May, 2019

The developer has provided us with the following update:

The site sewer infrastructure upgrade works are now on track to be completed by mid-May 2019 with the civil earthworks package (in ground services and roads) due to commence shortly after.

Under ideal weather conditions the civil construction period is estimated to take 6-8 weeks, commencing with site clearing and bulk earthworks followed by benching of the townhouses.

In addition, the retaining wall along the northern boundary will be constructed during phase by the civil contractor. Lot servicing infrastructure works to each stage will then begin.

We will continue to provide construction updates over the life of the project.