August, 2019

Scaffolding has been removed on Royal Parade and we are looking forward to the removal of the scaffolding on Glen Huntly Road shortly.

We have been advised earlier this week that Buildcept has experienced delays with receiving the joinery from the cabinet makers.

Unfortunately, due to the delays of joinery this has resulted in a further delay in practical completion.

Practical Completion is anticipated to occur Mid- late September.

Settlement will occur Once Titles have been registered with the Land Titles Office and the Occupancy Certificate has been issued.

Further communications will be sent to you in the coming weeks announcing when Valuation and Pre-Settlement Inspections are able to commence.

If you have any other questions, please do not hesitate to contact the Settlement Team using details below.