2021.

Photos and further updates to come from the developer in due course.

Anderson Park

585 Burke Road
Hawthorn East
Builder:Ironside
Project Manager:Nash Project Management
Anticipated Completion Date:Q2 2021
Anticipated Settlement:Q2 2021

Project Update

December, 2020

Please find the below update for Anderson Park from the developer:

  • Structure Works fully completed
  • Crane now removed from site
  • Wall framing completed
  • Services rough-ins progressed right up to Level 3
  • Wall Sheeting commenced levels 1 & 2
  • Hard landscaping elements now commenced
  • Street level works now commencing

Works continue to progress on programme, and we remain on track for settlements ~ June 2021. We will provide further updates as we approach this time

 

+ View More

Ascot Place

9 Newsom Street
Ascot Vale
Builder:TBC
Project Manager:TBC
Anticipated Completion Date:2023
Anticipated Settlement:2023

Project Update

November 2020,

We are currently in the sales and marketing phase.

Whilst sales are occurring the development team is in discussions with builders and banks to bring Ascot Place to life.

Construction updates will be provided quarterly.

+ View More

Balwyn Park

7 Cherry Road
Balwyn
Builder:Cobild
Project Manager:M2mg
Anticipated Completion Date:Q3 2021
Anticipated Settlement:Q3 2021

Project Update

October, 2020

We pleased to pass on the below update from the developer:

Construction is underway –  there are no delays to the plan at this stage and progress continues on site.

A series of updated pictures are included and a further construction update to come.

+ View More

Beckworth

184-186 Tooronga Road
Glen Iris
Builder:Harris HMC
Project Manager:Point Polaris
Anticipated Completion Date:Q1 2021
Anticipated Settlement:Q1 2021

Project Update

September, 2020

Please find the latest update from the developer below:

Dear Purchasers,

We are pleased to advise that we have been powering ahead with construction in the last few months. We have noted the progress highlights below.

  • Retention & Structure – 100% complete
  • Windows – 100% installed
  • Services Rough In – 70% completed
  • Cladding – 70% competed

As you may be aware the Victorian Government have announced Covid – 19 stage 4 restrictions. Although construction activities fall under essential services, all construction projects must adhere to reduced workforce on site to continue construction activity. This means our builder has had to lower their workers to a maximum of 25% on site which will unfortunately slow down and delay the progress. Our builder and their subcontractors have been working incredibly hard and are doing everything they can to maintain work flow during these unprecedented times.

Due to the pandemic stage 4 restrictions, our expected completion date will be pushed to Q1 2021. Obviously, this all depends on further government regulations and how the covid-19 situation unfolds. We have been following all government advice and procedures to help ensure work continues steadily on site. We are working closely with our builder and providing maximum support to ensure the project will be completed in a timely manner with minimal delay. We will introduce you to our settlements team 3 months prior to practical completion and they will take you through the entire settlement process and help with settlement co-ordination.

We appreciate your patience and understanding during these challenging times and please be assured that we will endeavor to keep you updated as construction progresses.

I have also attached few site progress photos for your information – External and Basement.

Kind Regards,

Chris Yang

Project Development Coordinator

Point Polaris

L19, 390 St Kilda Road
Melbourne VIC 3004

P:  +61 3 8866 8888 | M: +61 430 068 166

E:  chris.yang@pointpolaris.com.au

W: www.pointpolaris.com.au

Further updates to come from the developer in due course.

+ View More

Bespoke

1394 Malvern Road
Glen Iris
Builder:Manresa Constructions
Project Manager:TBA
Anticipated Completion Date:Jan 2021
Anticipated Settlement:Jan 2021

Project Update

November, 2020

Due to the covid-19 restrictions,  Completion is likely be in January 2021.

KIN Property is the settlement coordinator for Bespoke Apartments and is in touch with purchasers directly.

If any purchasers have any settlement queries, please contact Netta via email at: bespokeapartments@kinproperty.com.au

 

+ View More

Bloom

1240 Glen Huntly Road
Carnegie
Builder:Nantong Construction
Project Manager:Conrock
Anticipated Completion Date:Late 2020
Anticipated Settlement:Late 2020

Project Update

October, 2020

We are pleased to pass on an update for Bloom; 1240 Glen Huntly Road, Carnegie.

Construction is progressing well onsite as you can see from the recent photos uploaded. The building now has a real presence and internal pics show the fit-outs of the kitchens and bathrooms. As has been previously advised, builders onsite are and taking precautions to work under safe conditions throughout Stage 4 of Covid-19, however this has of course slowed work in certain areas.

The developer has advised that a completion date is going to be further delayed, at this stage it is anticipated to be February/ March of 2021 with further updates to be provided from the developer as they progress.

For those who require additional information, the builder (Sam) is available on site to assist with most queries.

As previously advised we have ceased involvement with the Bloom development, with the exception of updates on our construction portal which we will continue to share with you here on the portal.

 

+ View More

Boston

16 Balwyn Ave
Balwyn
Builder:TBC
Project Manager:TBC
Anticipated Completion Date:Q4 2021
Anticipated Settlement:Q4 2021

Project Update

November, 2020

We are currently in the sales and marketing phase.

Whilst sales are occurring the development team is in discussions with builders and banks to bring Boston to life.

Construction updates will be provided quarterly.

+ View More

Botanical

16 Spring Road
Malvern
Builder:Hamilton Marino
Project Manager:Land Real
Anticipated Completion Date:November 2020
Anticipated Settlement:November/ December 2020

Project Update

November, 2020

The developer advises the following:

The most current estimate for completion of the apartment building is late November, settlement to follow soon after.

Chan will manage settlement queries and is best placed to be your point of contact. He can be reached via email at: CWickramaratne@landreal.com.au

+ View More

Broadway

630 Glen Huntly Road
Caulfield South
Builder:Holm Park
Project Manager:INPG
Anticipated Completion Date:Late 2021
Anticipated Settlement:Late 2021

Project Update

October, 2020

Holm Park Builders have been appointed. Developers are aiming to begin demolition in the coming months and construction will commence prior to Christmas.

Further updates and images to come from the developer in due course.

 

Carrington Hill

101 Carrington Road
Box Hill
Builder:D5
Project Manager:BHC Property
Anticipated Completion Date:Q3 2021
Anticipated Settlement:Q3 2021

Project Update

October, 2020

We are pleased to provide the progress achieved on-site to date for Carrington Hill.

Building C framing is now completed. Building A & B is pouring first level suspended slab. Our builder has developed a very robust Covid-Safe plan to ensure construction can continue to push forward during these harsh times.

We are expecting the practical completion for be Q3 2021 at this stage. We will provide further notice if this changes.

For more live updates, please visit our project management company Instagram https://www.instagram.com/skywardmanagement/

We will continue to provide you with regular construction updates leading up to settlement.

The developer will be in touch in due course with further updates.

 

+ View More

Central Park

2A Nyora Street
Malvern East
Builder:Figurehead
Project Manager:Pax Project Management
Anticipated Completion Date:March 2021
Anticipated Settlement:March 2021

Project Update

November, 2020

Despite stage four restrictions construction has continued steadily at Burke Road.  Figurehead builders have successfully navigated the tight government guidelines which limited the onsite workforce firstly to 25% and then 85%.  On a positive note, it is now business as usual with the site now able to operate at 100% original workforce capacity.

As you are aware COVID-19 restrictions have caused delays to the builder’s progress on site.  The good news is that Figurehead had been progressing well all year, so they were slightly ahead of programming before lockdown impacted. As we now gather momentum toward completion, Figurehead are still aiming for construction completion to occur in March 2021 with settlement to occur shortly after in late March 2021 or possibly shifting into April 2021.

As your apartment continues to take shape if you have had the chance to drive past Central Park you will have noticed the scaffolding is starting to come down and the beautiful facade is now exposed.  The timber soffit cladding to the balconies is now complete and the internal fit out is progressing well with tiling, stone, and joinery installation.  With the scaffold now being removed ground floor external works can now commence.  Next month sees the commencement of the installation of the beautiful timber flooring.

We will endeavour to share with you the latest updates on progress and provide accurate timelines as we move closer to completion.  As always timelines are indicative only due to the involvement of authorities outside of our control such as Stonnington Council, service authorities and the titles office.

Please look out for our next Central Park update in December. In the meantime, stay well and do not hesitate to contact the Settlement Team should you have any further queries.

Jackie Zandveld

Settlement Coordinator

T: 0438 812 800

E: customercare@roulston.com.au

+ View More

Contour

250 Wattletree Road
Malvern
Builder:TBC
Project Manager:TBA
Anticipated Completion Date:Q2 2022
Anticipated Settlement:Q2 2022

Project Update

November, 2020

Demolition work is complete on-site. Please see photos attached.

Further update and site pics to come in due course from the developers.

Custom

20 Station Street
Highett
Builder:TBC
Project Manager:TBC
Anticipated Completion Date:Q2 2022
Anticipated Settlement:Q2 2022

Project Update

November, 2020

We are currently in the sales and marketing phase.

Whilst sales are occurring the development team is in discussions with builders and banks to bring Custom to life.

Construction updates will be provided quarterly.

+ View More

Daracombe

369-371 Cotham Rd
Kew
Builder:Pulitano Commercial Construction
Project Manager:TBA
Anticipated Completion Date:March 2022
Anticipated Settlement:March 2022

Project Update

November, 2020

We are pleased to pass on that the builder has been appointed for Daracombe. Pulitano Commercial Construction will build your new homes.

The builders have advised that they have started pilling, the anticipated Project completion will be March 2022 at this stage.

Further news and construction updates to come from the developer in due course.

 

+ View More

East End Ringwood

30 Maroondah Highway
Ringwood
Builder:TBC
Project Manager:TBC
Anticipated Completion Date:Q1 2023
Anticipated Settlement:TBA

Project Update

October, 2020

We are currently in the sales and marketing phase.

Whilst sales are occurring the development team is in discussions with builders and banks to bring East End Ringwood to life.

Construction updates will be provided quarterly.

+ View More

East Village Prahran

283-289 High Street
Prahran
Builder:Method Constructions
Project Manager:Prince Corporation
Anticipated Completion Date:Mid 2021
Anticipated Settlement:Mid 2021

Project Update

November, 2020

Work slowed during stage 4 lockdown however our team was still able to continue on site. Method Constructions are confident that the lost time can be made up and at this stage we are still on track for a mid-2021 completion.

All basement retention works have been completed including piling and anchoring, the bulk excavation down to the bottom of the second basement has been completed and, the concrete has been poured for the lift core, and crane base.

Currently the civil and drainage works of the lower basement are being done, as seen in the attached photo.

 

+ View More

Eastbridge

833 High Street
Kew East
Builder:D5 Building Group
Project Manager:BHC Property
Anticipated Completion Date:November 2020
Anticipated Settlement:November 2020

Project Update

November, 2020

We are pleased to pass on the following update for Eastbridge:

James from the Skyward Settlement team will be in touch to co-ordinate bank finance valuations (if required), pre-settlement inspections and any other queries you may have to ensure smooth settlement.

An exact settlement date will not be known until the Plan of Subdivision has been registered with the Titles Office and the Certificate of Occupancy achieved, and settlement is called.

We appreciate your patience and understanding during these challenging times and please be assured that we will endeavor to keep you updated as construction progresses.

+ View More

Gardenia Park

8 Genista Avenue
Boronia
Builder:Batbuild
Project Manager:BHC Property
Anticipated Completion Date:April 2021
Anticipated Settlement:April 2021

Project Update

October, 2020

We are pleased to provide the progress achieved on-site to date for Gardenia Park.

– Framing, 90% completed
– Plumbing/Drainage, 60% completed
– Roofing, 30% completed
– Brickwork have commenced

Completion is currently forecasted to be by late May 2021, however due to Stage 4 restrictions, this could be extended further.
We will monitor the situation and report on the programme impacts once they become known.

We will keep everyone updated and thankyou for your patience.

+ View More

Glenarm Square

1 Glenarm Road
Glen Iris
Builder:Hamilton Marino
Project Manager:TBC
Anticipated Completion Date:December 2021
Anticipated Settlement:December 2021

Project Update

November, 2020

Builder Hamilton Marino will continue with the next phase of works on site later this month. Given the current government-imposed restrictions on construction sites we are working closely with our consultants to ensure we move forward with progress onsite as efficiently as possible.

The project team look forward to continuing to provide updates to purchasers in due course. We hope everyone is staying safe and well.

Should you have any queries in the interim, please contact our sales manager, Brett Hallam:

0418 318 283
bhallam@dealcorp.com.au

 

 

+ View More

Greenwell

597 Burke Road
Camberwell
Builder:Creation Homes
Project Manager:Pomeroy Pacific
Anticipated Completion Date:Late 2021
Anticipated Settlement:Late 2021

Project Update

November, 2020

We are pleased to pass on the following update from the developer below:

  • Suspended deck formwork has been 95% erected
  • Service penetrations are underway
  • Top steel going in early next week
  • Concrete pour is scheduled for Thursday

Further updates to come in due course.

 

+ View More

Hazel Hawthorn

368 Burwood Road
Hawthorn
Builder:TBC
Project Manager:TBC
Anticipated Completion Date:Mid 2022
Anticipated Settlement:Mid 2022

Project Update

November, 2020

We are currently in the sales and marketing phase.

Whilst sales are occurring the development team is in discussions with builders and banks to bring Hazel Hawthorn to life.

Construction updates will be provided quarterly.

+ View More

Helm

300 Burwood Road
Hawthorn
Builder:FourSquare
Project Manager:TBA
Anticipated Completion Date:Jan 2021
Anticipated Settlement:Feb 2021

Project Update

November, 2020

Please find the latest update below from the developer:

Lockdown has finally lifted and, with construction well and truly underway again, we have had FourSQ determine in more detail how the Lockdown has affected their completion schedule.  We are now in a position to be able to give you some more accurate updates to the timing for Completion and Settlement for the Apartments.

With the major Construction on the Apartments now essentially complete, so that only internal finishing touches and appliances, and work on external patios and balconies is still needing to be finalised on the Residences themselves, should you require a Valuation Inspection to be done as part of your Lending Institution’s requirements, now is the time to be talking with your Lender and getting these booked in.

Please contact Danielle at our office to provide your Lender’s Contact Details so that these Valuation Inspections can be co-ordinated between the timeframe of 7 – 19th December 2020.  Should your Lender require the Inspection to be done sooner, please get in touch with us and we will do our utmost to accommodate these requests.

At this point, we anticipate being able to welcome all Purchasers for your own personal inspections of your respective Apartment in the week of 23 – 30th January 2021, with Settlement then likely to take place around the first-second week of February 2021.

Please do not hesitate to contact Danielle if you have any questions. Danielle Stukenborg ‎[DStukenborg@mcdb.com.au]‎

 

+ View More

Highmont

3 James Street
Bayswater
Builder:TBC
Project Manager:TBC
Anticipated Completion Date:Q4 2021
Anticipated Settlement:Q4 2021

Project Update

November, 2020

The Developer has advised that a builder has been appointed,  D5 Building Group, please click link and check out their completed and in progress projects. https://d5build.com.au/

Demolition is now pending based on the councils permit.

Further updates to be provided by the developer in due course.

+ View More

Hotham

99 Hotham Street
Balaclava
Builder:Paragon Development Group
Project Manager:Paragon Development Group
Anticipated Completion Date:Early - Mid 2021
Anticipated Settlement:Early - Mid 2021

Project Update

November, 2020

Progress is continuing at a promising rate on site at 99 Hotham Street.

Current anticipated completion is mid 2021.

Further updates to come from the developer in due course.

Hudson Green

6 Hudson Street
Caulfield North
Builder:Shustin
Project Manager:Shustin
Anticipated Completion Date:Q4 2020
Anticipated Settlement:Q4 2020

Project Update

December, 2020

Please find attached the update from the developer:

2020 has been a trying year for all of us, but despite all the challenges we have been able to continue to focus on completing Hudson Green to the highest level of craftsmanship.

With joinery nearly complete, internal fitments are progressing well and it is starting to feel more and more like home.

External works are taking huge strides, with tiling and fencing complete, we will be starting landscaping in the coming weeks. The front façade is coming along with the hope to complete all common area works over the next month.

On site works are completed to have all utilities connected with connections to take place within next few weeks. We are aware that all major utility companies are overwhelmed by post COVID lockdown demand for new connections, but we remain optimistic to achieve our targets.

Interior construction: We are progressing with submission of required documentation to have the Plan of Subdivision approved by the relevant authority and will be hoping to avoid any lengthy delays due to the backlog of applications currently experienced by all local councils.

If you have any queries please do not hesitate to contact us on 9530 6800
or via email info@shustin.com

Photos included show the progress of the site.

Should you have any queries please contact us on 9530 6800 or info@shustin.com

 

+ View More

Hurstmon

3 Hurstmon Street
Malvern East
Builder:TBC
Project Manager:TBC
Anticipated Completion Date:Q4 2021
Anticipated Settlement:Q4 2021

Project Update

November, 2020

We are currently in the sales and marketing phase.

Whilst sales are occurring the development team is in discussions with builders and banks to bring Hurstmon to life.

Construction updates will be provided quarterly.

+ View More

Lothian Street

141 Arden Street
North Melbourne
Builder:Bear Projects
Project Manager:Exelon Projects
Anticipated Completion Date:November 2020
Anticipated Settlement:November 2020

Project Update

November, 2020

Progress continues well at Lothian Street. Developers update below. Please note our builder has updated their expected completion date to mid December. This is related to authority approvals that have taken longer than expected

We are now expecting to call for settlement around early December, and expect inspections for purchasers to occur in the 2 weeks following call for settlement and settlement of the property. We will be in touch to arrange these inspections with you shortly, and will update you if these expectation change

As of 23rd November, our builder has advised us that valuation inspections will be delayed until later next week, and the week following (unit dependent)

Excelon has been in touch with valuation teams and will continue to update them as requested in line with this updated timeframe

We will continue to keep you informed about the progress.

Settlement will be managed by Luke Melican who can be contacted on 0448 745 544 with any queries.

+ View More

Luar

22-24 Pakington Street
St Kilda
Builder:Drakk Constructions
Project Manager:David Parsons
Anticipated Completion Date:Q2 2021
Anticipated Settlement:Q2 2021

Project Update

October, 2020

The developers have provided us with the following update:

Now that we have resolved the difficult issues associated with ground water and contamination, we are making very good progress.  We have now poured the two basement level slabs plus half of the ground floor in less than two months. We are already preparing the rear of the first floor for pouring as we finish the complex form work associated with the front of the ground level.

From here on, we are looking at pouring half a level every two weeks, with structure complete by Christmas and completion mid year 2021, subject of course to weather, Covid and other unknowns.

Photos attached- 1: Forming up the rear pour, level 1, 2: Completing the complex form work at the front of the Ground floor and 3: Apartment courtyards starting to take shape. Further updates to come in due course.

+ View More

Luminess

27 Russell Street
Essendon
Builder:TBC
Project Manager:TBC
Anticipated Completion Date:Q4 2021
Anticipated Settlement:Q4 2021

Project Update

September, 2020

We have been provided the following update from the developer:

I am pleased to advise after spending a protracted amount of time with council to meet some new legislation around parking requirements, we now have our plan endorsed.

We have also appointed a builder on an early works contract and have all our building permits in place.

You will see some early work over the next month, with construction commencing in earnest in the next 8 weeks.

Obviously this is assuming that the government restrictions relating to Covid19 do not further impact our program.

Should you have any further concerns, you can contact Lee, Development manager on lee@urbanpropertyfinance.com.au or call 0418 555 265

+ View More

Melfort

496 Glenferrie Road
Hawthorn
Builder:Pulitano Commercial Construction
Project Manager:HS Consortium
Anticipated Completion Date:Q2 2021
Anticipated Settlement:Q2 2021

Project Update

November, 2020

Pulitano has commenced construction and progress continues well onsite.  Their program is for a completion in July 2021.

We will keep you advised following the builder’s assessment of any potential delays.

Further update to come from the developer in due course.

 

+ View More

Olea

50 Kambrook Road
Caulfield North
Builder:Balmain & Co
Project Manager:BNG Group
Anticipated Completion Date:Late 2021
Anticipated Settlement:Late 2021

Project Update

November, 2020

We are pleased to pass on the following update from the OLEA group:

The Project of the Olea Residences (44-54 Kambrook Rd, Caulfield North) is currently under construction. The anticipated completion date is the end of 2021.

As previously advised Marshall White Projects is no longer the sales agent for OLEA however the project will however remain on our construction portal with quarterly updates and some site photos supplied by BNG group.

Please see latest photos attached.

In the interim, we invite you to communicate BNG group on 1300 853 761 and ask to speak to Dina or email: Oleasales@bng.group for additional information.

 

+ View More

Parq

134-138 McKinnon Road
McKinnon
Builder:Fynnan Construction
Project Manager:Oxford Developments
Anticipated Completion Date:Mid 2021
Anticipated Settlement:Mid 2021

Project Update

November, 2020

We are pleased to advise that progress continues well on site.

Further info and updates to come in due course.

Profile

1443 Dandenong Rd
Malvern East
Builder:Goldfields
Project Manager:M2
Anticipated Completion Date:July 2021
Anticipated Settlement:August 2021

Project Update

December, 2020

We are pleased to pass on the following update from the builder:

  • Ground floor slab completed
  • Level 1 concrete slab completed
  • Level 2 concrete slab competed
  • Level 3 formwork in progress, 90% completed
  • Level 3 concrete slab pouring on 4/12/20
  • On schedule and operating in covid safety plan environment

We are advised that the developer is anticipating July- Aug 2021 Practical Completion.

+ View More

Rose & Bird

30 Rosamond Rd
Maribyrnong
Builder:Creation Homes
Project Manager:Metro Property Management
Anticipated Completion Date:Early - Mid 2021
Anticipated Settlement:Early - Mid 2021

Project Update

August, 2020

The team at Metro Property Development are excited to provide you with the following update:

Whilst we are all continuing to live with a number of restrictions on our daily lives, construction sites have remained open and civil works are now complete with housing construction now well under way.

At this stage our construction program has not been impacted by COVID restrictions and we expect homes to be ready to settle progressively from early 2021 to late 2021.

As you would appreciate, our construction program and expected settlement dates may be impacted by future work restrictions; however we will endeavour to keep you updated as construction progresses.

We will introduce you to our settlements team over the coming months who will take you through the settlement process and provide you with all the necessary information required to take possession of your new home.

Construction updates will be provided quarterly.

+ View More

St James Park

1A Yarra St
Hawthorn
Builder:Marcus Group
Project Manager:TBA
Anticipated Completion Date:Q1 2021
Anticipated Settlement:Q1 2021

Project Update

September, 2020

The Victorian government introduced on 2 August 2020 stage 4 Covid restrictions, which have reduced the workforce permitted on site down to 25% of the prior level and limited production of on-site materials.

Construction work is continuing, with the builder rescheduling the various trades to get the most efficient progress possible in the circumstances. The stage 4 restrictions are meant to apply until 13 September 2020, but this date may change. It is therefore too early to assess the full impact on our delivery program of the restrictions, but completion within the first quarter 2021 is still being targeted.

General Onsite Status Update

Construction at St. James Park had been progressing well before the government restrictions with the builder on schedule. The crane has been dismantled and removed from site, with fill in work commenced.

Solar panels have been installed on the rooftop and installation of windows throughout the development is almost complete.

Internal spaces are shaping up well, with wall set-outs complete, and all electrical rough-ins complete for all cavities and ceiling spaces.

Furthermore, the finalisation of plaster board walls and painting is well underway and joinery installation has commenced within several lower level apartments.

 
+ View More

Surrey Gardens

288 Canterbury Road
Surrey Hills
Builder:Stosius Constructions
Project Manager:Nicky Keating
Anticipated Completion Date:Feb 2021
Anticipated Settlement:Feb 2021

Project Update

November 2020,

Construction work is progressing on site at Surrey Gardens, within the COVID-19 guidelines. We are currently able to have a more contractors on site with the slight easing of restrictions.

We anticipate completion around February 2021. However, this date may vary with the ever changing government restrictions.

Please contact Nicky Keating for any valuation inspection bookings on 0412 646 375

+ View More

Tailor

481-491 Victoria St
West Melbourne
Builder:Manresa Constructions
Project Manager:TBA
Anticipated Completion Date:August 2021
Anticipated Settlement:August 2021

Project Update

September, 2020

We wish to pass on the following update from the developer:

We are well under way, lower level walls constructed and floor slabs complete, ground floor slab also poured.
Expecting to start frame stage at the end of this month.
Expected completion date August 2021. Total days lost to covid so far is 7 so we have not been affected much.

We will probably lose another 3 over the next 4 weeks but we are going very very well considering.

See attached, ground floor formwork and steel as well as lower ground shots.

Construction updates will be provided quarterly.

+ View More

Ten to Twelve

10- 12 Lindsay Street
Brighton
Builder:Cobild
Project Manager:Hub PG
Anticipated Completion Date:Late 2021
Anticipated Settlement:Late 2021

Project Update

October, 2020

The developers advise us that they are now commencing preliminary works and have some movement happening onsite. They are working towards a 15 month construction process and anticipate completion at this stage for late 2021.

Photos and thorough update to come from the developer later this month once the impact of stage 4 restrictions have been fully realised.

 

+ View More

Timeless

555 Burke Road
Camberwell
Builder:Balmain & Co
Project Manager:J2 Projects
Anticipated Completion Date:December 2021
Anticipated Settlement:December 2021

Project Update

November, 2020

We are pleased to advise and pass on to our purchasers that a builder has been appointed at Timeless, that is Balmain & Co.

Further updates and news to come in due course from the developer.

Verse

18 -28 Wilkinson Road
Sunshine
Builder:Rise Constructions
Project Manager:Paragon Development Group
Anticipated Completion Date:Q2 2021
Anticipated Settlement:Q2 2021

Project Update

October, 2020

Anytime lost has been absorbed and we are advised that the construction remains on track for Q2 2021 settlement.

We will provide a further update in due course.

Wattle on the Park

2 Wattle Grove
McKinnon
Builder:Arch 10
Project Manager:KBMV
Anticipated Completion Date:Mid- Late 2021
Anticipated Settlement:Mid- Late 2021

Project Update

October, 2020

We have been advised that the builder is mobilising all trades and getting final permits in place, with the plan they will be on-site first week  of next month.

Thankyou for your patience and we will pass any further update on as we are provided it.

 

 

 

+ View More

Westend (Adderly, The Foundry, Spencer, Mailhouse)

185 Rosslyn Street
West Melbourne
Builder:Hacer
Project Manager:Urban
Anticipated Completion Date:Mid-Dec 2020
Anticipated Settlement:Mid-Dec 2020

Project Update

October, 2020

We have been provided the following update from the developer:

I am sure our settlement manager Property Settlement Solutions has been in contact with you over the past few months regarding the formal process associated with managing the settlement of your apartment.

In any case, I wanted to provide a more casual update to keep you informed about West End and other matters.

As I write this update, COVID cases in Victoria are dropping considerably ( I hope this continues of course) and property inspections are now permitted thereby making the settlement process so much easier and clearer for us all.

It seems we are well underway to a COVID normal and predominantly restriction-free December and thereafter. This means we will most likely be able to enjoy the use of the 3 West End pools including a 25-meter lap pool, plunge, and spa pool, the large 1500 square meters of private resident gardens including a meditation and reflection garden incorporating water features and a beautifully landscaped public park.

I am also pleased to report that the final steps in preparing titles for settlement are now well underway. So again, please ready yourselves!

In keeping with the Melbourne City Council requirements to reflect our indigenous culture in all-new addresses, we are pleased to advise that the arcade and public park will be named using “Wominjeka” which is a local Aboriginal word to mean “Welcome”

Wominjeka pronounced “Woe – min – gee – kar” equals WELCOME

Your new address and proposed settlement dates are listed as follows:

Building/Location New Address Approved by Melbourne City Council Proposed Settlement Date
The Main Arcade Wominjeka Avenue Due for Completion in February 2021
The Public Park West End Square Due for Completion in February 2021
Building 2, Adderley 112 Adderley Street, West Melbourne Early December 2020
Building 3, Mailhouse 5 Wominjeka Walk, West Melbourne Early March 2021
Building 4, Foundry 25 Wominjeka Walk, West Melbourne Early December 2020
Building 5, Spencer 10 Wominjeka Walk, West Melbourne Early March 2021
Building 1, Adina 221 Rosslyn Street, West Melbourne End of November 2020

NB: As of 14th October 2020: The Foundry, West End.

We are pleased to advise you that your apartment will be ready for a bank valuation inspection from the 22nd of October.

If you require finance to settle your apartment your lender may require a bank valuation inspection to be carried out in order to complete the loan application.

Valuers must contact Tom Hawkins on 03 8582 8972 or email tom@settlement-solutions.com.au to make an appointment.

Tom Hawkins | Settlement Co-ordinator
P: +61 3 8582 8972
E: tom@settlement-solutions.com.au
Charles Liu | International Support
电话: +61 415 266 621 | 微信: pss90363383
邮箱: support@settlement-solutions.com.au

 

+ View More

For further enquiry or any issues, please contact:

Amy Bennison
Email : amy.bennison@marshallwhite.com.au
phone : 03 9832 1278

Please note our Concierge office hours are:

9.30 – 4.30pm on Tuesdays and Thursdays, and from
9.30 – 3pm on Mondays.

X

X

Register for instant email alerts when a property matches your criteria.